Title: Ministry of Economy of Poland and World Bank Seminar on Legal Economic and Implementation Issues in
1Ministry of Economy of Poland and World
BankSeminar on Legal Economic and
Implementation Issues in PPP ProjectsJune 17
and 18, 2008 Warsaw WHAT CAN WE LEARN FROM
FAILURES?
- The point of view of an investor
- by Olivier Bonnin
- DCEO of AKA Zrt.
- Drivers of Success
2Different kind of failures. Some examples
- You invest in commercial approach, but the tender
never come (or is cancelled)
- You answer to the tender, but you loose
- You answer to the tender, but no contract is ever
signed
- You signed the PPP contract, but no financial
closing occurs
- You close but preconditions for first drawing not
met
- You invest and built, but revenues are not there
3Commercial Approach, No Tender (or no PPP Tender)
- Happened to Bouygues TP in Romania, Poland,
Albania, Brazil, France, Serbia, China, Macedonia
etc..
- RULE Its always possible.
- MITIGATION
- Spend what is necessary to assess the quality of
Project, but not more
- Select the project not too big, not too small
4You answer the tender, but you loose
- RULE Its always possible, and not avoidable
- HAPPENED IN France, UK, Croatia, Portugal,
Serbia, Chile etc
- MITIGATION
- Do not spend too much money if too many
candidates.
- (3 is better than 4)
- Run away from tenders which cost too much.
- SECOND CONSEQUENCE (FOR GRANTORS)
- Avoid prequalification with too many candidates
- Avoid asking financial closing at tender stage
-
5You answer the tender, but no contract ever agreed
- HAPPENED IN Serbia, Croatia, Turkey, France,
China, Australia
- RULE not so often, can be due to
- No real political will
- Strong opponents to the project
- No real clear legal background
- No good economical vision from the tenders
issue
- MITIGATION check that the grantors vision is
reasonable
- Avoid tenders that involve too much
expanses
- (too detailed offer)
- SECOND CONSEQUENCE (FOR GRANTORS) Do
not issue tender if you are not sure of your
political will
-
6SERBIA
- 1996 Tender for Highway Beograd Hungary
(200km), launched in 1995.
- Bouygues TP studied roughly cash flow stream,
and very preliminary investment assessment.
Traffic interesting, investment reasonable (two
lanes existing) HUGE FRAUD - After six month, the minister decided on a
contract with a bank to finance some minimal
works and collect tolls.
- 1995 NIS - Macedonia border (100 km)
- 100kms of heavy works, with little traffic
- Bouygues TP answer the tender, proposing to
finance the NIS border section with revenues of
existing Beograd NIS section
- No contract was awarded to anybody.
-
7CROATIA
- 1992 tender for 6 highways
- Two offers were submitted.
- Bouygues got the contract of Istrian motorways
and negotiations for main Zagreb - Rijeka
motorways lasted one year, without any result.
- At the end, the government decided to create a
new company to built and operate the missing
links between Zagreb and Rijeka.
8TURKEY
- Izmit bridge
- Tender launched
- Bouygues submitted two tenders one bridge / one
tunnel
- Huge technical costs to assess the feasibility
under extreme earthquake risk.
- No decision made by Turkish government.
- Tender relaunched some years later under a
different scheme.
9FRANCE
- 1992 Tunnel under Grenoble
- Tender launched
- 3 answers
- Bouygues TP winner
- The city of Grenoble initiated a long lasting
process of
- communication with the citizens and the opponents
to the project.
- After two years, decision was made to do
nothing.
- Huge cost occurred.
10CHINA
- 1999 Port of Qin DAO Container terminal 1km
quay length and 50 ha storage 200M
- Answer given at the request of Qin DAO
municipality
- Long lasting technical fine turning
- No green light from central authority
- 2001 Port of New Castle 1km, 100ha 250 M
- Tender launched
- Two answers, clearly indicating that the
precondition to success is that the government
limit extension of Sidney Botany Bay Port.
(competiting) - No decision by government. No award.
AUSTRALIA
11You signed the contract, but no financial closing
occured
- HAPPENED IN Bosnia, Marocco
- RULE generally comes from
- Disagreement on risks allocation, or
- Lack of appetite from lenders, or
- Lack of political will
- MITIGATION
- Clarify in your offer
- Check political will
- Test financial market before spending too much
time and money
- FOR GRANTORS
- Avoid launching tenders if no real political
will
12BOSNIA
- Tender launched in 1998 for a motorway between
Sarajevo and Croatian border towards north
(..)
- Two answers.
- BY TP winner, negotiated and signed the
contract.
- Very few banks interested.
- Try to agree with the government for a phasing
without success.
- Huge pressure from the then acting minister to
work with not reputable bank.
- No agreement. Contract terminated in 2000.
13MAROCCO
- New port of TANGIERS 400M
- Tender launched in 1998.
- Three answers.
- BY TP winner
- Long lasting negotiations for the concession
contract. Contract agreed in 2000. Memorandum
signed by the prime minister.
- Then the government decided to change the port
location and to finance it from public funds.
14You reached financial close, but condition
precedent first drawing are not met
RULE ALMOST NEVER HAPPENS (You are suppo
sed to have signed reasonable conditions
precedent) BUT HAPPENED ONCE TO BOUYGUES (Iv
ory Coast- Quasi-war situation)
ASSESS POLITICAL STABILITY FOR GRANTORS Avoi
d wars
15IVORY COAST
- Abidjan 3rd bridge.
- Tender in 1996.
- Two answers, by TP winner.
- Contract signed detailed studies performed.
- Financial closing reached on 19th November 1999
with a first drawing forecast on 31st of January
2000.
- Preliminary works performed equity injected.
- -26th of December 1999 first coup of a long list
to follow. No vote on the law necessary to
sustain the project.
- Concession contract still valid. Loan agreements
terminated.
16You invested and built, but revenues are not there
- VERY FREQUENT SITUTATION (Germany, Jamaica,
Hungary, Croatia, .)
- It will happen to you.
- Everything will depend on
- The robustness of your financial model
- (did you test 20,-25 down scenarios?)
- The real share of risks between private and
public partners
- (limited in time and amount public support)
- BE OPEN . BE PRUDENT.
17GERMANY
- Warnowquerung in Rostock 1 km tunnel.
- Traffic below forecast, partially due to huge
ramp-up process (1st tolled project in Germany).
- Contract still valid. Negotiation of loan
agreements and of concession length.
- Main consequences Investors IRR.
JAMAICA Highway 2000. Government reluctant t
o apply the toll that was in the business plan.
Main consequences Investors IRR.
HUNGARY Obviously M1-M15 is a good example of
project with less revenues than expected but M5
as well, with a different end.
1996 -Opening of M5 traffic below expectations
, due to ramp up, and then war in Serbia.
-AKA has been able to survive, due to a robust
financial arrangement but no dividends was paid
in ten years. -Then AKA refinanced the loan agre
ement, giving comfort for the whole concession
duration, and restate profitability taking into
account a new risk profile (no more construction
risk) and new market conditions.
-Now, toll system has been changed into the
vignette system.
18There could be other types of failures
- Construction cost rise Bouygues TP has no
experience of it in PPP.
- MITIGATION some risky business as some kind of
tunnels which are highly dependant on geological
conditions are not fitted with PPPs where most of
construction risk is borne by the contractor. Run
away! (or agree on geological risk borne by
grantor) - -Macro economical risks (inflation,
devaluation,)
- Financial structure should be robust enough
- -War risk to be borne by states only
- -Change of political majority have a good
contract. Give the public partner all rights to
change its mind, but with clear compensation
rule - No one PPP is signed with a single Political
Ruling Party. During a PPPs life you will meet
dozens of successive ministers.
19CONCLUSION
- We learned a lot from failures, if we take the
time to analyse.
- THE GENERAL RULE IS
- Some time it is better to run away
- All the other times, simple rules have to be
respected
- Progressive commercial expanses
- Robust financial arrangements
- (it is even more important to have run good
sensibilities than to have good debt/equity or
debt service cover ratios)
- Assess the real political will including
opposition to the project
- Be humble and consider you may have made
unprecise forecast
- The best financial structure is not the one which
suits the best to the most probable set of
hypothesis, but the one which resists to all sets
of hypothesis, even if not so likely to occur. - The best concession contract is not the one which
forecasts all possible events (this does not
exist) but the one which sets the principles to
solve unexpected problems, with respect to the
interest of all stakeholders.
20PPPs are a must in the countries where
- There is a lack of transport infrastructure.
- There is a real will to develop it.
- There are budget limitations.
- (THAT IS TO SAY, ALMOST ALL EUROPEAN COUNTRIES.)
- PPP is before all, a way to manage risks
- Financial risks
- Technical risks
- Legal risks
- Political risks
- In a manner that
- A majority of risks are
- Identified
- Limited in extend
- - Mitigated
- Allocated to the party that is the more able to
cope with it.
- There is a clear rule to
- - identify
- - limit
- -mitigate
21PPPs is a matter of experience but unfortunately
- 1. Experience is like toothbrushes
- You dont like to use others ones.
- 2. People like explain you their success
stories,
- they dont like to detail their failures.
-
- Experience is also made of failures.
- What does not kill me, makes me stronger. (F.
Nietzsche)