Presentation on ELECTRICITY DISTRIBUTION LOSSES

1 / 20
About This Presentation
Title:

Presentation on ELECTRICITY DISTRIBUTION LOSSES

Description:

Presentation on ELECTRICITY DISTRIBUTION LOSSES & CONCEPT OF AGGREGATE TECHNICAL AND COMMERCIAL (AT&C) LOSS R.V. Shahi Former Power Secretary, Govt. of India – PowerPoint PPT presentation

Number of Views:1352
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: Presentation on ELECTRICITY DISTRIBUTION LOSSES


1
Presentation on ELECTRICITY DISTRIBUTION
LOSSESCONCEPT OF AGGREGATE TECHNICAL AND
COMMERCIAL (ATC) LOSS
R.V. Shahi Former Power Secretary, Govt. of
India Chairman of Energy Infratech Pvt. Ltd.
(November, 2011)
2
CONTENTS
  • Anomalies in TD Loss Computation
  • Concept of ATC Losses
  • Pre-requisites for obtaining baseline ATC
    losses
  • Methodology for establishing ATC Losses for
    Project Area
  • Sample Calculation for Baseline ATC Losses

3
ANOMALIES IN TD LOSS COMPUTATION
  • In Indian Power Sector, TD Losses, as computed
    in the past, over several decades, never
    represented the true picture about losses in the
    system.
  • Similar is the situation in a number of
    developing countries.
  • The Method Procedures enable manipulations in
    computations. The functionaries (Officers
    Staff) could present a good picture to reflect
    their efficiency, while the ground reality could
    be different.

Contd...
4
ANOMALIES IN TD LOSS COMPUTATION
  • In absence of feeder metering separating
    Agriculture Domestic Consumption, substantial
    portion of TD loss, including theft of
    electricity, gets attributed to agricultural
    consumption.
  • Also, TD loss was being computed taking into
    account electricity bills issued to consumers as
    accrued income not on actual collection.

Contd...
5
ANOMALIES IN TD LOSS COMPUTATION
  • Just by overbilling, one could show a much lower
    than actual loss. Therefore, TD loss figures did
    not capture the major gap between the Billing and
    the Collection, apart from large amount of theft.
  • Theft and deliberate manipulations by staff get
    subsumed in excess Billing (Which would obviously
    never get collected)
  • To get over this problem, concept of Aggregate
    Technical Commercial (ATC) loss was introduced.

6
CONCEPT OF ATC LOSSES
  • TECHNICAL LOSSES
  • Factors causing Technical Losses
  • Transformation Losses (at various transformation
    levels)
  • High I2R losses on distribution lines due to
    inherent resistance and poor power factor in the
    electrical network
  • Inadequate Planning Design, irresponsible
    overdrawals by Consumers
  • Overloading of existing lines and substation
    equipments
  • Absence of upgradation of old lines and
    equipments
  • Low HT LT ratio

Contd...
7
CONCEPT OF ATC LOSSES
  • TECHNICAL LOSSES
  • Factors causing Technical Losses
  • Poor repair and maintenance of equipments
  • Non-installation of sufficient capacitors
  • Requirements for calculating Technical Losses
  • 33 kV and below HT network Line Diagrams
  • Line Diagrams for each of distribution
    transformers and LT circuits upto poles/feeder
    pillars
  • Voltage levels, Power factor and Current loading
    on HT/LT network network equipments
  • Line lengths, cross section nature of material,
    network equipments load curve etc

Contd...
8
CONCEPT OF ATC LOSSES
  • COMMERCIAL LOSSES
  • Factors causing Commercial Losses
  • Discrepancy in Meter Reading
  • Untraceable consumers
  • Stopped/defective meters
  • Temporarily disconnected consumers continuing in
    billing solution
  • Premises found locked

Contd...
9
CONCEPT OF ATC LOSSES
  • COMMERCIAL LOSSES
  • Factors causing Commercial Losses
  • Metering
  • Meter tampering
  • Bypassing of meters
  • Usage of magnets to slow down the meters
  • Tampering of PT circuits
  • CT/PT ratios (in case of HT meters)

Contd...
10
CONCEPT OF ATC LOSSES
  • COMMERCIAL LOSSES
  • Factors causing Commercial Losses
  • Theft by direct hooking
  • Tapping of LT lines to indulge in theft through
    direct hooking
  • Sometimes even drawing an underground cable
    direct from Distribution Transformer

Contd...
11
CONCEPT OF ATC LOSSES
  • COMMERCIAL LOSSES
  • Collection efficiency
  • Utility is not being able to collect the complete
    amount billed by it.
  • Absence of Energy Accounting Auditing
  • In case of unavailability of arrear figures, the
    collection efficiency figures can be more than
    100.
  • Revenue collected shall exclude the arrears.
  • In above cases efficiency needs to be restricted
    to 100 and shall be used for computation of ATC
    losses.

12
PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
  • Metering of Energy Input Points of Project Area
  • On incoming lines of 33/11 kV sub-stations
    located within project area.
  • On 33 kV, 11 kV feeders emanating from
    sub-station located outside project area but
    supplying power to HT/LT consumers located within
    project area.

Contd...
13
PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
  • Ring-fencing of Project area electrical network
  • Import/export meters at the boundary of those
    lines that are feeding outside as well as inside
    project area so that import and export of energy
    can be measured for project area. These lines may
    emanate from the sub-stations located within or
    outside project area.
  • Import/export meters on the dedicated feeder
    emanating from sub-stations located within
    project area but feeding outside project area.
  • Import/export meters on 33/11 kV sub-stations
    LILO/tie lines.

Contd...
14
PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
  • Segregation of Rural Loads within Project Area
  • For HT (11kV) feeders, providing power to mixed
    category of consumers including agricultural
    (rural), commercial, domestic etc., within
    project area, utilities may segregate these
    feeders through installation of separate HT
    feeder for such loads.

Contd...
15
PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
  • Billing Revenue Collection System
  • Billing system is to be able to provide data like
    sales, revenue billed and collected for entire
    project area.
  • The current billing system is designed in a way
    that sale data can be extracted for 11 kV feeder
    or for distribution centers (DCs) as whole.
  • Utilities to make provisions to account for sales
    happening outside project area.

Contd...
16
PRE-REQUISITES FOR OBTAINING BASELINE ATC
LOSSES
  • Computation of Input Energy
  • To install meters at input points of each of
    feeders (66 kV, 33 kV, 11 kV etc.) and read them
    at pre-defined intervals.
  • In case of LILO, net input energy to the project
    area of the feeder shall be considered.
  • If 66 kV or 33 kV feeder is directly feeding to a
    dedicated consumer and that consumer(s) is within
    project area, input of such feeder shall be
    considered as part of input energy to the project
    area.

17
METHODOLOGY FOR ESTABLISHING ATC LOSSES FOR
PROJECT AREA
  • Computation of Sales
  • The billing for metered consumers can be done
    through energy recorded by meters and the
    applicable tariff.
  • In case of unmetered consumption
  • Norms established by respective state regulatory
    commission (SERC) for assessment of unmetered
    consumption.
  • In case SERC norms are not defined, a consumption
    of 150 (Units) kWh for each 1 kW of sanctioned
    connected load.
  • The assessment is allowed only for limited period
    of time and the utilities are required to
    complete 100 metering within 6 months.

Contd...
18
METHODOLOGY FOR ESTABLISHING ATC LOSSES FOR
PROJECT AREA
  • Computation of Billing Efficiency
  • Billing Efficiency Total Units Sold (kWh)
  • Total Input (kWh)
  • Computation of Collection Efficiency
  • Collection Efficiency Revenue Collected (in
    Naira)
  • Billed Amount (in
    Naira)
  • Computation of ATC Losses
  • ATC Losses 1-(Billing Efficiency x
    Collection Efficiency)x100

19
COMPUTATION OF ATC LOSSES
20
THANK YOU
Write a Comment
User Comments (0)