Title: CONSTRUCTION CONTRACTS DOCUEMENTS
1CONSTRUCTION CONTRACTS DOCUEMENTS
BYLECTURERMaha Muhaisen
- APPLIED CIVIL ENGINEERING DEPT
2General Conditions of contract
- The conditions are intended to govern and
regulate the obligation of formal contract. - Although the headings and topics included within
different sets of GCC vary, there is a certain
similarity of subject matter
3Contents of GCC
- Definitions
- Contract documents
- Rights and responsibilities of owner
- Duties and authorities of engineer
- Rights and responsibilities of contractor
- Sub-contractor, Separate contractors
- Time
- Payments and completions
- Changes in the work
- Protection of persons and property
- Insurance and bond
- Disputes
- Termination of contract
- Miscellaneous provisions
4FIDIC , AN INTRODUCTION
- Founded in 1913
- Expanded in 1945 to include 40 national
associations - Published first Conditions of Contract in 1957
- In 2004 has 64 member associations
- Headquarters in Switzerland
- Web Site www.fidic.org
5FIDIC , AN INTRODUCTION
- Pre 1957 no internationally recognised contract
conditions - First red book based on UK ICE conditions
- FIDIC has international committees to improve
contracts
6Contract Documents 1999
- Conditions of Contract for Construction (Red
Book) - Conditions of Contract for Plant Design Build
(Yellow Book) - Conditions of Contract for EPC Turnkey Projects
(Silver Book) - Short Form of Contracts (Green Book)
7FIDIC Document UsageConditions of Contract for
Construction
- Works designed by Employer or Engineer
- Contractor Constructs in accordance with designs
provided - May include some design elements
8 FIDIC Document UsageConditions of Contract
for, Plant Design Build
- Electrical Mechanical Plant
- May include building and engineering
- Design Execution of works
- Contractor designs and constructs in accordance
with Employers Requirements - Engineer Administers
9FIDIC Document UsageShort Form of Contract
- Small capital value projects
- Simple content
- Contractor constructs to Employers designs
- No Particular Conditions
- No Impartial Engineer
10Typical sequence of Principal Events during
Contracts
11Typical sequence of Payment Events envisaged in
Clause 14(contract price and payment)
12Typical sequence of Dispute Events envisaged in
Clause 20
DAB the persons so named in the contract or
other persons appointed under sub-clause
(appointment of the dispute adjudication board)
13FIDIC conditions of contract
- 1 GENERAL PROVISIONS
- 2 THE EMPLOYER .
- 3 THE ENGINEER
- 4 THE CONTRACTOR
- 5 NOMINATED SUBCONTRACTORS
- 6 STAFF AND LABOUR
- 7 PLANT, MATERIALS AND WORKMANSHIP
- 8 COMMENCEMENT, DELAYS AND SUSPENSION
- 9 TESTS ON COMPLETION
- 10 EMPLOYERS TAKING OVER .
- 11 DEFECTS LIABILITY
- 12 MEASUREMENT AND EVALUATION
14FIDIC conditions of contract (contd)
- 13 VARIATIONS AND ADJUSTMENTS
- 14 CONTRACT PRICE AND PAYMENT
- 15 TERMINATION BY EMPLOYER
- 16 SUSPENSION AND TERMINATION BY CONTRACTOR
- 17 RISK AND RESPONSIBILITY
- 18 INSURANCE
- 19 FORCE MAJEURE
- 20 CLAIMS, DISPUTES AND ARBITRATION
15FIDIC conditions of contract
- 1 GENERAL PROVISIONS
- 1.1 Definitions
- 1.2 Interpretation
- 1.3 Communications
- 1.4 Law and Language
- 1.5 Priority of Documents
- 1.6 Contract Agreement
- 1.7 Assignment
- 1.8 Care and Supply of Documents
- 1.9 Delayed Drawings or Instructions
- 1.10 Employers Use of Contractors Documents
- 1.11 Contractors Use of Employers Documents
- 1.12 Confidential Details
- 1.13 Compliance with Laws
- 1.14 Joint and Several Liability
16FIDIC conditions of contract contd
- 2 THE EMPLOYER .
- 2.1 Right of Access to the Site
- 2.2 Permits, Licenses or Approvals
- 2.3 Employers Personnel
- 2.4 Employers Financial Arrangements
- 2.5 Employers Claims
- 3 THE ENGINEER
- 3.1 Engineers Duties and Authority
- 3.2 Delegation by the Engineer
- 3.3 Instructions of the Engineer
- 3.4 Replacement of the Engineer
- 3.5 Determinations
17FIDIC conditions of contract contd
- 4 THE CONTRACTOR
- 4.1 Contractors General Obligations
- 4.2 Performance Security
- 4.3 Contractors Representative
- 4.4 Subcontractors
- 4.5 Assignment of Benefit of Subcontract
- 4.6 Co-operation
- 4.7 Setting Out
- 4.8 Safety Procedures
- 4.9 Quality Assurance
- 4.10 Site Data
- 4.11 Sufficiency of the Accepted Contract Amount
- 4.12 Unforeseeable Physical Conditions
- 4.13 Rights of Way and Facilities
18- 4.14 Avoidance of Interference
- 4.15 Access Route
- 4.16 Transport of Goods
- 4.17 Contractors Equipment
- 4.18 Protection of the Environment
- 4.19 Electricity, Water and Gas
- 4.20 Employers Equipment and Free-Issue Material
- 4.21 Progress Reports
- 4.22 Security of the Site
- 4.23 Contractors Operations on Site
- 4.24 Fossils
19- 5 NOMINATED SUBCONTRACTORS
- 5.1 Definition of nominated Subcontractor
- 5.2 Objection to Nomination
- 5.3 Payments to nominated Subcontractors
- 5.4 Evidence of Payments
20- 6 STAFF AND LABOUR
- 6.1 Engagement of Staff and Labour
- 6.2 Rates of Wages and Conditions of Labour
- 6.3 Persons in the Service of Employer
- 6.4 Labour Laws
- 6.5 Working Hours
- 6.6 Facilities for Staff and Labour
- 6.7 Health and Safety
- 6.8 Contractors Superintendence
- 6.9 Contractors Personnel
- 6.10 Records of Contractors Personnel and
Equipment - 6.11 Disorderly Conduct
- 6.12 Foreign Personnel
- 6.13 Supply of Foodstuffs
21- 6.14 Supply of Water
- 6.15 Measures against Insect and Pest Nuisance
- 6.16 Alcoholic Liquor or Drugs
- 6.17 Arms and Ammunition
- 6.18 Festival and Religious Customs
- 6.19 Funeral Arrangements
- 6.20 Prohibition of Forced or Compulsory Labor
- 6.21 Prohibition of Harmful Child Labour
- 6.22 Employment Records of Workers
22- 7 PLANT, MATERIALS AND WORKMANSHIP
- 7.1 Manner of Execution
- 7.2 Samples
- 7.3 Inspection
- 7.4 Testing
- 7.5 Rejection
- 7.6 Remedial Work
- 7.7 Ownership of Plant and Materials
- 7.8 Royalties
- 8 COMMENCEMENT, DELAYS AND SUSPENSION
- 8.1 Commencement of Works
- 8.2 Time for Completion
- 8.3 Programme
- 8.4 Extension of Time for Completion
- 8.5 Delays Caused by Authorities
- 8.6 Rate of Progress
- 8.7 Delay Damages
23- 8.8 Suspension of Work
- 8.9 Consequences of Suspension
- 8.10 Payment for Plant and Materials in Event of
Suspension - 8.11 Prolonged Suspension
- 8.12 Resumption of Work
- 9 TESTS ON COMPLETION
- 9.1 Contractors Obligations
- 9.2 Delayed Tests
- 9.3 Retesting
- 9.4 Failure to Pass Tests on Completion
- 10 EMPLOYERS TAKING OVER
- 10.1 Taking Over of the Works and Sections
- 10.2 Taking Over of Parts of the Works
- 10.3 Interference with Tests on Completion
- 10.4 Surfaces Requiring Reinstatement
24- 11 DEFECTS LIABILITY
- 11.1 Completion of Outstanding Work and Remedying
Defects - 11.2 Cost of Remedying Defects
- 11.3 Extension of Defects Notification Period
- 11.4 Failure to Remedy Defects
- 11.5 Removal of Defective Work
- 11.6 Further Tests
- 11.7 Right of Access
- 11.8 Contractor to Search
- 11.9 Performance Certificate
- 11.10 Unfulfilled Obligations
- 11.11 Clearance of Site
25- 12 MEASUREMENT AND EVALUATION .
- 12.1 Works to be Measured
- 12.2 Method of Measurement
- 12.3 Evaluation
- 12.4 Omissions
- 13 VARIATIONS AND ADJUSTMENTS
- 13.1 Right to Vary
- 13.2 Value Engineering
- 13.3 Variation Procedure
- 13.4 Payment in Applicable Currencies
- 13.5 Provisional Sums
- 13.6 Daywork
- 13.7 Adjustments for Changes in Legislation
- 13.8 Adjustments for Changes in Cost
26- 14 CONTRACT PRICE AND PAYMENT
- 14.1 The Contract Price
- 14.2 Advance Payment
- 14.3 Application for Interim Payment Certificates
- 14.4 Schedule of Payments
- 14.5 Plant and Materials intended for the Works
- 14.6 Issue of Interim Payment Certificates
- 14.7 Payment
- 14.8 Delayed Payment
- 14.9 Payment of Retention Money
- 14.10 Statement at Completion
- 14.11 Application for Final Payment Certificate
- 14.12 Discharge
- 14.13 Issue of Final Payment Certificate
- 14.14 Cessation of Employers Liability
- 14.15 Currencies of Payment
27- 15 TERMINATION BY EMPLOYER
- 15.1 Notice to Correct
- 15.2 Termination by Employer
- 15.3 Valuation at Date of Termination
- 15.4 Payment after Termination
- 15.5 Employers Entitlement to Termination for
Convenience - 15.6 Corrupt or Fraudulent Practices
28- 16 SUSPENSION AND TERMINATION BY CONTRACTOR
- 16.1 Contractors Entitlement to Suspend Work
- 16.2 Termination by Contractor
- 16.3 Cessation of Work and Removal of
Contractors Equipment - 16.4 Payment on Termination
- 17 RISK AND RESPONSIBILITY
- 17.1 Indemnities
- 17.2 Contractors Care of the Works
- 17.3 Employers Risks
- 17.4 Consequences of Employers Risks
- 17.5 Intellectual and Industrial Property Rights
- 17.6 Limitation of Liability
- 17.7 Use of Employers Accommodation/Facilities
29- 18 INSURANCE
- 18.1 General Requirements for Insurances
- 18.2 Insurance for Works and Contractors
Equipment - 18.3 Insurance against Injury to Persons and
Damage to Property - 18.4 Insurance for Contractors Personnel
- 19 FORCE MAJEURE
- 19.1 Definition of Force Majeure
- 19.2 Notice of Force Majeure
- 19.3 Duty to Minimize Delay
- 19.4 Consequences of Force Majeure
- 19.5 Force Majeure Affecting Subcontractor
- 19.6 Optional Termination, Payment and Release
- 19.7 Release from Performance
30- 20 CLAIMS, DISPUTES AND ARBITRATION
- 20.1 Contractors Claims
- 20.2 Appointment of the Dispute Board
- 20.3 Failure to Agree on the Composition of the
Dispute Board - 20.4 Obtaining Dispute Boards Decision
- 20.5 Amicable Settlement
- 20.6 Arbitration
- 20.7 Failure to Comply with Dispute Boards
Decision - 20.8 Expiry of Dispute Boards Appointment
31General conditions
- The following are main items that include in the
general conditions for the tender ( or the
construction contract.
32Definitions
- Main definitions related to
- Contract include contract agreement, letter of
acceptance, letter of tender, specifications,
drawings, schedules, tender, appendix to tender,
bill of quantities. - parties and persons party, employer,
contractor, engineer, contractor representative,
employers' personnel, contractors personnel, sub-
contractor, DAB (dispute adjudication board),
Fidic. - Dates , tests, periods and completion include
base date, commencement date, time of completion,
test on completion, taking over certificate,
defects notification period, performance
certificate, day - Money and payment accepted contract amount,
contract price, cost, final , interim payment
certificate, currency, provisional sum, retention
money,
33 Definitions
- The main definitions that are included in and
repeated in the articles of general conditions,
are - Employer The party named in the Contract as the
"FIRST PARTY" who will enter into contract with
the Contractor for the execution of the Works
covered by the Contract, or any other party
authorized by the Employer to exercise the powers
and obligations of the First Party, provided that
the Contractor will be informed accordingly in
writing . - Contractor The person, company or joint venture
named as Second Party in the Contract whose
Tender has been accepted by the Employer and with
whom the Employer has entered into Contract, and
includes the Contractors personal agents and his
legal successors - Engineer The Consulting office, or Engineering
office or Engineer or any other technical body
appointed from time to time by the Employer to
exercise in whole or in part the powers of the
Engineer in accordance with the Conditions of the
Contract provided that the Contractor shall be
accordingly notified in writing.
34Definitions, Contd
- Engineers Representative - Any resident engineer,
or clerk of works appointed by the Engineer from
time to time - Contract - The documents constituting these
Conditions (Parts I and II), the Specification,
the Drawings, the Bill of Quantities, the Tender,
the Letter of Acceptance, the Contract Agreement,
and such further documents as may be expressly
incorporated in the Letter of Acceptance or
Contract Agreement (if completed). - Contract Sum - The sum stated in the Letter of
Acceptance as payable to the Contractor for the
execution and completion of the Works and the
remedying of any defects therein in accordance
with the provisions of the Contract, subject to
such additions thereto or deductions therefore as
may be made under the provisions of the Contract. - Equipment is the Contractors machinery and
vehicles brought temporarily to the Site to
construct the Works. - Site - The land and other places provided by the
Employer or designated as such where the Works
are to be executed, and any other places
specifically designated in the Contract as
forming part of the Site. - approval (written approval)
- time (calendar / working days)
35Engineer's Duties and Authority
- a) The Engineer shall carry out the duties
specified in the Contract . - b) The Engineer shall exercise the authority
specified in or necessarily to be implied from
the Contract . - Provided, that the Engineer shall obtain the
specific approval of the Employer, in compliance
with the terms of his appointment, and after
submitting his recommendations to the Employer in
writing, in the following matters - issuing variation orders
- deciding on the extension of Time for Completion
and applying the Liquidated Damages Clause - approving the appointment of Subcontractors
- notifying the Contractor on suspension of Works
and any other matters as may be set out in Part
II of these conditions). - (c) Except as expressly stated in the Contract,
the Engineer shall have no authority to relieve
the Contractor of any of his obligations under
the Contract
36- Engineer's Representative
- The Engineer's Representative shall be appointed
by and be responsible to the Engineer and shall
carry out such duties of watching and supervising
the execution and workmanship of the Works and to
test and examine any materials to be used or
workshop employed in connection with the Works.
He shall exercise such authority as may be
delegated to him by the Engineer
37- Engineer's Authority to Delegate
- The Engineer may from time to time delegate to
the Engineer's Representative any of the duties
and authorities vested in the Engineer and he may
at any time revoke such delegation. Any such
delegation or revocation shall be in writing and
shall not take effect until a copy thereof has
been delivered to the Employer and the Contractor
. - Any communication given by the Engineer's
Representative to the Contractor in accordance
with such delegation shall have the same effect
as though it had been given by the Engineer - Provided that
- any failure of the Engineer's Representative to
disapprove any work, materials or Plant shall not
prejudice the authority of the Engineer to
disapprove such work, material or Plant and to
give instructions for the rectification thereof - if the Contractor questions any communication of
the Engineers Representative, he may refer the
matter to the Engineer who shall confirm, reverse
or vary the contents of such communication .
38Contractors General Obligations
- The Contractor shall design (to the extent
specified in the Contract), execute and complete
the Works in accordance with the Contract and
with the Engineers instructions, and shall
remedy any defects in the Works. - The Contractor shall provide the Plant and
Contractors Documents specified in the Contract,
and all Contractors Personnel, Goods,
consumables and other things and services,
whether of a temporary or permanent nature,
required in and for this design, execution,
completion and remedying of defects. - The Contractor shall be responsible for the
adequacy, stability and safety of all Site
operations and of all methods of construction.
Except to the extent specified in the Contract,
the Contractor - shall be responsible for all Contractors
Documents, Temporary Works, and such design of
each item of Plant and Materials as is required
for the item to be in accordance with the
Contract, and - shall not otherwise be responsible for the design
or specification of the Permanent Works.
39Contractors General Obligations,
- The Contractor shall, whenever required by the
Engineer, submit details of the arrangements and
methods which the Contractor proposes to adopt
for the execution of the Works. No significant
alteration to these arrangements and methods
shall be made without this having previously been
notified to the Engineer. - If the Contract specifies that the Contractor
shall design any part of the Permanent Works,
then unless otherwise stated in the Particular
Conditions - the Contractor shall submit to the Engineer the
Contractors Documents for this part in
accordance with the procedures specified in the
Contract - these Contractors Documents shall be in
accordance with the Specification and Drawings,
shall be written in the language for
communications
40ASSIGNMENT AND SUBCONTRACTINGASSIGNMENT AND
SUBCONTRACTING
- Assignment of Contract
- The Contractor shall not, without the prior
consent of the Employer, assign the Contract or
any part thereof, or benefit or interest therein
or thereunder, otherwise than by - a charge in favor of the Contractor's bankers of
any moneys due or to become due under the
Contract, or - assignment to the Contractor's insurers of the
Contractor's right to obtain relief against any
other party liable. - Subcontracting
- The Contractor shall not subcontract the whole
of the Works. Except where otherwise provided by
the Contract, the Contractor shall not
subcontract any part of the Works without the
prior consent of the Engineer. Any such consent
shall not relieve the Contractor from any
liability or obligation under the Contract and he
shall be responsible for the acts, defaults and
neglects of any Subcontractor, his agents,
servants or workmen as fully as if they were the
acts, defaults or neglects of the Contractor, his
agents, servants or workmen. - Provided that the Contractor shall not be
required to obtain such consent for - (a) the provision of labor, or
- (b) the subcontracting of any part of the Works
for which the Subcontractor is named in the
Contract.
41- Assignment of Subcontractor's Obligations
- In the event of a Subcontractor having
undertaken towards the Contractor in respect of
the work executed, or the goods, materials, Plant
or services supplied by such Subcontractor, any
continuing obligation extending for a period
exceeding that of the Defects Liability Period
under the Contract, the Contractor shall at any
time, after the expiration of such Period, assign
to the Employer, at the Employer's request and
cost, the benefit of such obligation for the
unexpired duration thereof.
42Language and Law
- Arabic language shall be the ruling language
of the Contract Documents unless stated otherwise
in these conditions, and consequently all
correspondence, payment statements, and take-over
certificates shall be drawn in this language.
43Priority of Contract Documents
- The several documents forming the Contract are
to be taken as mutually explanatory of one
another, but in case of ambiguities or
discrepancies the same shall be explained and
adjusted by the Engineer who shall thereupon
issue to the Contractor instructions thereon and
in such event, unless otherwise provided in the
Contract, the priority of the documents forming
the Contract shall be as follows - (1) The Contract Agreement (if completed)
- (2) The Letter of Acceptance
- (3) The Tender
- (4) Part II of these Conditions
- (5) Part I of these Conditions and
- (6) Any other document forming part of the
Contract.
44Performance Security
- The Contractor, upon receiving the Letter of
Acceptance, shall obtain and provide to the
Employer before signing the Contract, the
Performance Guarantee in the value of ten percent
of the Contract Sum, as a guarantee of the proper
execution of the Works in accordance with the
Contract. This guarantee shall be issued by a
licensed bank or financial institution acceptable
to the Employer. The guarantee shall be prepared
in the form included in part B of these
conditions. The obtaining of such guarantee
shall in all respects be at the expense of the
Contractor.
45Inspection of Site
- The Employer shall have made available to the
Contractor, before the submission by the
Contractor of the Tender, such data on
hydrological and sub - surface conditions as have
been obtained by or on behalf of the Employer
from investigations undertaken relevant to the
Works but the Contractor shall be responsible for
his own interpretation thereof. - The Contractor shall be deemed to have inspected
and examined the Site and its surroundings and
information available in connection therewith and
to have satisfied himself (so far as time is
practicable), before submitting his Tender, as to
- (a) the form and nature thereof, including the
sub - surface conditions, - (b) the hydrological and climate conditions,
- (c) the extent and nature of work and materials
necessary for the execution and completion of the
Works and the remedying of any defects therein,
and - (d) the means of access to the Site and the
accommodation he may require and, in general,
shall be deemed to have obtained all necessary
information, subject as above mentioned, as to
risks, contingencies and all other circumstances
which may influence or affect his Tender. - The Contractor shall be deemed to have based on
his Tender, the data made available by the
Employer and on his own inspection and
examination, all as aforementioned.
46Sufficiency of Tender
- The Contractor shall be deemed to have satisfied
himself as to the correctness and sufficiency of
the Tender and of the rates and prices stated in
the Bill of Quantities, all of which shall
except insofar as it is otherwise provided in the
Contract, cover all his obligations under the
Contract (including those in respect of the
supply of goods, materials, Plant or services or
of contingencies for which there is a Provisional
Sum) and all matters and things necessary for the
proper execution and completion of the Works and
the remedying of any defects therein.
47PROGRAMME TO BE SUBMITTED
- Within a specified time (in days), after the
date of the Letter Of Acceptance, the contractor
shall submit a programme to the engineer for his
consent in such a way and detail as the engineer
shall reasonable prescribe for the execution of
the works. It is also required that whenever
the engineer requires, the contractor shall
provide in writing, for his information, a
general description of the arrangement and
methods which the contractor proposes to adopt
for the execution of the works.
48REVISED PROGRAMME
- If it appears to the engineer, at any time, that
the actual progress of the works does not conform
to the progamme to which consent, is given the
contractor at the request of the engineer, is
required to produce a revised programme necessary
to ensure completion of the works within the Time
for Completion.
49CASHFLOW ESTIMATE
- The contractor shall within time stated in Part
II provide a detailed cash flow estimate, in
quarterly period, for all payments to which the
contractor will be entitled under the contract
(to the engineer) and the contractor shall
subsequently supply revised cash flow estimates
at quarterly intervals, if required to do so by
the engineer. - Such cash flow statements do not relieve the
contractor of any of this duties or
responsibilities under the contract.
50- CONTRACTORS SUPERINTENDENCE
- The contractor is needed to provide all
necessary superintendence during the execution of
the work and thereafter, as long as the engineer
consider it necessary for proper fulfillment of
the contractors obligations under the contract. - If the approval of Contractors representative
is withdrawn by the Engineer then Contractor
shall replace him by any other representative
approved by the Engineer. - CONTRACTORS EMPLOYEES
- The contractor shall provide on the site only
skilled and experienced technical assistants and
foremen to provide proper superintendence to
skilled, semiskilled and unskilled labour as is
necessary. - ENGINEER AT LIBERTY TO OBJECT
- The Clients engineer having objection on the
contractors worker when they misconduct
themselves, or are incompetent or negligent in
the proper performance of his duties. Such
workers should be replaced as soon as possible. - SETTING OUT
- The contractor has to look after about the
accurate setting out of the works and the
provision of all necessary instruments,
appliances and labour in connection with the
foregoing responsibilities. - The contractor shall rectify any error if caused
regarding setting out unless it was caused due to
incorrect data provided by Engineer in writing.
51INSURANCE
- The Contractor shall insure the following
- The full replacement cost for the plant and
materials to be incorporated in the works plus 15
percent of the full replacement cost - in addition to be insured for the additional
costs like rectification of loss or damage,
Professional fees, Demolishing cost and removing
the debris from the work. - The Contractors Equipment and other things
brought to the site for a sum sufficient for its
replacement.
52- SCOPE OF COVER
- For the cases mentioned the insurance will be in
the joint names of the contractor and the
employer, and shall cover - (a) the employer and the contractor against all
loss or damage other than force Majeure causes
stated below from start of work till take over
by Employer. - (b) the contractor during Defects Liability
Period for loss or damage caused prior to
beginning of Defects Liability Period. - EXCLUSIONS
- There shall be no obligation of insurance to
cover force Mejure issues such as - War, Hostilities, Invasion, Act of Foreign
enemies. - Rebellion, Revolution, Insurrection, Military or
usurped power or civil war. - ionizing radiation, Contamination by
radioactivity - Pressure waves from aircraft or other aerial
devices
53- DAMAGE TO PERSONS AND PROPERTY
- The Contractor indemnifies and holds harmless,
the Employer on following issues. - a) Death of or Injury to any person or
- Loss of or damage to any property other than
Works which may arise out of execution and
completion of the works, subject to following
exceptions - EXCEPTIONS
- The exceptions referred above are
- a) The permanent use or occupation of land by the
works. - b) The right of employer to execute the works
over under or through the land. - c) Damage to the property during the execution of
the work if the damage is unavoidable in the
process of execution and remedying the defects as
per the Contract. - d) Damage to property and persons who are either
injured or dead because of any act or neglect of
the Employer, his agents, other Contractors who
are not directly employed by the contractor. - The Employer shall indemnify the Contractor
against all claims arising out of exceptions
provided in the contract. - THIRD PARTY INSURANCE
- The Contractor shall insure in the joint names
of the Employer and himself, without limiting
his or Employer obligations and responsibilities,
against injury or death to any person, loss or
damages to the property arising out of the
performance of contract. This insurance is not
to cover the exceptions above
54- THIRD PARTY INSURANCE
- The Contractor shall insure in the joint names
of the Employer and himself, without limiting
his or Employer obligations and responsibilities,
against injury or death to any person, loss or
damages to the property arising out of the
performance of contract. MINIMUM AMOUNT OF
INSURANCE - The insurance made shall be for at least the
amount specified in the appendix of the Tender.
55SUSPENSION
- The Contractor shall, on the instructions of the
Engineer, suspend the progress of the Works or
any part thereof for such time and in such manner
as the Engineer may consider necessary and shall,
during such suspension, properly protect and
secure the Works or such part thereof so far as
is necessary in opinion of the Engineer. Unless
such suspension is - a) otherwise provided for in the Contract, or
- b) necessary by reason of some default of or
breach of contract by the Contractor or for which
he is responsible, or - (c) necessary by reason of climatic conditions on
the Site, or - (d) necessary for the proper execution of the
Works or for the safety of the Works on any part
thereof (save to the extent that such necessity
arises from any act or default by the Engineer or
the Employer or from any of the risks defined in
GCC), or - (e) by mutual agreement in writing by both
parties to the Contract, provided that the
Employer shall not suffer the expenses resulting
from such suspension, provided always that the
Contractor shall not be entitled to recover any
such extra expenses unless he gives to the
Engineer written notice of his intention to claim
within (28) days of the Engineers order,
56- Engineer's Determination Following Suspension
- The engineer shall after consulting the
contractor and the employer determine, - - Any extension of time
- - The amount to be added to the contract price,
due to suspension. - Suspension Of Work For More Than 84 Days
- If the progress of the work is suspended for
more than 84 days then the contractor can give a
notice for resumption of work within 28 days of
receipt of order. If permission for resumption
is not given within the said period then the
contractor can consider it as termination of
contract.
57Time for Completion
- The whole of the Works and, required to be
completed within a particular time as stated in
the Appendix to Tender, shall be completed,,
within the time stated in the Appendix to Tender
for the whole of the Works or the Section (as the
case may be), calculated from the Commencement
Date, or such extended time as may be allowed
under next clauses. - No mobilisation period will be allowed for as an
extension of the Completion Time, as such period
is considered to be included in it.
58Extension of Time for Completion
- In the event of
- (a) the amount or nature of extra or additional
work, or - (b) any cause of delay referred to in these
Conditions, or - (c) exceptionally adverse climatic condition (but
no extension of time shall be granted for the
anticipated climatic changes), or - (d) any delay, impediment or prevention by the
Employer, or - (e) other special circumstances which may occur,
other than through a default of or breach of
contract by the Contractor or for which he is
responsible, being such as fairly to entitle the
Contractor to an extension of the Time for
Completion of the Works, or any Section or part
thereof, the Engineer shall, after due
consultation with the Employer and the
Contractor, determine the amount of such
extension and shall notify the Contractor
accordingly, with a copy to the Employer.
59Contractor to Provide Notification and Detailed
Particulars
- The Engineer is not bound to make any
determination unless the Contractor has - (a) within 28 days after such event has first
arisen notified the Engineer with a copy to the
Employer, and - (b) within 28 days, or such other reasonable time
as may be agreed by the Engineer, after such
notification submitted to the Engineer detailed
particulars of any extension of time to which he
may consider himself entitled in order that such
submission may be investigated at the time.
60Interim Determination of Extension
- If it is impracticable for contractor to provide
details of delay within 28 days, the extension
shall still be granted, if contractor can provide
interim details. But the full details of event
need to be provided within 28 days of the end of
the effects resulting from events.
61Liquidated Damages for Delay
- If the Contractor fails to comply with the Time
for Completion, for the whole of the Works or, if
applicable, then the Contractor shall pay to the
Employer the relevant sum stated in the Appendix
to Tender as liquidated damages for such default
and not as a penalty for every day or part of a
day which shall elapse between the relevant Time
for Completion and the date stated in a
Taking-Over Certificate of the whole of the Works
or the relevant Section, subject to the
applicable limit stated in the Appendix to
Tender. - The Employer may, without prejudice to any other
method of recovery, deduct the amount of such
damages from any moneys due or to become due to
the Contractor. The payment or deduction of such
damages shall not relieve the Contractor from his
obligation to complete the Works, or from any
other of his obligations and liabilities under
the Contract. - The rate of liquidated damages stated in the
Appendix to Tender is exclusive of any additional
supervision costs in respect of the unjustified
time lapse in completing the Works, and the
Contractor shall bear such costs.
62Reduction of Liquidated Damages
- If, before the Time for Completion of the whole
of the Works or, if applicable, any Section, a
Taking-Over Certificate has been issued for any
part of Works or of a Section, the liquidated
damages for delay in completion of the remainder
of the Works or of that Section shall, for any
period of delay after the date stated in such
Taking-Over Certificate, and in the absence of
alternative provision in the Contract, be reduced
in the proportion which the value of the part so
certified bears to the value of the whole of the
Works or Section, as applicable. -
- The provisions of this Clause shall only apply to
the rate of liquidated damages and shall not
affect the limit thereof.
63Taking-Over Certificate
- When the whole of the Works have been
substantially completed and have satisfactorily
passed any Tests on Completion prescribed by the
Contract, the Contractor may give a notice to
that effect to the Engineer, with a copy to the
Employer, accompanied by a written undertaking to
finish with due expedition any outstanding work
during the Defects Liability Period. Such notice
and undertaking shall be deemed to be a request
by the Contractor for the Engineer to issue a
Taking-Over Certificate in respect of the Works. - The Engineer shall conduct an inspection of the
Works and report his findings to the Employer
with a copy to the Contractor. The Engineer may
either certify that the works have been properly
completed or ready for acceptance or give
instructions in writing to the Contractor specify
the works which, in the opinion of the Engineer,
require to be done by the Contractor and to the
Engineer's satisfaction, within a prescribed
period of time before acceptance. If the
contractor considers the Engineer's report to be
incorrect, he may give a notice to that effect to
the Employer, who shall, in the manner he deems
suitable either investigate the situation to
ascertain the validity of the Engineer's report
or form a Committee for the Taking-Over of the
Works.
64- The Employer shall, within ten days from receipt
of the Engineer's report, form a "Taking-Over
Committee", including the Engineer as one of its
members, and notify the Contractor of the time
and date fixed for carrying out an inspection of
the Works. The Engineer and the Contractor shall,
in the meanwhile, prepare all necessary
schedules, data, bills and drawings as are
necessary to facilitate the said Committees
work. - The Committee shall, within ten days from the
date of being formed, conduct in the presence of
the Contractor or his authorised agent an
inspection of the Works, and having done so,
shall draw up a memorandum of certification of
the Works which shall be signed by the Committee
members as well as by the Contractor or his
authorised agent. Copies of the same shall be
given to the Employer and the Contractor. - The Engineer shall within seven days of the date
of delivery of the memorandum of the Taking-Over
Committee to the Contractor, issue a Taking-Over
Certificate in respect of the Works, stating the
date on which, in his opinion, the Works are
considered to be substantially completed in
accordance with the Contract and the date of
commencement of the Defects Liability Period. The
Engineer shall enumerate in the Taking-Over
Certificate all defects and faults to be remedied
by the Contractor within a prescribed time
starting from the start of the Maintenance
Period. - The Contractor is entitled to comment or object
to the memorandum of the Taking-over Committee in
writing to the Engineer, provided he does so
within (7) days from the date of signing the
memorandum. The Engineer, in such a case, shall
study the objection and submit his findings to
the Employer.
65Variations
- If the Engineer feels the necessity to make any
variations of the form, quality or quantity of
the Works he has the authority to instruct the
Contractor to do so and the Contractor shall do
any of the following - a) Increase or decrease the quantity of any work
included in the contract. - b) Omit any such work (but not if the omitted
work is to be carried out by the Employer or by
another contractor). - c) Change the character or quality or kind of
any such work. - d) Change the levels, lines, position and
dimensions of any part of the works. - e) Execute additional work of any kind necessary
for the completion of the works. - f) Change sequence or timing of construction.
- Note
- Max Allowable variation by Fidic is 15, but in
Palestinian Contracting contract is 20.
66- INSTRUCTIONS FOR VARIATIONS
- The Contractor is not supposed to make any
variation without an instruction of the Engineer.
No instructions are required if work execution
results into increase/decrease of quantities than
those stated in the Bill of quantities. - VALUATION OF VARIATIONS
- All variations and any additions to the Contract
Price shall be as per the rates and price of
variations present in the Contract. If the
Contract does not contain any rates or prices
applicable to varied work, the rates and prices
of the Contract shall be used as the basis for
valuation. In the event of disagreement the
Engineer shall notify the Contractor with a copy
to the Employer. Till the time the rates are
agreed or fixed, the Engineer shall determine
provisional rates or prices to enable on-account
payments to be included in certificates issued
67- POWER OF ENGINEER TO FIX RATES
- The Engineer shall determine the rate for varied
work if existing rates in the contract are
inappropriate, in consultation with Employer and
Contractor. If agreement is not reached on the
rates, the engineer shall fix provisional rates
which are appropriate in his opinion, to enable
on account payment for payment certificates
issued under clause of payment, until such time
as rates or prices are agreed, provided
Contractor or engineer has given notice of 14
days to each other about their intention to seek
varied rates. - VARIATIONS EXCEEDING 15 PERCENT
- If, on the issue of the Taking-Over Certificate
for the Whole of the Works, it is found that as a
result of - a) All varied work valued (cases listed in the
start of variation) - b) all adjustments upon measurement of the
estimated quantities set out in the Bill Of
Quantities, excluding Provisional Sums, day works
and adjustments of price made under Clause of
increase or decrease of the cost (There shall be
increase/decrease in contract price based on rise
and fall in cost of labor and material as
provided in the part II of these conditions) that
the contract price has varied in excess of 15
then Engineer will decide increase/decrease to
contract price having regards to Contractors
site and general overhead cost. This change if
any shall be related to 15 excess level over
contract price. - DAY WORK
- The Engineer if he feels that it is necessary,
can issue a instruction that any varied work
shall be executed on a day work basis according
to the terms and conditions provided in the day
work schedule.
68PROVISIONAL SUM
- DEFINITION Provisional Sum means a sum (if
any) which is specified in the contract as a
provisional sum. Provisional Sum shall only be
used in whole or in part, in accordance with the
Engineers instructions and the Contract Price
shall be adjusted accordingly. - USE OF PROVISIONAL SUMS
- The engineer shall have authority to issue
instruction for the execution of work or for
supply of goods or services under provisional
sum.
69- MONTHLY STATEMENTS
- The contractor shall submit to the Engineer
after the end of each month six copies of
statements showing the amounts to which the
contractor considers himself to be entitled up to
the end of the month in respect of - a) The value of the permanent work.
- b) Any other item in the Bill of Quantities
including those for contractors equipment. - c) And plant delivery by the contractor on the
sire for incorporation in the permanent works but
not incorporated in such works. - d) Adjustment under the increase or decrease the
cost. - e) Any other sum to which the contractor may be
entitled under the contract.
70- MONTHLY PAYMENTS
- The Engineer shall, within 28 days of receiving
such statement, deliver to the employer an
interim payment certificate stating the amount
of payment due to the contractor subject. - a) Firstly to retention of the amount calculated
by applying the percentage of retention stated in
the appendix to tender until the amount so
retained reaches the limit or retention money
stated in the appendix to Tender. - b) Secondly to the deduction other than pursuant
to liquidated damages for delay of any sums which
may have become due and payable by the contractor
to the Employer. - Provided that the engineer shall not be bound to
certify any payment in the net amount thereof,
after the retention and deduction, would be less
than the minimum Amount of interim payment
certificate stated in the appendix to tender. - PAYMENT OF RETENTION MONEY
- a) Upon the issue of the taking-Over Certificate
with respect to the whole of the works, one half
of the retention money, shall be certified by the
Engineer for payment to the Contractor. - b) Upon the expiration of the Defect Liability
Period for the work other half of the Retention
Money shall be certified by the Engineer for
payment to the contractor. The expression
expiration of the Defect Liability Period shall
for the purpose of the clause, be deemed to mean
the expiration of the latest of such periods
provided also that if at such time there shall
remain to be executed by the contractor any work
instructed, pursuant to clause 49 and 50 in
respect of the works the Engineer shall be
entitled to withhold certification until
completion of such work.
71- CORRECTION OF CERTIFICATES
- The Engineer May in any interim Payment
Certificate carryout any correction or
modification in any previous Interim Payment
Certificate. - STATEMENT AT COMPLETION
- Not later than 84 days after the issue of the
Taking-Over Certificate in respect of the whole
of the works, the contractor shall submit to the
Engineer six copies of Statement of completion
showing in detail, - a) The final value of all work done
- b) Any further sums which the contractor
considerers to be due and - c) An estimate of amount which contractor
considers will become due. The engineer shall
certify payment - FINAL STATEMENT
- Not later than 56 days after the issue of Defect
Liability Certificate the contractor shall submit
to the Engineer for six copies of draft final
statement showing in detail. - a) The value of all the work done in accordance
with the contract - b) Any further sum which contractor consider to
be due to him. If the Engineer disagree or
cannot verify any part of draft final statement,
contractor shall submit any further information
required. - The Engineer shall deliver to the Employer an
Interim Payment Certificate for those part of the
draft final statement, which are not in dispute.
72- DISCHARGE
- Upon submission of final statement, the
contractor shall give to the Employer, written
discharge confirming that the total of the final
statement represent full and final settlement of
all monies due to the contractor. Provided that
such discharge become effective only after
payment due under the final payment certificate
has been paid to the contractor and the
performance security is returned. - FINAL PAYMENT CERTIFICATE
- Within 28 days after receipt of final statement,
and written discharge the Engineer shall issue a
final payment certificate stating - a) The amount which is finally due under the
contract . - b) After giving credit to Employer for all
amount previously paid other than under clause 47
and all sums to which Employer is entitled under
the contract. - CESSATION OF EMPLOYERS LIABILITY
- The employer shall not be liable to the
contractor connection with the contract or
execution of the work unless the contractor shall
have included a claim in respect thereof in his
final statement. - TIME OF PAYMENT
- i. The amount due to the Contractor under any
interim Certificate issued by the Engineer be
paid by Employer to the contractor within 56
days. - ii. Final payment Certificate within 56 days
after such Final Payment Certificate has been
delivered to the Employer. In the event of the
failure of employer to make the payment within
the time stated the Employer shall pay
contractor interest at the rate stated in
appendix to tender