Title: Proposed conceptual Cameroon gas development scheme


1
Proposed conceptual Cameroon gas development
scheme
  • Paul NGII NAG
  • Head of Gas Department, SNH

2
Outline
  • Cameroon objectives
  • Cameroon gas reserves
  • Cameroon gas master plan
  • Rio del rey scheme 1
  • Rio del rey scheme 2
  • Greater gas development sheme 3
  • Snh conceptual scheme
  • Conclusion

3
CAMEROON OBJECTIVES
  • Cameroon objectives are
  • Domestic gas market supply
  • Lpg and condensate supply to local market and
    export of excess
  • Export of dry gas to eg lng train 2

4
CAMEROON GAS RESERVES
  • Cameroon is unexploited in term of gas
  • Non associated gas 5,5 Tcf (156 billion m3)
  • Associated gas 0.035 TCF (1 billion m 3)
  • Non risk exploration about 20 Tcf (570 billion
    m3)


5
CAMEROON GAS MASTER PLAN
  • Following the gas master plan, three main
    development cases were studied
  • RDR scheme 1
  • This development scheme comprised the kita, edem
    and ekoundou fields
  • RDR scheme 2
  • This case consisted of developing the
    non-associated gas and associated gas in the
    wider kita area and also the northern fields
  • Greater gas development scheme 3
  • This case consisted of developing all discoved
    gas fields in cameroon that were perceived to be
    economically developable

6
SCHEME 1









Kita






(Kita Gas)












Key



New Wellhead Platform




65 MMSCFD



Refurb
. Wellhead Platform
18

Pipeline


478
Numbers show sales gas



flowrate
in
MMscfd
Onshore Plant




(100
MMscfd
Sales Gas

1,000 bpd Condensate)
Bioko
Island


7
PRODUCTION FORECAST FOR SCHEME 1
PATRIMONIAL GAZ RDR KITA/EDEM EKUNDU
70
60
50
40
Ekundu
Edem
DCQ (MMscf/f)
Kita 1
Kita 2
30
20
10
0
année1
année2
anneé3
année4
année5
année6
année7
année8
année9
année10
année11
année12
année13
année14
année15
année16
année17
année18
année19
année20
année21
année22
année23
année24
année25
année26
année27
année28
année29
année30
8
PRODUCTION FORECAST FOR SCHEME 1 DEVELOPMENT
BASED ON P90 VOLUMES
PATRIMONIAL GAZ RDR - KITA/EDEM EKUNDU
40
35
30
25
Ekundu
Edem
20
DCQ (MMscf/d)
Kita 1
Kita 2
15
10
5
0
année1
année2
anneé3
année4
année5
année6
année7
année8
année9
année10
année11
année12
année13
année14
année15
année16
année17
année18
année19
année20
année21
année22
année23
année24
année25
année26
année27
année28
année29
année30
9
SCHEME 2
Ekundu
10
PRODUCTION FORECAST FOR SCHEME 2
DCQ P50 (COMPRESSION IN YEAR 5 READY)
120
100
Jabane DCQ
80
Ifari DCQ
Afaga DCQ
Edem DCQ
60
MMscf/d
EK Shallow DCQ
EK Deep DCQ
Kita Shallow swing DCQ
40
Kita Deep DCQ
20
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
11
GREATER GAS DEVELOPMENT
Jabane/Ifiari

Ekundu Nth
Kribi L
Kribi B
12
PRODUCTION FORECAST FOR SCHEME 3 GREATER GAS
DEVELOPMENT
350
300
South Douala Sanaga Sud
250
South Douala Kribi L
South Douala Kribi B
Northern Narendi
200
Nothern Ifiari
Nothern Idabato
Nothern Jabane East
150
Nothern Afaga West
Kita Ekoundou Kita Shallow
Kita Ekoundou Kita Deep
100
Kita Ekoundou EkoundouNorth Shallow
Kita Ekoundou Ekoundou North Deep
Kita Ekoundou Ekoundou Centre
50
Shallow
Kita Ekoundou Ekoundou Centre Deep
Kita Ekoundou Edem
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
Years
13
SNH CONCEPTUAL SCHEME
Jabane/Ifiari
  • SONARA
  • Centrale thermique de Limbé

Gaz sec
Narendi/Idaboto
Afaga
GPL 130000T/year up to 330 000 T/year
Edem
HUB
Kita
(140 km)
Condensats (3 300 bbb/j up to 4600 bbl/day)
(20 km)
Ekundu Nth
Isongo
(GNL au Cameroun) ou Export envisageable
Ekundu Sth
(50 km)
(140 km) 100
300
Key
Usine de GNL Onshore
Centrale thermique de Kribi
Plate-formes puits
Ile de Bioko
Plate-formes production
40
Sanaga Sud (234 Sanaga Sud Gas 260 Design)
478
Débit de gaz en MMSPC/J
(140 km)
Distance en kilomètre
Kribi B)
Kribi L
14
CONCLUSION
  • A LARGE INTEGRATED GAS EXPORT DEVELOPMENT WOULD
    PROVIDE THE BEST LONG-TERM PLATFORM FOR GAS
    COMMERCIALISATION FOR THE COUNTRY AND FOR
    DELIVERY OF COST-COMPETITIVE GAS POWER GENERATION
    IN CAMEROON.
  • ANY GAS DEVELOPMENT, EVEN SMALL, DECIDED BEFORE A
    BETTER UNDERSTANDING OF VOLUMES HAD BEEN
    DEVELOPED COULD ERODE THE LIKELIHOOD OF
    LARGE-SCALE DEVELOPMENT SEEKING TO MAXIMISE THE
    UTILIZATION OF CAMEROONS GAS RESOURCE OVER A
    PERIOD OF 20-30 YEARS.

15
CONCLUSION
  • DUE TO THE INSUFFISANT PRODUCTION OF LPG WITHIN
    THE COUNTRY, THE BEST SCHEME IS THE GREATER ONE
    WITH LIQUID RECOVERY IN CAMEROON AND LEAN GAS
    SENT TO EG LNG AT PUNTA EUROPA IN BIOKO ISLAND.
  • TO PROGRESS A SUCCESSFUL CAMEROON
    COMMERCIALISATION SCHEME, SUBTENTIAL ADDITIONAL
    VOLUMES WOULD NEED TO BE MATURED AS SOON AS
    POSSIBLE THROUTH DEDICATED GAS EXPLORATION AND
    APPRAISAL ACTIVITIES.

16
THANK YOU