EE 394J10 Distributed Technologies - PowerPoint PPT Presentation

About This Presentation
Title:

EE 394J10 Distributed Technologies

Description:

EE 394J10 Distributed Technologies Grid-Microgrids Interconnection Motivation Reasons for connecting a microgrid to a main grid: Availability: Highly available power ... – PowerPoint PPT presentation

Number of Views:72
Avg rating:3.0/5.0
Slides: 23
Provided by: AlexisKw9
Category:

less

Transcript and Presenter's Notes

Title: EE 394J10 Distributed Technologies


1
EE 394J10 Distributed Technologies
Grid-Microgrids Interconnection
2
Motivation
  • Reasons for connecting a microgrid to a main
    grid
  • Availability Highly available power grids may
    act as an additional source for micro-grids.
  • Operations/stability
  • Direct connection of ac microgrids to a large
    power grid facilitates stable operation but only
    if the power grid acts as a stiff source to the
    microgrid.
  • When using renewable energy sources, a grid
    connection may allow reducing the need for energy
    storage in the microgrid.
  • If not all loads in a microgrid are critical, a
    grid connection may allow to reduce the
    investment in local generation.
  • Economics
  • Microgrids are typically planned with extra
    capacity with respect to the local load. This
    extra power capacity can be injected back into
    the grid in order to obtain some economic
    benefit.
  • Grid interconnection allows to reduce fuel
    operational costs by using the grid at night when
    electricity costs are low.

3
Definitions
  • Point of common coupling (PCC) it is the point
    in the electric circuit where a microgrid is
    connected to a main grid.

4
Standards
  • There are several standards specifying various
    aspects grid interconnection of a local power
    generation source. Arguably the most important
    one is IEEE 1547.
  • IEEE 1547 has several parts
  • Main body
  • IEEE Standard 1547.1 IEEE Standard Conformance
    Test Procedures for Equipment Interconnecting
    Distributed Resources with Electric Power
    Systems.
  • EEE Standard 1547.2 IEEE Application Guide for
    IEEE Std 1547, IEEE Standard for Interconnecting
    Distributed Resources with Electric Power
    Systems.
  • IEEE Standard 1547.3 IEEE Guide for Monitoring,
    Information Exchange, and Control of Distributed
    Resources Interconnected with Electric Power
    Systems.
  • IEEE Standard 1547.4 IEEE Guide for Design,
    Operation, and Integration of Distributed
    Resource Island Systems with Electric Power
    Systems.
  • IEEE Standard 1547.5 has not been issued, yet.
    Its intended scope is to address issues when
    interconnecting electric power sources of more
    than 10 MVA to the power grid.
  • IEEE Standard 1547.6 IEEE Recommended Practice
    for Interconnecting Distributed Resources with
    Electric Power Systems Distribution Secondary
    Networks.
  • IEEE Standard 1547.8 has not been issued, yet.
    Its intended scope is to provide supplemental
    support for implementation methods for expanded
    use of the previous standards, for example when
    addressing issues with high penetration of
    residential PV systems.

5
Standards
  • Main provisions from IEEE 1547
  • The micro-grid must not actively regulate the
    voltage at the PCC.
  • The grounding approach chosen for the local area
    power and energy system (LAPES) must not create
    overvoltages that exceed the ratings of the
    equipment connected to the main grid or must not
    affect ground fault protection coordination in
    the main grid.
  • The distributed resources in the LAPES must be
    able to parallel with the main grid without
    causing voltage fluctuations at the PCC greater
    than 5 of the prevailing voltage level of the
    Area electric power system (EPS) at the PCC and
    flicker must be within acceptable ranges.
  • The LAPES must not energized the main grid when
    the main grid is not energized.
  • Each distributed resource (DR) unit of 250 kVA
    or more or DR aggregate of 250 kVA or more at a
    single PCC shall have provisions for monitoring
    its connection status, real power output,
    reactive power output, and voltage at the point
    of DR connection.
  • A visible-break isolation device must be located
    between the main grid and a DR unit only when
    required by the main grid provider practices.
  • The interconnection system must meet applicable
    surge and EMI standards.

6
Standards
  • Main provisions from IEEE 1547
  • When a fault occurs in the main grid circuit to
    which a LAPES is connected, then the micro-grid
    local power generation units must stop to power
    this circuit before reclosure from the main grid
    happens.
  • The interconnection system must be able to
    measure relevant indicated voltages and
    frequencies at the PCC or the point of connection
    of DR and disconnect within a given allowed time
    all local power generating units in the
    micro-grid when these measured voltages or
    frequencies fall within a range specified in a
    table in this standard. For example, when
    voltages fall below 50 of the base voltage, the
    LAPES must disconnect its DR within 0.16 seconds
    (one 60 Hz cycle). The time extends to 2 seconds
    for voltages between 50 and 88 of the base
    voltage. Disconnection must occur within 1 second
    if measured voltages are between 110 and 120 of
    the base voltage and within 0.16 seconds if the
    voltage exceeds 120 of the base voltage. For
    frequency measurements, any DR of 30 kW or less
    must disconnect 0.16 seconds if the measured
    frequency is above 60.5 Hz or below 59.3 Hz. The
    same disconnect time applies for DR of more than
    30 kW when the frequency exceeds 60.5 Hz, but for
    the lower range at these power levels disconnect
    within 0.16 seconds must occur if the frequency
    falls below 57 Hz, whereas disconnection is
    adjustable between 0.16 and 300 Hz if the
    frequency falls between 59.8 and 57 Hz.
  • Reconnection of a LAPES to a main grid may occur
    at least 5 minutes after voltages and frequency
    fall within indicated required ranges.

7
Standards
  • Main provisions from IEEE 1547
  • Reconnection of a LAPES to a main grid may occur
    at least 5 minutes after voltages and frequency
    fall within indicated required ranges.
  • A microgrid must not inject dc current greater
    than 0.5 of the full rated output current at
    the PCC.
  • Harmonic current injection by the LAPES into the
    main grid measured at the PCC must not exceed
    certain levels both in total and for given
    harmonic order ranges. The total demand
    distortion must not be more than 5 of the local
    main grid maximum load current integrated demand
    (15 or 30 minutes) without the DR unit, or the DR
    unit rated current capacity, whatever is
    greater. Base of this same base current, harmonic
    content for harmonics with an odd order below 11
    must not exceed 4 . If the odd harmonic order is
    between 11 and 17 the limit is 2 , whereas this
    limit falls to 1.5 for odd harmonics with an
    order between 17 and 23 and 0.6 for odd
    harmonics with an order between 23 and 35. For
    odd harmonics with an order above 35, the
    harmonic content with respect to the indicated
    current must not exceed 0.3 . For even harmonics
    their content limits are a quarter of those
    indicated for the odd harmonic orders.

8
Standards
  • Other important provisions from IEEE 1547.6
    about network protections (NP) on the grids
    side
  • The presence of DR should not
  • - cause any NP to exceed its fault-interrupting
    capability.
  • - cause any NP to operate more frequently than
    prior to DR operation.
  • - prevent or delay the NP from opening for
    faults on the network feeders.
  • - delay or prevent NP closure.
  • - require the NP settings to be adjusted except
    by consent of the area EPS operator.
  • - cause an islanding condition within part of
    a grid network.

9
Interconnection methods and technologies
  • Interconnection methods
  • Directly through switchgear
  • Power electronic interfaces
  • Static switches
  • Directly through circuit breakers
  • Relatively simple and inexpensive
  • Slow (3 to 6 cycles to achieve a complete
    disconnection).
  • Since electrical characteristics on both sides
    of the circuit breakers must be the same, then,
    electrical characteristics on the micro-grid side
    are dependent on the grid characteristics. For
    example, use of a circuit breaker implicitly
    limits the micro-grid to have, at least
    partially, an ac power distribution system in
    order to match the grids electrical
    characteristics.
  • Power flow through the PCC cannot be controlled

10
Interconnection methods and technologies
  • Directly through circuit breakers
  • Example of one of such systems
  • Use of static switches
  • Usually based on SCRs in antiparallel
    configuration to allow bidirectional power flow

11
Interconnection methods and technologies
  • Use of static switches
  • They are costlier and more complex than using
    circuit breakers.
  • Usually, conventional circuit breakers are still
    used to provide a way to achieve full galvanic
    isolation. A Bypass switch is also added for
    maintenance reasons.

12
Interconnection methods and technologies
  • Use of static switches
  • They allow for many open/close operations
  • They act much faster than conventional circuit
    breakers (in the order of half a cycle to a
    cycle). Sometimes IGBTs are used instead of SCR
    because IGBTs tend to be faster than SCRs and
    their current is inherently limited.
  • Still power flow cannot be controlled.
  • There are some conduction losses in the devices.

13
Interconnection methods and technologies
  • Power electronic interfaces
  • It is the costlier option but it is also the
    most flexible one.
  • Allow for power distribution architecture
    characteristics on both sides of the PCC to be
    completely different.
  • Both real and reactive power flow can be
    controlled.
  • Reaction times to connection or disconnection
    commands are similar to those provided by static
    switches, although in the case of a power
    electronic circuit, it response also depends on
    its dynamic performance, given by its controller,
    topology, and internal energy storage components
    characteristics.
  • Still, in many cases, a circuit breaker will
    still be required at the grid-side terminal of
    the power electronic interface with a LAPES in
    order to provide a way to physically disconnect
    the micro-grid from the grid.
  • Also, similarly to static switches, the presence
    of a power electronic circuit will lead to some
    power losses not found in the approach using
    mechanical interfaces.

14
Grid-connected inverter control
  • Consider the following configuration in which it
    is assumed that we can control both real and
    reactive power can be controlled at the inverter
    (this is not always the case).

15
Grid-connected inverter control
  • With a small voltage drop in the grid impedance
    (so the voltage at the PCC, va is fixed and
    cannot be regulated by the inverter
  • The inverter impedance depends on the inverter
    output filter parameters and the inverter
    controller.
  • In most typical applications, for low
    frequencies the inverter impedance is mostly
    resistive. Hence,

16
Grid-connected inverter control
  • If the inverter is controlled as in most PV
    grid-tied inverters so their power factor is
    close to 1, then
  • Hence,
  • If due to the output filter or the controller
    parameters the inverter presents an inductive
    equivalent series impedance, then

17
Grid-connected inverter control
  • Condition for unity power factor
  • Consider the following triangle based on the
    above condition
  • Then
  • and

18
Islanding
  • In IEEE Standard 1547.4 an intentional island is
    said to be the result of intentional events for
    which the time and duration of the planned island
    are agreed upon by all parties involved.
  • There are several reasons why intentional island
    operation of a micro-grid may occur, but a common
    one is a preemptive disconnection from the grid
    in anticipation of a power outage on the main
    grid side caused by an event that can be
    anticipated, such as an incoming hurricane or
    storm, or wildfires. The advantage of this
    intentional islanding operation instead of
    waiting for the outage in the main grid to occur
    in order to switch the LAPES to operate in
    islanding mode is that an intentional islanding
    allows for a controlled transition that prevents
    potential failures or quality issues in the
    micro-grid.
  • Two phases can be distinguished in islanded
    operation
  • transition from grid connected to island
    operation
  • operation isolated from the grid.

19
Islanding
  • During the transition into island operation it
    is important that
  • voltage disturbances are quickly dampened and
    that protection schemes both inside the LAPES and
    in the grid are not affected.
  • When the transition is completed it is important
    that
  • the micro-grid has sufficient local power
    generation and energy storage in order to ensure
    that loads are powered with the agreed quality
    level. For example, in ac micro-grids it is
    important that distributed resources are able to
    provide real and reactive power to the specified
    load range. This is particularly important in
    order to avoid loss of stability if there are
    large motors in the LAPES that require
    significant amounts of reactive power during
    startup
  • Also for ac micro-grids, their control systems
    must be able to regulate both voltage and
    frequency within acceptable ranges. In dc
    micro-grids, neither frequency regulation nor
    reactive power generation are issues to consider.

20
Islanding
  • Eventually, it can be anticipated that the
    micro-grid would be connected to the main grid
    again. Grid connection of dc micro-grids or ac
    micro-grids with a power electronics interface
    with the main grid tends to be simpler than the
    case of ac micro-grids connected to the main grid
    through circuit breakers, contactors, or static
    switches because in the dc micro-grid and the ac
    micro-grid with a power electronics interface
    cases reconnection control resides only in this
    power electronic interface. That is, the
    controller in this power electronic interface
    would controlled in order to realize on its grid
    side some voltage waveform so its amplitude,
    frequency and phase angle are within specified
    limits to allow reconnection.
  • In the other ac micro-grid casesthose directly
    connected to the main grid though mechanical
    switchgear or static switchesreconnection is
    more complicated because there is no possibility
    of directly controlling the voltage waveforms at
    the PCC. In this case, ensuring that the voltage,
    frequency and phase angle are within acceptable
    limits depend on how the LAPES distributed
    resources are controlled.

21
Islanding
  • According to IEEE Standard 1547.4 these
    approaches can be distinguished in this case of
    ac micro-grids in order to achieve a successful
    reconnection
  • Active synchronization In this approach, the
    LAPES controller matches the voltage signal on
    the PCC micro-grid side to those of the PCC on
    the grid side immediately before closing the
    islanding devices, such as a circuit breaker.
    Implementation of this approach requires
    measuring these three voltage signal
    parametersamplitude, frequency and phase
    angleon both sides of the PCC. A communications
    channel in order to exchange information between
    the micro-grid and the main grid is also
    necessary. This need for sensing and
    communications may lead to a higher failure rate
    as the sensing and communications subsystems may
    become a single point of failure.
  • Passive synchronization In this approach a
    device is used to monitor the voltage at both
    sides of the PCC and allows the LAPES to connect
    to the main grid only when the voltage signal on
    the LAPES side is within some given required
    range of the main grid analogous voltage
    parameters. Like the active synchronization
    approach, passive synchronization requires
    sensing and communications, leading to the same
    potential reliability concerns. In addition, this
    method may be slower than active synchronization.
  • Open transition This approach is more basic
    than the other two, because the method involves
    connecting both ends of the PCC after
    interrupting disconnecting the LAPES load. Once
    the micro-grid is connected to the grid then this
    load is brought back online.

22
Islanding
  • According to IEEE Standard 1547.4,
    un-intentional islanding operations are
    inadvertent events that are typically initiated
    by loss of area EPS or equipment failure, and the
    DR island system may be automatically
    sectionalized from the area EPS by protective
    equipment.
  • Once the island has been established, the same
    considerations that were considered for the
    intentional island condition applies to the
    un-intentional island.
  • Contrary to the case of intentional islanding,
    during an un-intentional island it is not
    possible to prepare the LAPES for such
    transition, such as verifying that there is
    sufficient local generation to sustain a stable
    operation powering all loads. Hence, in case it
    is expected that local generation capacity may be
    insufficient to sustain the load during
    un-intentional islands, black start functions or
    standby generators with transfer switches have to
    be allocated within the LAPES.
  • Once the issue in the main grid that led to loss
    of service to the micro-grid feeder is solved, it
    may be of interest to reconnect soon the main
    grid to the micro-grid. However, such connection
    cannot occur until the voltage and frequency of
    the grid are stable and within acceptable ranges.
    In order to ensure meeting such requirement, a
    delay of up to five minutes may be provided
    between the time power is restored at the PCC
    from the main grid and the time reconnection to
    the LAPES is established.
Write a Comment
User Comments (0)
About PowerShow.com