Title: Peabody Coal Lower Basin Pipeline
1Peabody Coal Lower Basin Pipeline
- Engineering Appraisal Study
- Bureau of Reclamation
- September 18, 2002
2Purpose and Scope
- To develop alternatives to divert 5,700 and
12,000 acre-feet of main stem Colorado River
water from a point located downstream of Lee
Ferry (0.0 mile), (including associated
conveyance infrastructure necessary to deliver
lower basin river water), to Kaibito, Arizona.
3Objectives
- To identify fatal flaws as related to the study
purpose. - Develop conceptual alternatives
4Assumptions
- Final report of findings to be reviewed and
completed by September 20, 2002. - Design for 5,700 and 12,000 acre-feet per year
using a 1.2 peaking factor. - Use existing available data.
- Study area limited to the corridor of land
necessary for development of a diversion,
storages, pipeline conveyance, right-of-way, and
electrical infrastructure necessary to deliver
water from the main stem Colorado River to the
community of Kaibito, Arizona. - Right-of-Way cost to be determined by Navajo
Nation. (not included in project cost estimate)
5Investigations and Data
- Conducted and over-flight of the project area.
- Utilized Reclamations project database and made
contacts with industry experts. - Accessed Grand Canyon Research and Monitoring
Center database. - Obtained copies of completed studies in the
project area and incorporated by reference. - All data utilized in the Report of Findings are
suitable for conceptual Appraisal Level studies.
6(No Transcript)
7Alignment follows existing roadways
8Alignment Profile3,097 to 5702 elevation
9Infiltration Gallery
108.0 Mile Jackass CanyonDiversion Site
Infiltration gallery
11Direction Drill _at_ Jackass Canyon
12Second Direction Drill _at_ Echo Cliffs
13Outlet of Direction Drill Hole at top of Echo
Cliffs
14Engineering Hydraulics
The peaking factor is based on information
received from the Settlement Negotiation Team.
Assuming a 1.2 peaking factor, pumping occurs 20
out of 24 hours on the maximum day, the required
design flow is 11.23 cubic feet per second
(ft3/s) and 22.68 ft3/s, respectively.
15PIPE TRENCHING COSTS Pipe Installation Item Unit
Cost (/cubic yard) Excavation (Rock
Trenching) 20.00 Pipe Bedding (Select
Material) 15.00 Backfill 3.25
16Environmental Impacts
- 28 species to be potentially considered in the
scoping of potential fish and wildlife issues. - Listed species are for Coconino County under the
Federal Endangered Species Act. - Consultation would also be required with the
Navajo Nation to address project impacts to
species on the Navajo Endangered Species List. - Area through which the proposed pipeline may be
constructed is rich in prehistoric and historic
cultural resources going back perhaps as far as
10,000 years in age.
17Project Cost EstimatesConceptual Appraisal
Level15 Unlisted Construction Costs25
Contingency
- Alternative 1 (5,700 acre-feet p/yr) 38
million - Alternative 2 (12,000 acre-feet p/yr) 58
million
18Summary
- No identified fatal flaws at conceptual
appraisal stage. - Project alignment can change.
- Diversion point could possibly be moved upstream
to alluvial basin in proximity to Lees Ferry
crossing. - Environmental Impacts to main stem Colorado River
need more evaluation. - Various degrees of uncertainty remain without
additional data and analysis.