CONSTRUCTION CONTRACTS DOCUEMENTS - PowerPoint PPT Presentation

1 / 72
About This Presentation
Title:

CONSTRUCTION CONTRACTS DOCUEMENTS

Description:

... Change sequence or timing of construction. Note : Max Allowable variation by Fidic is 15%, but in Palestinian Contracting contract is 20%. – PowerPoint PPT presentation

Number of Views:307
Avg rating:3.0/5.0
Slides: 73
Provided by: Maha73
Category:

less

Transcript and Presenter's Notes

Title: CONSTRUCTION CONTRACTS DOCUEMENTS


1
CONSTRUCTION CONTRACTS DOCUEMENTS
BYLECTURERMaha Muhaisen
  • APPLIED CIVIL ENGINEERING DEPT

2
General Conditions of contract
  • The conditions are intended to govern and
    regulate the obligation of formal contract.
  • Although the headings and topics included within
    different sets of GCC vary, there is a certain
    similarity of subject matter

3
Contents of GCC
  • Definitions
  • Contract documents
  • Rights and responsibilities of owner
  • Duties and authorities of engineer
  • Rights and responsibilities of contractor
  • Sub-contractor, Separate contractors
  • Time
  • Payments and completions
  • Changes in the work
  • Protection of persons and property
  • Insurance and bond
  • Disputes
  • Termination of contract
  • Miscellaneous provisions

4
FIDIC , AN INTRODUCTION
  • Founded in 1913
  • Expanded in 1945 to include 40 national
    associations
  • Published first Conditions of Contract in 1957
  • In 2004 has 64 member associations
  • Headquarters in Switzerland
  • Web Site www.fidic.org

5
FIDIC , AN INTRODUCTION
  • Pre 1957 no internationally recognised contract
    conditions
  • First red book based on UK ICE conditions
  • FIDIC has international committees to improve
    contracts

6
Contract Documents 1999
  • Conditions of Contract for Construction (Red
    Book)
  • Conditions of Contract for Plant Design Build
    (Yellow Book)
  • Conditions of Contract for EPC Turnkey Projects
    (Silver Book)
  • Short Form of Contracts (Green Book)

7
FIDIC Document UsageConditions of Contract for
Construction
  • Works designed by Employer or Engineer
  • Contractor Constructs in accordance with designs
    provided
  • May include some design elements

8
FIDIC Document UsageConditions of Contract
for, Plant Design Build
  • Electrical Mechanical Plant
  • May include building and engineering
  • Design Execution of works
  • Contractor designs and constructs in accordance
    with Employers Requirements
  • Engineer Administers

9
FIDIC Document UsageShort Form of Contract
  • Small capital value projects
  • Simple content
  • Contractor constructs to Employers designs
  • No Particular Conditions
  • No Impartial Engineer

10
Typical sequence of Principal Events during
Contracts
11
Typical sequence of Payment Events envisaged in
Clause 14(contract price and payment)
12
Typical sequence of Dispute Events envisaged in
Clause 20
DAB the persons so named in the contract or
other persons appointed under sub-clause
(appointment of the dispute adjudication board)
13
FIDIC conditions of contract
  • 1 GENERAL PROVISIONS
  • 2 THE EMPLOYER .
  • 3 THE ENGINEER
  • 4 THE CONTRACTOR
  • 5 NOMINATED SUBCONTRACTORS
  • 6 STAFF AND LABOUR
  • 7 PLANT, MATERIALS AND WORKMANSHIP
  • 8 COMMENCEMENT, DELAYS AND SUSPENSION
  • 9 TESTS ON COMPLETION
  • 10 EMPLOYERS TAKING OVER .
  • 11 DEFECTS LIABILITY
  • 12 MEASUREMENT AND EVALUATION

14
FIDIC conditions of contract (contd)
  • 13 VARIATIONS AND ADJUSTMENTS
  • 14 CONTRACT PRICE AND PAYMENT
  • 15 TERMINATION BY EMPLOYER
  • 16 SUSPENSION AND TERMINATION BY CONTRACTOR
  • 17 RISK AND RESPONSIBILITY
  • 18 INSURANCE
  • 19 FORCE MAJEURE
  • 20 CLAIMS, DISPUTES AND ARBITRATION

15
FIDIC conditions of contract
  • 1 GENERAL PROVISIONS
  • 1.1 Definitions
  • 1.2 Interpretation
  • 1.3 Communications
  • 1.4 Law and Language
  • 1.5 Priority of Documents
  • 1.6 Contract Agreement
  • 1.7 Assignment
  • 1.8 Care and Supply of Documents
  • 1.9 Delayed Drawings or Instructions
  • 1.10 Employers Use of Contractors Documents
  • 1.11 Contractors Use of Employers Documents
  • 1.12 Confidential Details
  • 1.13 Compliance with Laws
  • 1.14 Joint and Several Liability

16
FIDIC conditions of contract contd
  • 2 THE EMPLOYER .
  • 2.1 Right of Access to the Site
  • 2.2 Permits, Licenses or Approvals
  • 2.3 Employers Personnel
  • 2.4 Employers Financial Arrangements
  • 2.5 Employers Claims
  • 3 THE ENGINEER
  • 3.1 Engineers Duties and Authority
  • 3.2 Delegation by the Engineer
  • 3.3 Instructions of the Engineer
  • 3.4 Replacement of the Engineer
  • 3.5 Determinations

17
FIDIC conditions of contract contd
  • 4 THE CONTRACTOR
  • 4.1 Contractors General Obligations
  • 4.2 Performance Security
  • 4.3 Contractors Representative
  • 4.4 Subcontractors
  • 4.5 Assignment of Benefit of Subcontract
  • 4.6 Co-operation
  • 4.7 Setting Out
  • 4.8 Safety Procedures
  • 4.9 Quality Assurance
  • 4.10 Site Data
  • 4.11 Sufficiency of the Accepted Contract Amount
  • 4.12 Unforeseeable Physical Conditions
  • 4.13 Rights of Way and Facilities

18
  • 4.14 Avoidance of Interference
  • 4.15 Access Route
  • 4.16 Transport of Goods
  • 4.17 Contractors Equipment
  • 4.18 Protection of the Environment
  • 4.19 Electricity, Water and Gas
  • 4.20 Employers Equipment and Free-Issue Material
  • 4.21 Progress Reports
  • 4.22 Security of the Site
  • 4.23 Contractors Operations on Site
  • 4.24 Fossils

19
  • 5 NOMINATED SUBCONTRACTORS
  • 5.1 Definition of nominated Subcontractor
  • 5.2 Objection to Nomination
  • 5.3 Payments to nominated Subcontractors
  • 5.4 Evidence of Payments

20
  • 6 STAFF AND LABOUR
  • 6.1 Engagement of Staff and Labour
  • 6.2 Rates of Wages and Conditions of Labour
  • 6.3 Persons in the Service of Employer
  • 6.4 Labour Laws
  • 6.5 Working Hours
  • 6.6 Facilities for Staff and Labour
  • 6.7 Health and Safety
  • 6.8 Contractors Superintendence
  • 6.9 Contractors Personnel
  • 6.10 Records of Contractors Personnel and
    Equipment
  • 6.11 Disorderly Conduct
  • 6.12 Foreign Personnel
  • 6.13 Supply of Foodstuffs

21
  • 6.14 Supply of Water
  • 6.15 Measures against Insect and Pest Nuisance
  • 6.16 Alcoholic Liquor or Drugs
  • 6.17 Arms and Ammunition
  • 6.18 Festival and Religious Customs
  • 6.19 Funeral Arrangements
  • 6.20 Prohibition of Forced or Compulsory Labor
  • 6.21 Prohibition of Harmful Child Labour
  • 6.22 Employment Records of Workers

22
  • 7 PLANT, MATERIALS AND WORKMANSHIP
  • 7.1 Manner of Execution
  • 7.2 Samples
  • 7.3 Inspection
  • 7.4 Testing
  • 7.5 Rejection
  • 7.6 Remedial Work
  • 7.7 Ownership of Plant and Materials
  • 7.8 Royalties
  • 8 COMMENCEMENT, DELAYS AND SUSPENSION
  • 8.1 Commencement of Works
  • 8.2 Time for Completion
  • 8.3 Programme
  • 8.4 Extension of Time for Completion
  • 8.5 Delays Caused by Authorities
  • 8.6 Rate of Progress
  • 8.7 Delay Damages

23
  • 8.8 Suspension of Work
  • 8.9 Consequences of Suspension
  • 8.10 Payment for Plant and Materials in Event of
    Suspension
  • 8.11 Prolonged Suspension
  • 8.12 Resumption of Work
  • 9 TESTS ON COMPLETION
  • 9.1 Contractors Obligations
  • 9.2 Delayed Tests
  • 9.3 Retesting
  • 9.4 Failure to Pass Tests on Completion
  • 10 EMPLOYERS TAKING OVER
  • 10.1 Taking Over of the Works and Sections
  • 10.2 Taking Over of Parts of the Works
  • 10.3 Interference with Tests on Completion
  • 10.4 Surfaces Requiring Reinstatement

24
  • 11 DEFECTS LIABILITY
  • 11.1 Completion of Outstanding Work and Remedying
    Defects
  • 11.2 Cost of Remedying Defects
  • 11.3 Extension of Defects Notification Period
  • 11.4 Failure to Remedy Defects
  • 11.5 Removal of Defective Work
  • 11.6 Further Tests
  • 11.7 Right of Access
  • 11.8 Contractor to Search
  • 11.9 Performance Certificate
  • 11.10 Unfulfilled Obligations
  • 11.11 Clearance of Site

25
  • 12 MEASUREMENT AND EVALUATION .
  • 12.1 Works to be Measured
  • 12.2 Method of Measurement
  • 12.3 Evaluation
  • 12.4 Omissions
  • 13 VARIATIONS AND ADJUSTMENTS
  • 13.1 Right to Vary
  • 13.2 Value Engineering
  • 13.3 Variation Procedure
  • 13.4 Payment in Applicable Currencies
  • 13.5 Provisional Sums
  • 13.6 Daywork
  • 13.7 Adjustments for Changes in Legislation
  • 13.8 Adjustments for Changes in Cost

26
  • 14 CONTRACT PRICE AND PAYMENT
  • 14.1 The Contract Price
  • 14.2 Advance Payment
  • 14.3 Application for Interim Payment Certificates
  • 14.4 Schedule of Payments
  • 14.5 Plant and Materials intended for the Works
  • 14.6 Issue of Interim Payment Certificates
  • 14.7 Payment
  • 14.8 Delayed Payment
  • 14.9 Payment of Retention Money
  • 14.10 Statement at Completion
  • 14.11 Application for Final Payment Certificate
  • 14.12 Discharge
  • 14.13 Issue of Final Payment Certificate
  • 14.14 Cessation of Employers Liability
  • 14.15 Currencies of Payment

27
  • 15 TERMINATION BY EMPLOYER
  • 15.1 Notice to Correct
  • 15.2 Termination by Employer
  • 15.3 Valuation at Date of Termination
  • 15.4 Payment after Termination
  • 15.5 Employers Entitlement to Termination for
    Convenience
  • 15.6 Corrupt or Fraudulent Practices

28
  • 16 SUSPENSION AND TERMINATION BY CONTRACTOR
  • 16.1 Contractors Entitlement to Suspend Work
  • 16.2 Termination by Contractor
  • 16.3 Cessation of Work and Removal of
    Contractors Equipment
  • 16.4 Payment on Termination
  • 17 RISK AND RESPONSIBILITY
  • 17.1 Indemnities
  • 17.2 Contractors Care of the Works
  • 17.3 Employers Risks
  • 17.4 Consequences of Employers Risks
  • 17.5 Intellectual and Industrial Property Rights
  • 17.6 Limitation of Liability
  • 17.7 Use of Employers Accommodation/Facilities

29
  • 18 INSURANCE
  • 18.1 General Requirements for Insurances
  • 18.2 Insurance for Works and Contractors
    Equipment
  • 18.3 Insurance against Injury to Persons and
    Damage to Property
  • 18.4 Insurance for Contractors Personnel
  • 19 FORCE MAJEURE
  • 19.1 Definition of Force Majeure
  • 19.2 Notice of Force Majeure
  • 19.3 Duty to Minimize Delay
  • 19.4 Consequences of Force Majeure
  • 19.5 Force Majeure Affecting Subcontractor
  • 19.6 Optional Termination, Payment and Release
  • 19.7 Release from Performance

30
  • 20 CLAIMS, DISPUTES AND ARBITRATION
  • 20.1 Contractors Claims
  • 20.2 Appointment of the Dispute Board
  • 20.3 Failure to Agree on the Composition of the
    Dispute Board
  • 20.4 Obtaining Dispute Boards Decision
  • 20.5 Amicable Settlement
  • 20.6 Arbitration
  • 20.7 Failure to Comply with Dispute Boards
    Decision
  • 20.8 Expiry of Dispute Boards Appointment

31
General conditions
  • The following are main items that include in the
    general conditions for the tender ( or the
    construction contract.

32
Definitions
  • Main definitions related to
  • Contract include contract agreement, letter of
    acceptance, letter of tender, specifications,
    drawings, schedules, tender, appendix to tender,
    bill of quantities.
  • parties and persons party, employer,
    contractor, engineer, contractor representative,
    employers' personnel, contractors personnel, sub-
    contractor, DAB (dispute adjudication board),
    Fidic.
  • Dates , tests, periods and completion include
    base date, commencement date, time of completion,
    test on completion, taking over certificate,
    defects notification period, performance
    certificate, day
  • Money and payment accepted contract amount,
    contract price, cost, final , interim payment
    certificate, currency, provisional sum, retention
    money,

33
Definitions
  • The main definitions that are included in and
    repeated in the articles of general conditions,
    are
  • Employer The party named in the Contract as the
    "FIRST PARTY" who will enter into contract with
    the Contractor for the execution of the Works
    covered by the Contract, or any other party
    authorized by the Employer to exercise the powers
    and obligations of the First Party, provided that
    the Contractor will be informed accordingly in
    writing .
  • Contractor The person, company or joint venture
    named as Second Party in the Contract whose
    Tender has been accepted by the Employer and with
    whom the Employer has entered into Contract, and
    includes the Contractors personal agents and his
    legal successors
  • Engineer The Consulting office, or Engineering
    office or Engineer or any other technical body
    appointed from time to time by the Employer to
    exercise in whole or in part the powers of the
    Engineer in accordance with the Conditions of the
    Contract provided that the Contractor shall be
    accordingly notified in writing.

34
Definitions, Contd
  • Engineers Representative - Any resident engineer,
    or clerk of works appointed by the Engineer from
    time to time
  • Contract - The documents constituting these
    Conditions (Parts I and II), the Specification,
    the Drawings, the Bill of Quantities, the Tender,
    the Letter of Acceptance, the Contract Agreement,
    and such further documents as may be expressly
    incorporated in the Letter of Acceptance or
    Contract Agreement (if completed).
  • Contract Sum - The sum stated in the Letter of
    Acceptance as payable to the Contractor for the
    execution and completion of the Works and the
    remedying of any defects therein in accordance
    with the provisions of the Contract, subject to
    such additions thereto or deductions therefore as
    may be made under the provisions of the Contract.
  • Equipment is the Contractors machinery and
    vehicles brought temporarily to the Site to
    construct the Works.
  • Site - The land and other places provided by the
    Employer or designated as such where the Works
    are to be executed, and any other places
    specifically designated in the Contract as
    forming part of the Site.
  • approval (written approval)
  • time (calendar / working days)

35
Engineer's Duties and Authority
  • a) The Engineer shall carry out the duties
    specified in the Contract .
  • b) The Engineer shall exercise the authority
    specified in or necessarily to be implied from
    the Contract .
  • Provided, that the Engineer shall obtain the
    specific approval of the Employer, in compliance
    with the terms of his appointment, and after
    submitting his recommendations to the Employer in
    writing, in the following matters
  • issuing variation orders
  • deciding on the extension of Time for Completion
    and applying the Liquidated Damages Clause
  • approving the appointment of Subcontractors
  • notifying the Contractor on suspension of Works
    and any other matters as may be set out in Part
    II of these conditions).
  • (c) Except as expressly stated in the Contract,
    the Engineer shall have no authority to relieve
    the Contractor of any of his obligations under
    the Contract

36
  • Engineer's Representative
  • The Engineer's Representative shall be appointed
    by and be responsible to the Engineer and shall
    carry out such duties of watching and supervising
    the execution and workmanship of the Works and to
    test and examine any materials to be used or
    workshop employed in connection with the Works.
    He shall exercise such authority as may be
    delegated to him by the Engineer

37
  • Engineer's Authority to Delegate
  • The Engineer may from time to time delegate to
    the Engineer's Representative any of the duties
    and authorities vested in the Engineer and he may
    at any time revoke such delegation. Any such
    delegation or revocation shall be in writing and
    shall not take effect until a copy thereof has
    been delivered to the Employer and the Contractor
    .
  • Any communication given by the Engineer's
    Representative to the Contractor in accordance
    with such delegation shall have the same effect
    as though it had been given by the Engineer
  • Provided that
  • any failure of the Engineer's Representative to
    disapprove any work, materials or Plant shall not
    prejudice the authority of the Engineer to
    disapprove such work, material or Plant and to
    give instructions for the rectification thereof
  • if the Contractor questions any communication of
    the Engineers Representative, he may refer the
    matter to the Engineer who shall confirm, reverse
    or vary the contents of such communication .

38
Contractors General Obligations
  • The Contractor shall design (to the extent
    specified in the Contract), execute and complete
    the Works in accordance with the Contract and
    with the Engineers instructions, and shall
    remedy any defects in the Works.
  • The Contractor shall provide the Plant and
    Contractors Documents specified in the Contract,
    and all Contractors Personnel, Goods,
    consumables and other things and services,
    whether of a temporary or permanent nature,
    required in and for this design, execution,
    completion and remedying of defects.
  • The Contractor shall be responsible for the
    adequacy, stability and safety of all Site
    operations and of all methods of construction.
    Except to the extent specified in the Contract,
    the Contractor
  • shall be responsible for all Contractors
    Documents, Temporary Works, and such design of
    each item of Plant and Materials as is required
    for the item to be in accordance with the
    Contract, and
  • shall not otherwise be responsible for the design
    or specification of the Permanent Works.

39
Contractors General Obligations,
  • The Contractor shall, whenever required by the
    Engineer, submit details of the arrangements and
    methods which the Contractor proposes to adopt
    for the execution of the Works. No significant
    alteration to these arrangements and methods
    shall be made without this having previously been
    notified to the Engineer.
  • If the Contract specifies that the Contractor
    shall design any part of the Permanent Works,
    then unless otherwise stated in the Particular
    Conditions
  • the Contractor shall submit to the Engineer the
    Contractors Documents for this part in
    accordance with the procedures specified in the
    Contract
  • these Contractors Documents shall be in
    accordance with the Specification and Drawings,
    shall be written in the language for
    communications

40
ASSIGNMENT AND SUBCONTRACTINGASSIGNMENT AND
SUBCONTRACTING
  • Assignment of Contract
  • The Contractor shall not, without the prior
    consent of the Employer, assign the Contract or
    any part thereof, or benefit or interest therein
    or thereunder, otherwise than by
  • a charge in favor of the Contractor's bankers of
    any moneys due or to become due under the
    Contract, or
  • assignment to the Contractor's insurers of the
    Contractor's right to obtain relief against any
    other party liable.
  • Subcontracting
  • The Contractor shall not subcontract the whole
    of the Works. Except where otherwise provided by
    the Contract, the Contractor shall not
    subcontract any part of the Works without the
    prior consent of the Engineer. Any such consent
    shall not relieve the Contractor from any
    liability or obligation under the Contract and he
    shall be responsible for the acts, defaults and
    neglects of any Subcontractor, his agents,
    servants or workmen as fully as if they were the
    acts, defaults or neglects of the Contractor, his
    agents, servants or workmen.
  • Provided that the Contractor shall not be
    required to obtain such consent for
  • (a) the provision of labor, or
  • (b) the subcontracting of any part of the Works
    for which the Subcontractor is named in the
    Contract.

41
  • Assignment of Subcontractor's Obligations
  • In the event of a Subcontractor having
    undertaken towards the Contractor in respect of
    the work executed, or the goods, materials, Plant
    or services supplied by such Subcontractor, any
    continuing obligation extending for a period
    exceeding that of the Defects Liability Period
    under the Contract, the Contractor shall at any
    time, after the expiration of such Period, assign
    to the Employer, at the Employer's request and
    cost, the benefit of such obligation for the
    unexpired duration thereof.

42
Language and Law
  • Arabic language shall be the ruling language
    of the Contract Documents unless stated otherwise
    in these conditions, and consequently all
    correspondence, payment statements, and take-over
    certificates shall be drawn in this language.

43
Priority of Contract Documents
  • The several documents forming the Contract are
    to be taken as mutually explanatory of one
    another, but in case of ambiguities or
    discrepancies the same shall be explained and
    adjusted by the Engineer who shall thereupon
    issue to the Contractor instructions thereon and
    in such event, unless otherwise provided in the
    Contract, the priority of the documents forming
    the Contract shall be as follows
  • (1) The Contract Agreement (if completed)
  • (2) The Letter of Acceptance
  • (3) The Tender
  • (4) Part II of these Conditions
  • (5) Part I of these Conditions and
  • (6) Any other document forming part of the
    Contract.

44
Performance Security
  • The Contractor, upon receiving the Letter of
    Acceptance, shall obtain and provide to the
    Employer before signing the Contract, the
    Performance Guarantee in the value of ten percent
    of the Contract Sum, as a guarantee of the proper
    execution of the Works in accordance with the
    Contract. This guarantee shall be issued by a
    licensed bank or financial institution acceptable
    to the Employer. The guarantee shall be prepared
    in the form included in part B of these
    conditions. The obtaining of such guarantee
    shall in all respects be at the expense of the
    Contractor.

45
Inspection of Site
  • The Employer shall have made available to the
    Contractor, before the submission by the
    Contractor of the Tender, such data on
    hydrological and sub - surface conditions as have
    been obtained by or on behalf of the Employer
    from investigations undertaken relevant to the
    Works but the Contractor shall be responsible for
    his own interpretation thereof.
  • The Contractor shall be deemed to have inspected
    and examined the Site and its surroundings and
    information available in connection therewith and
    to have satisfied himself (so far as time is
    practicable), before submitting his Tender, as to
  • (a) the form and nature thereof, including the
    sub - surface conditions,
  • (b) the hydrological and climate conditions,
  • (c) the extent and nature of work and materials
    necessary for the execution and completion of the
    Works and the remedying of any defects therein,
    and
  • (d) the means of access to the Site and the
    accommodation he may require and, in general,
    shall be deemed to have obtained all necessary
    information, subject as above mentioned, as to
    risks, contingencies and all other circumstances
    which may influence or affect his Tender.
  • The Contractor shall be deemed to have based on
    his Tender, the data made available by the
    Employer and on his own inspection and
    examination, all as aforementioned.

46
Sufficiency of Tender
  • The Contractor shall be deemed to have satisfied
    himself as to the correctness and sufficiency of
    the Tender and of the rates and prices stated in
    the Bill of Quantities, all of which shall
    except insofar as it is otherwise provided in the
    Contract, cover all his obligations under the
    Contract (including those in respect of the
    supply of goods, materials, Plant or services or
    of contingencies for which there is a Provisional
    Sum) and all matters and things necessary for the
    proper execution and completion of the Works and
    the remedying of any defects therein.

47
PROGRAMME TO BE SUBMITTED
  • Within a specified time (in days), after the
    date of the Letter Of Acceptance, the contractor
    shall submit a programme to the engineer for his
    consent in such a way and detail as the engineer
    shall reasonable prescribe for the execution of
    the works. It is also required that whenever
    the engineer requires, the contractor shall
    provide in writing, for his information, a
    general description of the arrangement and
    methods which the contractor proposes to adopt
    for the execution of the works.

48
REVISED PROGRAMME
  • If it appears to the engineer, at any time, that
    the actual progress of the works does not conform
    to the progamme to which consent, is given the
    contractor at the request of the engineer, is
    required to produce a revised programme necessary
    to ensure completion of the works within the Time
    for Completion.

49
CASHFLOW ESTIMATE
  • The contractor shall within time stated in Part
    II provide a detailed cash flow estimate, in
    quarterly period, for all payments to which the
    contractor will be entitled under the contract
    (to the engineer) and the contractor shall
    subsequently supply revised cash flow estimates
    at quarterly intervals, if required to do so by
    the engineer.
  • Such cash flow statements do not relieve the
    contractor of any of this duties or
    responsibilities under the contract.

50
  • CONTRACTORS SUPERINTENDENCE
  • The contractor is needed to provide all
    necessary superintendence during the execution of
    the work and thereafter, as long as the engineer
    consider it necessary for proper fulfillment of
    the contractors obligations under the contract.
  • If the approval of Contractors representative
    is withdrawn by the Engineer then Contractor
    shall replace him by any other representative
    approved by the Engineer.
  • CONTRACTORS EMPLOYEES
  • The contractor shall provide on the site only
    skilled and experienced technical assistants and
    foremen to provide proper superintendence to
    skilled, semiskilled and unskilled labour as is
    necessary.
  • ENGINEER AT LIBERTY TO OBJECT
  • The Clients engineer having objection on the
    contractors worker when they misconduct
    themselves, or are incompetent or negligent in
    the proper performance of his duties. Such
    workers should be replaced as soon as possible.
  • SETTING OUT
  • The contractor has to look after about the
    accurate setting out of the works and the
    provision of all necessary instruments,
    appliances and labour in connection with the
    foregoing responsibilities.
  • The contractor shall rectify any error if caused
    regarding setting out unless it was caused due to
    incorrect data provided by Engineer in writing.

51
INSURANCE
  • The Contractor shall insure the following
  • The full replacement cost for the plant and
    materials to be incorporated in the works plus 15
    percent of the full replacement cost
  • in addition to be insured for the additional
    costs like rectification of loss or damage,
    Professional fees, Demolishing cost and removing
    the debris from the work.
  • The Contractors Equipment and other things
    brought to the site for a sum sufficient for its
    replacement.

52
  • SCOPE OF COVER
  • For the cases mentioned the insurance will be in
    the joint names of the contractor and the
    employer, and shall cover
  • (a) the employer and the contractor against all
    loss or damage other than force Majeure causes
    stated below from start of work till take over
    by Employer.
  • (b) the contractor during Defects Liability
    Period for loss or damage caused prior to
    beginning of Defects Liability Period.
  • EXCLUSIONS
  • There shall be no obligation of insurance to
    cover force Mejure issues such as
  • War, Hostilities, Invasion, Act of Foreign
    enemies.
  • Rebellion, Revolution, Insurrection, Military or
    usurped power or civil war.
  • ionizing radiation, Contamination by
    radioactivity
  • Pressure waves from aircraft or other aerial
    devices

53
  • DAMAGE TO PERSONS AND PROPERTY
  • The Contractor indemnifies and holds harmless,
    the Employer on following issues.
  • a) Death of or Injury to any person or
  • Loss of or damage to any property other than
    Works which may arise out of execution and
    completion of the works, subject to following
    exceptions
  • EXCEPTIONS
  • The exceptions referred above are
  • a) The permanent use or occupation of land by the
    works.
  • b) The right of employer to execute the works
    over under or through the land.
  • c) Damage to the property during the execution of
    the work if the damage is unavoidable in the
    process of execution and remedying the defects as
    per the Contract.
  • d) Damage to property and persons who are either
    injured or dead because of any act or neglect of
    the Employer, his agents, other Contractors who
    are not directly employed by the contractor.
  • The Employer shall indemnify the Contractor
    against all claims arising out of exceptions
    provided in the contract.
  • THIRD PARTY INSURANCE
  • The Contractor shall insure in the joint names
    of the Employer and himself, without limiting
    his or Employer obligations and responsibilities,
    against injury or death to any person, loss or
    damages to the property arising out of the
    performance of contract. This insurance is not
    to cover the exceptions above

54
  • THIRD PARTY INSURANCE
  • The Contractor shall insure in the joint names
    of the Employer and himself, without limiting
    his or Employer obligations and responsibilities,
    against injury or death to any person, loss or
    damages to the property arising out of the
    performance of contract. MINIMUM AMOUNT OF
    INSURANCE
  • The insurance made shall be for at least the
    amount specified in the appendix of the Tender.

55
SUSPENSION
  • The Contractor shall, on the instructions of the
    Engineer, suspend the progress of the Works or
    any part thereof for such time and in such manner
    as the Engineer may consider necessary and shall,
    during such suspension, properly protect and
    secure the Works or such part thereof so far as
    is necessary in opinion of the Engineer. Unless
    such suspension is
  • a) otherwise provided for in the Contract, or
  • b) necessary by reason of some default of or
    breach of contract by the Contractor or for which
    he is responsible, or
  • (c) necessary by reason of climatic conditions on
    the Site, or
  • (d) necessary for the proper execution of the
    Works or for the safety of the Works on any part
    thereof (save to the extent that such necessity
    arises from any act or default by the Engineer or
    the Employer or from any of the risks defined in
    GCC), or
  • (e) by mutual agreement in writing by both
    parties to the Contract, provided that the
    Employer shall not suffer the expenses resulting
    from such suspension, provided always that the
    Contractor shall not be entitled to recover any
    such extra expenses unless he gives to the
    Engineer written notice of his intention to claim
    within (28) days of the Engineers order,

56
  • Engineer's Determination Following Suspension
  • The engineer shall after consulting the
    contractor and the employer determine,
  • - Any extension of time
  • - The amount to be added to the contract price,
    due to suspension.
  • Suspension Of Work For More Than 84 Days
  • If the progress of the work is suspended for
    more than 84 days then the contractor can give a
    notice for resumption of work within 28 days of
    receipt of order. If permission for resumption
    is not given within the said period then the
    contractor can consider it as termination of
    contract.

57
Time for Completion
  • The whole of the Works and, required to be
    completed within a particular time as stated in
    the Appendix to Tender, shall be completed,,
    within the time stated in the Appendix to Tender
    for the whole of the Works or the Section (as the
    case may be), calculated from the Commencement
    Date, or such extended time as may be allowed
    under next clauses.
  • No mobilisation period will be allowed for as an
    extension of the Completion Time, as such period
    is considered to be included in it.

58
Extension of Time for Completion
  • In the event of
  • (a) the amount or nature of extra or additional
    work, or
  • (b) any cause of delay referred to in these
    Conditions, or
  • (c) exceptionally adverse climatic condition (but
    no extension of time shall be granted for the
    anticipated climatic changes), or
  • (d) any delay, impediment or prevention by the
    Employer, or
  • (e) other special circumstances which may occur,
    other than through a default of or breach of
    contract by the Contractor or for which he is
    responsible, being such as fairly to entitle the
    Contractor to an extension of the Time for
    Completion of the Works, or any Section or part
    thereof, the Engineer shall, after due
    consultation with the Employer and the
    Contractor, determine the amount of such
    extension and shall notify the Contractor
    accordingly, with a copy to the Employer.

59
Contractor to Provide Notification and Detailed
Particulars
  • The Engineer is not bound to make any
    determination unless the Contractor has
  • (a) within 28 days after such event has first
    arisen notified the Engineer with a copy to the
    Employer, and
  • (b) within 28 days, or such other reasonable time
    as may be agreed by the Engineer, after such
    notification submitted to the Engineer detailed
    particulars of any extension of time to which he
    may consider himself entitled in order that such
    submission may be investigated at the time.

60
Interim Determination of Extension
  • If it is impracticable for contractor to provide
    details of delay within 28 days, the extension
    shall still be granted, if contractor can provide
    interim details. But the full details of event
    need to be provided within 28 days of the end of
    the effects resulting from events.

61
Liquidated Damages for Delay
  • If the Contractor fails to comply with the Time
    for Completion, for the whole of the Works or, if
    applicable, then the Contractor shall pay to the
    Employer the relevant sum stated in the Appendix
    to Tender as liquidated damages for such default
    and not as a penalty for every day or part of a
    day which shall elapse between the relevant Time
    for Completion and the date stated in a
    Taking-Over Certificate of the whole of the Works
    or the relevant Section, subject to the
    applicable limit stated in the Appendix to
    Tender.
  • The Employer may, without prejudice to any other
    method of recovery, deduct the amount of such
    damages from any moneys due or to become due to
    the Contractor. The payment or deduction of such
    damages shall not relieve the Contractor from his
    obligation to complete the Works, or from any
    other of his obligations and liabilities under
    the Contract.
  • The rate of liquidated damages stated in the
    Appendix to Tender is exclusive of any additional
    supervision costs in respect of the unjustified
    time lapse in completing the Works, and the
    Contractor shall bear such costs.

62
Reduction of Liquidated Damages
  • If, before the Time for Completion of the whole
    of the Works or, if applicable, any Section, a
    Taking-Over Certificate has been issued for any
    part of Works or of a Section, the liquidated
    damages for delay in completion of the remainder
    of the Works or of that Section shall, for any
    period of delay after the date stated in such
    Taking-Over Certificate, and in the absence of
    alternative provision in the Contract, be reduced
    in the proportion which the value of the part so
    certified bears to the value of the whole of the
    Works or Section, as applicable.
  • The provisions of this Clause shall only apply to
    the rate of liquidated damages and shall not
    affect the limit thereof.

63
Taking-Over Certificate
  • When the whole of the Works have been
    substantially completed and have satisfactorily
    passed any Tests on Completion prescribed by the
    Contract, the Contractor may give a notice to
    that effect to the Engineer, with a copy to the
    Employer, accompanied by a written undertaking to
    finish with due expedition any outstanding work
    during the Defects Liability Period. Such notice
    and undertaking shall be deemed to be a request
    by the Contractor for the Engineer to issue a
    Taking-Over Certificate in respect of the Works.
  • The Engineer shall conduct an inspection of the
    Works and report his findings to the Employer
    with a copy to the Contractor. The Engineer may
    either certify that the works have been properly
    completed or ready for acceptance or give
    instructions in writing to the Contractor specify
    the works which, in the opinion of the Engineer,
    require to be done by the Contractor and to the
    Engineer's satisfaction, within a prescribed
    period of time before acceptance. If the
    contractor considers the Engineer's report to be
    incorrect, he may give a notice to that effect to
    the Employer, who shall, in the manner he deems
    suitable either investigate the situation to
    ascertain the validity of the Engineer's report
    or form a Committee for the Taking-Over of the
    Works.

64
  • The Employer shall, within ten days from receipt
    of the Engineer's report, form a "Taking-Over
    Committee", including the Engineer as one of its
    members, and notify the Contractor of the time
    and date fixed for carrying out an inspection of
    the Works. The Engineer and the Contractor shall,
    in the meanwhile, prepare all necessary
    schedules, data, bills and drawings as are
    necessary to facilitate the said Committees
    work.
  • The Committee shall, within ten days from the
    date of being formed, conduct in the presence of
    the Contractor or his authorised agent an
    inspection of the Works, and having done so,
    shall draw up a memorandum of certification of
    the Works which shall be signed by the Committee
    members as well as by the Contractor or his
    authorised agent. Copies of the same shall be
    given to the Employer and the Contractor.
  • The Engineer shall within seven days of the date
    of delivery of the memorandum of the Taking-Over
    Committee to the Contractor, issue a Taking-Over
    Certificate in respect of the Works, stating the
    date on which, in his opinion, the Works are
    considered to be substantially completed in
    accordance with the Contract and the date of
    commencement of the Defects Liability Period. The
    Engineer shall enumerate in the Taking-Over
    Certificate all defects and faults to be remedied
    by the Contractor within a prescribed time
    starting from the start of the Maintenance
    Period.
  • The Contractor is entitled to comment or object
    to the memorandum of the Taking-over Committee in
    writing to the Engineer, provided he does so
    within (7) days from the date of signing the
    memorandum. The Engineer, in such a case, shall
    study the objection and submit his findings to
    the Employer.

65
Variations
  • If the Engineer feels the necessity to make any
    variations of the form, quality or quantity of
    the Works he has the authority to instruct the
    Contractor to do so and the Contractor shall do
    any of the following
  • a) Increase or decrease the quantity of any work
    included in the contract.
  • b) Omit any such work (but not if the omitted
    work is to be carried out by the Employer or by
    another contractor).
  • c) Change the character or quality or kind of
    any such work.
  • d) Change the levels, lines, position and
    dimensions of any part of the works.
  • e) Execute additional work of any kind necessary
    for the completion of the works.
  • f) Change sequence or timing of construction.
  • Note
  • Max Allowable variation by Fidic is 15, but in
    Palestinian Contracting contract is 20.

66
  • INSTRUCTIONS FOR VARIATIONS
  • The Contractor is not supposed to make any
    variation without an instruction of the Engineer.
    No instructions are required if work execution
    results into increase/decrease of quantities than
    those stated in the Bill of quantities.
  • VALUATION OF VARIATIONS
  • All variations and any additions to the Contract
    Price shall be as per the rates and price of
    variations present in the Contract. If the
    Contract does not contain any rates or prices
    applicable to varied work, the rates and prices
    of the Contract shall be used as the basis for
    valuation. In the event of disagreement the
    Engineer shall notify the Contractor with a copy
    to the Employer. Till the time the rates are
    agreed or fixed, the Engineer shall determine
    provisional rates or prices to enable on-account
    payments to be included in certificates issued

67
  • POWER OF ENGINEER TO FIX RATES
  • The Engineer shall determine the rate for varied
    work if existing rates in the contract are
    inappropriate, in consultation with Employer and
    Contractor. If agreement is not reached on the
    rates, the engineer shall fix provisional rates
    which are appropriate in his opinion, to enable
    on account payment for payment certificates
    issued under clause of payment, until such time
    as rates or prices are agreed, provided
    Contractor or engineer has given notice of 14
    days to each other about their intention to seek
    varied rates.
  • VARIATIONS EXCEEDING 15 PERCENT
  • If, on the issue of the Taking-Over Certificate
    for the Whole of the Works, it is found that as a
    result of
  • a) All varied work valued (cases listed in the
    start of variation)
  • b) all adjustments upon measurement of the
    estimated quantities set out in the Bill Of
    Quantities, excluding Provisional Sums, day works
    and adjustments of price made under Clause of
    increase or decrease of the cost (There shall be
    increase/decrease in contract price based on rise
    and fall in cost of labor and material as
    provided in the part II of these conditions) that
    the contract price has varied in excess of 15
    then Engineer will decide increase/decrease to
    contract price having regards to Contractors
    site and general overhead cost. This change if
    any shall be related to 15 excess level over
    contract price.
  • DAY WORK
  • The Engineer if he feels that it is necessary,
    can issue a instruction that any varied work
    shall be executed on a day work basis according
    to the terms and conditions provided in the day
    work schedule.

68
PROVISIONAL SUM
  • DEFINITION Provisional Sum means a sum (if
    any) which is specified in the contract as a
    provisional sum. Provisional Sum shall only be
    used in whole or in part, in accordance with the
    Engineers instructions and the Contract Price
    shall be adjusted accordingly.
  • USE OF PROVISIONAL SUMS
  • The engineer shall have authority to issue
    instruction for the execution of work or for
    supply of goods or services under provisional
    sum.

69
  • MONTHLY STATEMENTS
  • The contractor shall submit to the Engineer
    after the end of each month six copies of
    statements showing the amounts to which the
    contractor considers himself to be entitled up to
    the end of the month in respect of
  • a) The value of the permanent work.
  • b) Any other item in the Bill of Quantities
    including those for contractors equipment.
  • c) And plant delivery by the contractor on the
    sire for incorporation in the permanent works but
    not incorporated in such works.
  • d) Adjustment under the increase or decrease the
    cost.
  • e) Any other sum to which the contractor may be
    entitled under the contract.

70
  • MONTHLY PAYMENTS
  • The Engineer shall, within 28 days of receiving
    such statement, deliver to the employer an
    interim payment certificate stating the amount
    of payment due to the contractor subject.
  • a) Firstly to retention of the amount calculated
    by applying the percentage of retention stated in
    the appendix to tender until the amount so
    retained reaches the limit or retention money
    stated in the appendix to Tender.
  • b) Secondly to the deduction other than pursuant
    to liquidated damages for delay of any sums which
    may have become due and payable by the contractor
    to the Employer.
  • Provided that the engineer shall not be bound to
    certify any payment in the net amount thereof,
    after the retention and deduction, would be less
    than the minimum Amount of interim payment
    certificate stated in the appendix to tender.
  • PAYMENT OF RETENTION MONEY
  • a) Upon the issue of the taking-Over Certificate
    with respect to the whole of the works, one half
    of the retention money, shall be certified by the
    Engineer for payment to the Contractor.
  • b) Upon the expiration of the Defect Liability
    Period for the work other half of the Retention
    Money shall be certified by the Engineer for
    payment to the contractor. The expression
    expiration of the Defect Liability Period shall
    for the purpose of the clause, be deemed to mean
    the expiration of the latest of such periods
    provided also that if at such time there shall
    remain to be executed by the contractor any work
    instructed, pursuant to clause 49 and 50 in
    respect of the works the Engineer shall be
    entitled to withhold certification until
    completion of such work.

71
  • CORRECTION OF CERTIFICATES
  • The Engineer May in any interim Payment
    Certificate carryout any correction or
    modification in any previous Interim Payment
    Certificate.
  • STATEMENT AT COMPLETION
  • Not later than 84 days after the issue of the
    Taking-Over Certificate in respect of the whole
    of the works, the contractor shall submit to the
    Engineer six copies of Statement of completion
    showing in detail,
  • a) The final value of all work done
  • b) Any further sums which the contractor
    considerers to be due and
  • c) An estimate of amount which contractor
    considers will become due. The engineer shall
    certify payment
  • FINAL STATEMENT
  • Not later than 56 days after the issue of Defect
    Liability Certificate the contractor shall submit
    to the Engineer for six copies of draft final
    statement showing in detail.
  • a) The value of all the work done in accordance
    with the contract
  • b) Any further sum which contractor consider to
    be due to him. If the Engineer disagree or
    cannot verify any part of draft final statement,
    contractor shall submit any further information
    required.
  • The Engineer shall deliver to the Employer an
    Interim Payment Certificate for those part of the
    draft final statement, which are not in dispute.

72
  • DISCHARGE
  • Upon submission of final statement, the
    contractor shall give to the Employer, written
    discharge confirming that the total of the final
    statement represent full and final settlement of
    all monies due to the contractor. Provided that
    such discharge become effective only after
    payment due under the final payment certificate
    has been paid to the contractor and the
    performance security is returned.
  • FINAL PAYMENT CERTIFICATE
  • Within 28 days after receipt of final statement,
    and written discharge the Engineer shall issue a
    final payment certificate stating
  • a) The amount which is finally due under the
    contract .
  • b) After giving credit to Employer for all
    amount previously paid other than under clause 47
    and all sums to which Employer is entitled under
    the contract.
  • CESSATION OF EMPLOYERS LIABILITY
  • The employer shall not be liable to the
    contractor connection with the contract or
    execution of the work unless the contractor shall
    have included a claim in respect thereof in his
    final statement.
  • TIME OF PAYMENT
  • i. The amount due to the Contractor under any
    interim Certificate issued by the Engineer be
    paid by Employer to the contractor within 56
    days.
  • ii. Final payment Certificate within 56 days
    after such Final Payment Certificate has been
    delivered to the Employer. In the event of the
    failure of employer to make the payment within
    the time stated the Employer shall pay
    contractor interest at the rate stated in
    appendix to tender
Write a Comment
User Comments (0)
About PowerShow.com