Lockheed Martin Corporation: DTV Production Flow - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Lockheed Martin Corporation: DTV Production Flow

Description:

Dispenser Transport Vehicle (DTV) Prototype Construction 'Make it work' philosophy ... ADS DTV PDR (11Apr06) Project Deliverables. Further define the assembly ... – PowerPoint PPT presentation

Number of Views:132
Avg rating:3.0/5.0
Slides: 18
Provided by: wjse
Category:

less

Transcript and Presenter's Notes

Title: Lockheed Martin Corporation: DTV Production Flow


1
Lockheed Martin CorporationDTV Production Flow
  • Victoria Alvarado
  • Jordan McDonald
  • Laura Oquendo
  • Allison Shook
  • Megan Wolfe

2
Agenda
  • Company Background
  • Problem Formulation
  • Current Conditions
  • Analysis
  • Justifications
  • Final Recommendations

3
Company Background
  • Originally Perry Technologies (founder John
    Perry)
  • Invented one of the first submarines
  • Lockheed Martin Corporation
  • Maritime Systems and Sensors
  • Electronic Systems
  • Designs and manufactures prototype automated
    underwater vehicles (AUVs)
  • Ramping up to production on specific vehicles
  • Riviera Beach, FL
  • Contact
  • Kirsten Goerl

4
Problem Formulation
  • Advanced Deployable System
  • Array Installation Unit (AIM)
  • Dispenser Transport Vehicle (DTV)
  • Prototype Construction
  • Make it work philosophy
  • No set process for production

5
Project Deliverables
  • Further define the assembly flow of the build of
    the DTV
  • Segment the design into Subassembly and Install
    levels of integration
  • Estimate manufacturing hours for assembly of each
    section

6
Current Conditions
  • Riviera Beach is adjusting to a production
    environment
  • Engineers accustomed to designing prototypes
  • Prototype built in an inefficient and time
    consuming manner
  • At the time the prototype was built there was no
    defined production process.
  • Prototype built using the drawings as a reference
    and a make it work philosophy.
  • No set order of installation

7
Analysis
  • Production layout determined by the material flow
  • Material Control Kitting Dept Production
    Floor
  • Order of installation important
  • Small radius
  • Obstructions
  • Example Hub
  • Parts/Sections done in parallel
  • Forward and Aft Sections

8
Improvements
9
Improvements
10
Improvements
11
Layout- Aft Section
12
Layout- Forward Section
13
Human Factors
  • Anthropometric
  • Parts too heavy for average person to lift
  • Hands too small to install parts
  • Biomechanical
  • Sub-assemblies pushed and pulled together
  • Technicians backs were a concern
  • Physiological
  • Lifting parts repetitively affected the
    cardiovascular system
  • Psychomotor
  • Only diagrams and drawings are used for buildno
    text
  • Difficulty identifying some parts
  • Environmental
  • Large amount of space required due to its size
  • Air-conditioned area

14
Justifications
  • Technical
  • 4600 parts to 1705 parts
  • Ergonomic
  • Smaller workspace needed
  • Less complexity
  • Economic
  • Labor from 518.5 to 426.4 hours
  • Total savings 4,052.40 /vehicle
  • Not including part cost reduction

15
Final Recommendations
  • Use assembly flow
  • Follow schedule
  • Use production floor layout
  • Consider enforcing safety protocol
  • Wear safety glasses in designated areas
  • Make steel toe shoes available for all employees
    on production floor

16
Build Schedule
17
Questions?
Write a Comment
User Comments (0)
About PowerShow.com