Peabody Coal Lower Basin Pipeline - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Peabody Coal Lower Basin Pipeline

Description:

Listed species are for Coconino County under the Federal Endangered Species Act. ... to address project impacts to species on the Navajo Endangered Species List. ... – PowerPoint PPT presentation

Number of Views:88
Avg rating:3.0/5.0
Slides: 19
Provided by: klbl
Category:

less

Transcript and Presenter's Notes

Title: Peabody Coal Lower Basin Pipeline


1
Peabody Coal Lower Basin Pipeline
  • Engineering Appraisal Study
  • Bureau of Reclamation
  • September 18, 2002

2
Purpose and Scope
  • To develop alternatives to divert 5,700 and
    12,000 acre-feet of main stem Colorado River
    water from a point located downstream of Lee
    Ferry (0.0 mile), (including associated
    conveyance infrastructure necessary to deliver
    lower basin river water), to Kaibito, Arizona.

3
Objectives
  • To identify fatal flaws as related to the study
    purpose.
  • Develop conceptual alternatives

4
Assumptions
  • Final report of findings to be reviewed and
    completed by September 20, 2002.
  • Design for 5,700 and 12,000 acre-feet per year
    using a 1.2 peaking factor.
  • Use existing available data.
  • Study area limited to the corridor of land
    necessary for development of a diversion,
    storages, pipeline conveyance, right-of-way, and
    electrical infrastructure necessary to deliver
    water from the main stem Colorado River to the
    community of Kaibito, Arizona.
  • Right-of-Way cost to be determined by Navajo
    Nation. (not included in project cost estimate)

5
Investigations and Data
  • Conducted and over-flight of the project area.
  • Utilized Reclamations project database and made
    contacts with industry experts.
  • Accessed Grand Canyon Research and Monitoring
    Center database.
  • Obtained copies of completed studies in the
    project area and incorporated by reference.
  • All data utilized in the Report of Findings are
    suitable for conceptual Appraisal Level studies.

6
(No Transcript)
7
Alignment follows existing roadways
8
Alignment Profile3,097 to 5702 elevation
9
Infiltration Gallery
10
8.0 Mile Jackass CanyonDiversion Site
Infiltration gallery
11
Direction Drill _at_ Jackass Canyon
12
Second Direction Drill _at_ Echo Cliffs
13
Outlet of Direction Drill Hole at top of Echo
Cliffs
14
Engineering Hydraulics
The peaking factor is based on information
received from the Settlement Negotiation Team.
Assuming a 1.2 peaking factor, pumping occurs 20
out of 24 hours on the maximum day, the required
design flow is 11.23 cubic feet per second
(ft3/s) and 22.68 ft3/s, respectively.
15
PIPE TRENCHING COSTS Pipe Installation Item Unit
Cost (/cubic yard) Excavation (Rock
Trenching) 20.00 Pipe Bedding (Select
Material) 15.00 Backfill 3.25
16
Environmental Impacts
  • 28 species to be potentially considered in the
    scoping of potential fish and wildlife issues.
  • Listed species are for Coconino County under the
    Federal Endangered Species Act.
  • Consultation would also be required with the
    Navajo Nation to address project impacts to
    species on the Navajo Endangered Species List.
  • Area through which the proposed pipeline may be
    constructed is rich in prehistoric and historic
    cultural resources going back perhaps as far as
    10,000 years in age.

17
Project Cost EstimatesConceptual Appraisal
Level15 Unlisted Construction Costs25
Contingency
  • Alternative 1 (5,700 acre-feet p/yr) 38
    million
  • Alternative 2 (12,000 acre-feet p/yr) 58
    million

18
Summary
  • No identified fatal flaws at conceptual
    appraisal stage.
  • Project alignment can change.
  • Diversion point could possibly be moved upstream
    to alluvial basin in proximity to Lees Ferry
    crossing.
  • Environmental Impacts to main stem Colorado River
    need more evaluation.
  • Various degrees of uncertainty remain without
    additional data and analysis.
Write a Comment
User Comments (0)
About PowerShow.com