Title: Simulation
1 2Historical Background
- Prior to 1992, the Forest Service provided for a
a post-decision administrative appeals process
for most agency decisions - In March of 1992, the Forest Service proposed a
new regulation that would have eliminated
post-decision administrative appeals for all
proposed projects where an Environmental
Assessment resulted in a finding of no
significant impact
3- In response, Congress enacted the Appeals Reform
Act which required the Forest Service to
establish an administrative appeals process with
opportunity for notice and comment - 36 C.F.R. 215.12(f)
- Categorically exempts from notice, comment and
appeal Forest Service actions that do not require
an EA or and EIS under NEPA
4- In June of 2003, the Forest Service implemented
the National Environmental Policy Act
Determination needed for Fire Management
Activities (Fire CE) - Created a new categorical exclusion for
- fire rehabilitation activities on less than 4,200
acres - Salvage timber sales of 250 acres or less
5- September 8, 2003 the Forest Service approved
Burnt Ridge Project allowing for the sale and
treatment of 238 acres of post-fire forest area
in the Sequoia National Forest in California - Forest Service claimed that under the Fire CE the
project was categorically excluded from
requirements of documentation in an EA or EIS,
and thereby excluded from administrative appeal
6Earth Islands Claim
- They were unable to appeal the timber sale in the
decision memo because the Forest Service had
categorically excluded the project from a post
judgment appeal - The plain language of the ARA requires an
administrative appeals process
7Forest Service Claim
- Categorical exclusions are a result of the
Secretary's reasonable construction of the
statute to distinguish between agency actions
requiring an EA or EIS and projects that lack
significant individual or cumulative
environmental impacts
8Applicable Law
- ARA 322
- Required the Forest Service to establish an
administrative appeals process with opportunity
for notice and comment - NEPA
- Requires that an EA and an EIS must be conducted
for any federal action that would have
significant effects on the Environment - APA and Chevron
- Hard look at agency regulations.
- Courts must examine the statute itself to
determine whether Congress has spoken directly to
the precise question - If the statute is silent or ambiguous with
respect to the specific issue, the question for
the court is whether the agencys answer is based
on a permissible construction of the statute
9Earth Island v. Ruthenbeck
- Court holds that categorical exclusions which
exempt Forest Service actions that do not require
an EA or an EIS under NEPA from notice, comment
and appeal procedures conflict with the plain
language of ARA 322 - The (ARA) does not provide for any exclusions or
exemptions from its requirement that the Forest
Service provide an administrative appeal for
decisions implementing Forest Plans - Invalidates Forest Services categorically
excluded actions from administrative appeal under
36 C.F.R. 215.12(f)
10Implications
- Federal Agencies now must subject most agency
actions to notice, comment and appeal regardless
of categorical exclusions - Federal Agencies can not use the NEPA standards
to circumvent the administrative appeals process - More paper and more opportunity for public
involvment
11Question 1
- Is the approach of 'categorial exclusions' a
reasonable (legally) way to reduce the cost of
making decisions and the time needed to make
them? If so, why? If not, why not?
12Categorical Exclusions
- The Forest Service could use categorical
exclusions. - Exclude some decisions and actions that are
environmentally insignificant from an EA or EIS. - NEPA only requires an EA or EIS for major Federal
actions significantly affecting the quality of
the human environment
13Categorical Exclusions
- But cannot exclude those decisions and actions
from an appeal. - The ARA strictly forbids this.
- The Earth Island case held that the Forest
Service must promulgate regulations that
preserve administrative appeals for any decisions
subject to administrative appeal before the
proposed changes - Before 1992 an appeal was available for decision
memos, "decision notices," and "records of
decision.
14Reducing Cost
- How can this reduce the cost of making decisions
and the time needed to make them? - an EA or an EIS takes time, money, and man power
- Forest Service has a limited amount of resources
- Categorical exclusions could cut done on these
costs - If a decision or action in minor in area, time,
and potential environmental impact, there is no
need for an EA or EIS.
15Problem
- An decision may be minor to the Forest Service,
but important individuals or environmental
groups. - For example, the Forest Service could propose to
cut down one quarter of the trees around a small
remote lake. - environmentally insignificant no need for an
EIS - but what if someone goes camping there?
- That person may appeal the Forest Services
decision and lead to a costly law suit
16- When deciding what is categorically excluded from
an EA or EIS, the Forest Service may want to
consider what decisions might be appealed. - Should do an EA or EIS for a decision that
potentially could result in a costly appeal
17NEPA Lawsuits
- actually generates a relatively small volume of
litigation. - Out of approximately 50,000 EAs each year, plus
another 500 draft, final and supplemental EISs
for the much smaller number of major federal
actions, - aggrieved parties typically file about 100 NEPA
lawsuits per year, representing only 0.2 of the
actions generating NEPA documents annually.47 - only a few of these suits result in court orders
blocking government action. - preliminary injunctive relief was granted in NEPA
cases only 21 times in 2001 and 2002, and - permanent injunctions were issued only 28 times
(often, presumably, in the same case in which
preliminary injunctive relief had been granted). - courts ordered a remand of certain issues to the
federal agency in 33 cases in those two years. - courts ruled for the defendant agencies 114 times
during this period, - and dismissed NEPA cases (in some cases after a
settlement) in another 139 cases.
18Question 2
- If you were a general counsel to the Forest
Service, how would you advise decision makers
when they are making the critical significant
effects decision regarding the need for an EA or
EIS? What legal principles would inform your
judgment?
19Significant Effects
- Section 102(2)(C) of NEPA requires an EIS for
"major Federal actions significantly affecting
the quality of the human environment." 42 U.S.C.
4332(2)(C) (1982) - To show that a proposal will significantly affect
the human environment, plaintiffs must show a
proposed project may significantly degrade some
human environmental factor. Plaintiffs need not
show that the action will significantly affect
the environment - This is a broad definition that leaves agencies
with a lot of discretion. - Agencies are given considerable discretion in
defining the scope of an EIS however, they still
must consider connected actions in a single EIS
where the actions collectively produce an
environmentally significant impact, but when
looked at individually produce a finding of no
significant impact (FONSI).
20Council on Environmental Quality (CEQ) regulations
- Connected actions
- The CEQ regulations require "connected actions"
to be considered together in a single EIS. - "Connected actions" are defined as actions that
- (i) Automatically trigger other actions which may
require environmental impact statements. - (ii) Cannot or will not proceed unless other
actions are taken previously or simultaneously. - (iii) Are interdependent parts of a larger action
and depend on the larger action for their
justification. - Cumulative Actions
- The CEQ regulations also require that "cumulative
actions" be considered together in a single EIS.
40 C.F.R 1508.25(a)(2). "Cumulative actions"
are defined as actions "which when viewed with
other proposed actions have cumulatively
significant impacts.
21Thomas v. Peterson
- Where agency actions are sufficiently related so
as to be "connected" within the meaning of the
CEQ regulations, the agency may not escape
compliance with the regulations by proceeding
with one action while characterizing the others
as remote or speculative
22NEPA and Categorical Exclusions
- NEPA requires agencies to prepare Environmental
Assessments (EAs) to help them determine whether
proposed actions will have significant impacts
warranting preparation of an Environmental Impact
Statement (EIS) - Minor federal actions that have not been found to
have significant effects, either individual or
cumulatively, are excluded from this process. - These minor federal actions do not require
Environmental Assessments (EA), Environmental
Impact Statements (EIS) analysis under NEPA.
23New Forest Service Regulations
- December 23, 2005 New Planning Regulations from
the Forest Service - Regulations rely upon an Environmental
Management System for decision making - 2005 Regulations exempt Forest Plans from EIS
requirement based upon Ohio Forestry that did not
allow review of programmatic decisions in
strategic Forest Plans because they did not
specifically authorize actions on the ground,
commitments of staff, or expenditures of funds. - Only will be ripe for judicial review if find
significant effects and do EIS unless CE, then
no judicial review. - Forest plans chart the strategic direction for
management of the forest for 10 or more years
seems pretty significant.
24Mitigation measures
- Agencies can discuss mitigation measures in an EA
which, if followed, lead to no significant
environmental effects, and no EIS. - These mitigation measures can be used to issue a
mitigated FONSI on the basis of the EA
including the proposed mitigation measures - If these mitigation measures are not implemented,
the agency is not held accountable. The proposed
mitigation is not a requirement of the action or
a commitment by the agency.
25Advice to decision makers
- In doing an EA, consider cumulative effects and
connected actions that may require an EIS rather
than doing each action separately resulting in a
FONSI. This will ultimately prevent litigation
as was seen in the Peterson case. - Significant effects leaves a lot of discretion
and according to NEPA only significant effects to
the human environment must be considered. - Mitigation measures may be included in an EA to
prevent the need for an EIS, and since NEPA is
somewhat toothless they need not be carried
out. - When possible, use Categorical Exclusions to
avoid NEPA. - The Forest Service may be misunderstanding the
ripeness issue from Ohio Forestry in not
conducting an EIS on the forest plan. This is
confusing and it seems that you dont need an EIS
or NEPA compliance with a forest plan, but to do
anything in compliance with the forest plan, you
need to do an EA, and maybe EIS under NEPA.
Unless it is a CE. This is confusing and may
have a lot to do with how the Plaintiffs
addressed the issues.
26Reviewing the NFMA planning rules 36 CFR Part 219
and the FS list of categorical exclusions, at
what point does the decision by the agency to not
use NEPA become indefensible legally? Is this the
same point as when it becomes indefensible
politically?
Question 3
27NMFA Planning Rules
- Purpose of 36 CFR Part 219 is to set forth a
process for developing, adopting, and revising
land and resource management plans for the
National Forest System as required by the Forest
and Rangeland Renewable Resources Planning Act of
1974 - Among the planning principles enumerated
- (9) Coordination with the land and resource
planning efforts of other Federal agencies, State
and local governments, and Indian tribes - (10) Use of a systematic, interdisciplinary
approach to ensure coordination and integration
of planning activities for multiple-use
management - (11) Early and frequent public participation
28219.5 Interdisciplinary Approach
- (1) Assessing the problems and resource use and
development opportunities associated with
providing goods and services - (2) Obtaining the public's views about possible
decisions - (3) Implementing the planning coordination
activities within the Forest Service and with
local, State and other Federal agencies - (4) Developing a broad range of alternatives
which identify the benefits and costs of land and
resource management according to the planning
process described in this subpart. - (5) Developing the land and resource management
plan and associated environmental impact
statement required pursuant to the planning
process - (6) Presenting to the responsible line officer an
integrated perspective on land and resource
management planning and - (7) Establishing the standards and requirements
by which planning and management activities will
be monitored and evaluated.
29219.6 Public Participation in Planning
- Public comments shall be analyzed according to
NEPA procedures. - (c) Public participation activities, as deemed
appropriate by the responsible line officer,
shall be used early and often throughout the
development of plans. Formal public participation
activities will begin with a notice to the news
media and other sources - Discretionary authority is built in to control
the degree of public participation
30Recalling the Language Spirit of NEPASec. 102
42 USC 4332.
- (A) utilize a systematic, interdisciplinary
approach which will insure the integrated use of
the natural and social sciences and the
environmental design arts in planning and in
decision-making which may have an impact on man's
environment - (B) identify and develop methods and procedures,
in consultation with the Council on Environmental
Quality established by title II of this Act,
which will insure that presently unquantified
environmental amenities and values may be given
appropriate consideration in decision-making
along with economic and technical considerations
31Continued
- (C) include in every recommendation or report on
proposals for legislation and other major Federal
actions significantly affecting the quality of
the human environment, a detailed statement by
the responsible official on -- - (i) the environmental impact of the proposed
action, - (ii) any adverse environmental effects which
cannot be avoided should the proposal be
implemented, - (iii) alternatives to the proposed action,
- (iv) the relationship between local short-term
uses of man's environment and the maintenance and
enhancement of long-term productivity, and - (v) any irreversible and irretrievable
commitments of resources which would be involved
in the proposed action should it be implemented. - The NMFA planning language seems to echo the
language of NEPA in many fundamental ways and
develop procedures in accordance with its values
32CEQ Scoping Guidelines for the Forest Service
- (a) As part of the scoping process the lead
agency shall - (1) Invite the participation of affected Federal,
State, and local agencies, any affected Indian
tribe, the proponent of the action, and other
interested persons (including those who might not
be in accord with the action on environmental
grounds), unless there is a limited exception
under 1507.3(c). An agency may give notice in
accordance with 1506.6. - (2) Determine the scope (1508.25) and the
significant issues to be analyzed in depth in the
environmental impact statement. - (3) Identify and eliminate from detailed study
the issues which are not significant or which
have been covered by prior environmental review
(1506.3), narrowing the discussion of these
issues in the statement to a brief presentation
of why they will not have a significant effect on
the human environment or providing a reference to
their coverage elsewhere. - (4) Allocate assignments for preparation of the
environmental impact statement among the lead and
cooperating agencies, with the lead agency
retaining responsibility for the statement. - (5) Indicate any public environmental assessments
and other environmental impact statements which
are being or will be prepared that are related to
but are not part of the scope of the impact
statement under consideration. - (6) Identify other environmental review and
consultation requirements so the lead and
cooperating agencies may prepare other required
analyses and studies concurrently with, and
integrated with, the environmental impact
statement as provided in 1502.25. - (7) Indicate the relationship between the timing
of the preparation of environmental analyses and
the agency's tentative planning and
decisionmaking schedule. (40 CFR 1501.7)
33Categorical Exclusions
- 31.11 - Categories Established by the Secretary
- -Primarily related to administrative functions
- Ex. Program budget proposals and disbursements
- 31.12 - Categories Established by the Chief
- -Routine administrative, maintenance, and other
actions that normally do not individually or
cumulatively have a significant effect on the
quality of the human environment -
- Prohibitions to provide short-term resource
protection or to protect public health and safety
Ex. Closing a road to protect bighorn sheep
during lambing season. - Repair and maintenance of administrative sites.
Ex. Mowing lawns at a District office. - Repair and maintenance of roads, trails, and
landline boundaries. Ex.Authorizing a user to
grade, resurface, and clean the culverts of an
established National Forest System road.
See Sec. 31 of the Forest Service Handbook for
the full list of exclusions
34More Recent (and more controversial) CEs
- Hazardous Fuels Reduction and Fire Rehabilitation
Activities - Fire rehabilitation activities on less than 4,200
acres - Tree planting, habitat restoration, repair of
roads and fences - Limited Timber Harvests
- Salvage timber sales of 250 acres or less to
apply to trees severely damaged by fire, ice,
insects or disease - Allows incidental removal of trees for temporary
roads, landings, and skid trails
35Extraordinary Circumstances
- 2. Resource conditions that should be considered
in determining whether extraordinary
circumstances related to the proposed action
warrant further analysis and documentation in an
EA or an EIS are - a. Federally listed threatened or endangered
species or designated critical habitat, species
proposed for Federal listing or proposed critical
habitat, or Forest Service sensitive species. - b. Flood plains, wetlands, or municipal
watersheds. - c. Congressionally designated areas, such as
wilderness, wilderness study areas, or national
recreation areas. - d. Inventoried roadless areas.
- e. Research natural areas.
- f. American Indians and Alaska Native religious
or cultural sites. - g. Archaeological sites, or historic properties
or areas. - The mere presence of one or more of these
resource conditions does not preclude use of a
categorical exclusion. It is the degree of the
potential effect of a proposed action on these
resource conditions that determines whether
extraordinary circumstances exist.
36Clarification of Court Order inEarth Island
Institute v. Ruthenbeck
- Federal District Court ordered that categorically
excluded timber sales as well as - Projects involving the use of prescribed burning
- Projects involving the creation or maintenance of
wildlife openings - Various restrictions, regulations on off-highway
vehicles (OHV) and their travel - Projects involving the cutting of trees for
thinning or wildlife purposes occurring over an
area greater than 5 contiguous miles - Gather geophysical data using shorthole,
vibroseis, or surface charge - Trenching to obtain evidence of mineralization
- Clearing vegetation for sight paths from areas
used for mineral, energy, or geophysical
investigation or support facilities for such
activities - Are subject to notice, comment, and appeal under
- 36 CFR 215 rules.
37Forest Service Memo
- Therefore, any categorically excluded activity
that does not fall within the categories the
judge listed above does not require notice,
comment, and appeal.Any actions or
authorizations that were suspended under the
prior instructions and that do not fall within
the above categories should be immediately
reinstated. - Dale Bosworth, Chief
- What happened to public participation and
transparency?
38The Problems and Issues
- There was a reasonably inherent notion embedded
in NEPA and the Court decisions that followed
that targeted agency actions would receive some
unique site by site consideration and
investigation. Whether that concluded in a FONSI
or not, each action would seemingly receive an
evaluation. -
- This policy was at the root of holding federal
agencies accountable for their actions and to
create greater transparency in agency
decision-making and implementation.
39- Categorical exclusions exist to promote economic
efficiency and to - allow the FS to operate without additional
burdens on their - autonomy (to create internal regulations, etc)
however, when or - where do these CEs cross the line of legality?
- Consider cumulative effects of these CE
determinations - Economic Expediency or Environmental
Accountability? - Other thoughts?
40Question 4
- What is your analysis of the use of categorical
exclusions within the legal context of the Forest
Service to limit judicial review of strategic and
programmatic decisions?
41Categorical Exclusions
- Categorical Exclusions provide a mechanism for
streamlining and speeding up approvals for common
projects and activities that do not threaten the
environment - They allow Agencies to efficiently allocate
scarce resources and avoid unnecessary and
redundant work - However.
42Pre-Earth Island
- They are ripe for abuse
- Specifically, as evidenced in the Burnt Ridge
Project, agencies could use the categorical
exclusions to circumvent the judicial appeals
process - Agencies could avoid the cost and risk of an
administrative appeal process through a finding
of no significant impact of a project at the
strategic or programmatic level and then use that
NEPA standard to categorically exclude review at
a site specific level where the Courts afford
less deference
43Pre-Earth Island
- Under the Forest Services regulation set forth in
36 CFR part 219, the Forest Service could exempt
itself from administrative review required by the
ARA upon a finding of no significant effects of
a categorical exclusion such as the Fire CE - Under this procedure, any site specific actions
subsequently conducted under the Fire CE would
then be excluded from the administrative appeals
requirement - Agencies could thus avoid the Administrative
appeals process at a site specific level through
categorical exclusions based on NEPA data
gathered at programmatic level - Plaintiffs such as Earth Island or the Sierra
Club would then be unable to bring actions for
judicial review at either the Programmatic or
site specific level
44Ohio Forestry v. Sierra Club
- In holding that programmatic forest management
plans were not ripe for judicial review without
being applied in a specific context, - Justice Breyer wore for the Court that to
"'withhold court consideration' at present will
not cause the parties significant 'hardship.'"
"Before the Forest Service can permit logging,
it must focus upon a particular site, propose a
specific harvesting method, prepare an
environmental review, permit the public an
opportunity to be heard, and (if challenged)
justify the proposal in court," continued Justice
Breyer, "the Sierra Club thus will have ample
opportunity later to bring its legal challenge at
a time when harm is more imminent and more
certain."
45- Under the Forest Services categorical exclusions,
Citizens and Environmental groups could thus be
barred from challenging the Federal action at the
programmatic level based on ripeness and at the
site specific level based on the Forest Services
categorical exclusion
46Post-Earth Island
- Federal Agencies can no longer circumvent the
judicial appeals process by using categorical
exclusions based on NEPA standards gathered at
the programmatic or strategic level to exempt
site specific actions from administrative review - However, the District Court has clarified this by
indicating that permits for short term special
uses need not be subject to notice, comment, and
appeal
47What hasnt changed
- Continued incentive to use Categorical exclusions
at the Programmatic and Strategic level - Adaptability of plan
- Cutting down on research and paperwork
- Saving time and money
- Programmatic decisions, including categorical
exclusions, still given deference by the Court to
allow for agency efforts to refine its policies - Challenges to Forest Service plans remain unripe
under Ohio Forestry because they have not yet
been applied in a specific context
48