Title: Presentation on ELECTRICITY DISTRIBUTION LOSSES
1Presentation on ELECTRICITY DISTRIBUTION
LOSSESCONCEPT OF AGGREGATE TECHNICAL AND
COMMERCIAL (ATC) LOSS
R.V. Shahi Former Power Secretary, Govt. of
India Chairman of Energy Infratech Pvt. Ltd.
(November, 2011)
2CONTENTS
- Anomalies in TD Loss Computation
- Concept of ATC Losses
- Pre-requisites for obtaining baseline ATC
losses - Methodology for establishing ATC Losses for
Project Area - Sample Calculation for Baseline ATC Losses
3ANOMALIES IN TD LOSS COMPUTATION
- In Indian Power Sector, TD Losses, as computed
in the past, over several decades, never
represented the true picture about losses in the
system. - Similar is the situation in a number of
developing countries. - The Method Procedures enable manipulations in
computations. The functionaries (Officers
Staff) could present a good picture to reflect
their efficiency, while the ground reality could
be different.
Contd...
4ANOMALIES IN TD LOSS COMPUTATION
- In absence of feeder metering separating
Agriculture Domestic Consumption, substantial
portion of TD loss, including theft of
electricity, gets attributed to agricultural
consumption. - Also, TD loss was being computed taking into
account electricity bills issued to consumers as
accrued income not on actual collection.
Contd...
5ANOMALIES IN TD LOSS COMPUTATION
- Just by overbilling, one could show a much lower
than actual loss. Therefore, TD loss figures did
not capture the major gap between the Billing and
the Collection, apart from large amount of theft. - Theft and deliberate manipulations by staff get
subsumed in excess Billing (Which would obviously
never get collected) - To get over this problem, concept of Aggregate
Technical Commercial (ATC) loss was introduced.
6CONCEPT OF ATC LOSSES
- TECHNICAL LOSSES
- Factors causing Technical Losses
- Transformation Losses (at various transformation
levels) - High I2R losses on distribution lines due to
inherent resistance and poor power factor in the
electrical network - Inadequate Planning Design, irresponsible
overdrawals by Consumers - Overloading of existing lines and substation
equipments - Absence of upgradation of old lines and
equipments - Low HT LT ratio
Contd...
7CONCEPT OF ATC LOSSES
- TECHNICAL LOSSES
- Factors causing Technical Losses
- Poor repair and maintenance of equipments
- Non-installation of sufficient capacitors
- Requirements for calculating Technical Losses
- 33 kV and below HT network Line Diagrams
- Line Diagrams for each of distribution
transformers and LT circuits upto poles/feeder
pillars - Voltage levels, Power factor and Current loading
on HT/LT network network equipments - Line lengths, cross section nature of material,
network equipments load curve etc
Contd...
8CONCEPT OF ATC LOSSES
- COMMERCIAL LOSSES
- Factors causing Commercial Losses
- Discrepancy in Meter Reading
- Untraceable consumers
- Stopped/defective meters
- Temporarily disconnected consumers continuing in
billing solution - Premises found locked
Contd...
9CONCEPT OF ATC LOSSES
- COMMERCIAL LOSSES
- Factors causing Commercial Losses
- Metering
- Meter tampering
- Bypassing of meters
- Usage of magnets to slow down the meters
- Tampering of PT circuits
- CT/PT ratios (in case of HT meters)
Contd...
10CONCEPT OF ATC LOSSES
- COMMERCIAL LOSSES
- Factors causing Commercial Losses
- Theft by direct hooking
- Tapping of LT lines to indulge in theft through
direct hooking - Sometimes even drawing an underground cable
direct from Distribution Transformer
Contd...
11CONCEPT OF ATC LOSSES
- COMMERCIAL LOSSES
- Collection efficiency
- Utility is not being able to collect the complete
amount billed by it. - Absence of Energy Accounting Auditing
- In case of unavailability of arrear figures, the
collection efficiency figures can be more than
100. - Revenue collected shall exclude the arrears.
- In above cases efficiency needs to be restricted
to 100 and shall be used for computation of ATC
losses.
12PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
- Metering of Energy Input Points of Project Area
- On incoming lines of 33/11 kV sub-stations
located within project area. - On 33 kV, 11 kV feeders emanating from
sub-station located outside project area but
supplying power to HT/LT consumers located within
project area.
Contd...
13PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
- Ring-fencing of Project area electrical network
- Import/export meters at the boundary of those
lines that are feeding outside as well as inside
project area so that import and export of energy
can be measured for project area. These lines may
emanate from the sub-stations located within or
outside project area. - Import/export meters on the dedicated feeder
emanating from sub-stations located within
project area but feeding outside project area. - Import/export meters on 33/11 kV sub-stations
LILO/tie lines.
Contd...
14PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
- Segregation of Rural Loads within Project Area
- For HT (11kV) feeders, providing power to mixed
category of consumers including agricultural
(rural), commercial, domestic etc., within
project area, utilities may segregate these
feeders through installation of separate HT
feeder for such loads.
Contd...
15PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
- Billing Revenue Collection System
- Billing system is to be able to provide data like
sales, revenue billed and collected for entire
project area. - The current billing system is designed in a way
that sale data can be extracted for 11 kV feeder
or for distribution centers (DCs) as whole. - Utilities to make provisions to account for sales
happening outside project area.
Contd...
16PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
- Computation of Input Energy
- To install meters at input points of each of
feeders (66 kV, 33 kV, 11 kV etc.) and read them
at pre-defined intervals. - In case of LILO, net input energy to the project
area of the feeder shall be considered. - If 66 kV or 33 kV feeder is directly feeding to a
dedicated consumer and that consumer(s) is within
project area, input of such feeder shall be
considered as part of input energy to the project
area.
17METHODOLOGY FOR ESTABLISHING ATC LOSSES FOR
PROJECT AREA
- Computation of Sales
- The billing for metered consumers can be done
through energy recorded by meters and the
applicable tariff. - In case of unmetered consumption
- Norms established by respective state regulatory
commission (SERC) for assessment of unmetered
consumption. - In case SERC norms are not defined, a consumption
of 150 (Units) kWh for each 1 kW of sanctioned
connected load. - The assessment is allowed only for limited period
of time and the utilities are required to
complete 100 metering within 6 months.
Contd...
18METHODOLOGY FOR ESTABLISHING ATC LOSSES FOR
PROJECT AREA
- Computation of Billing Efficiency
- Billing Efficiency Total Units Sold (kWh)
- Total Input (kWh)
- Computation of Collection Efficiency
- Collection Efficiency Revenue Collected (in
Naira) - Billed Amount (in
Naira) - Computation of ATC Losses
- ATC Losses 1-(Billing Efficiency x
Collection Efficiency)x100
19COMPUTATION OF ATC LOSSES
20THANK YOU