Title: Patrick Rein Richard Armstrong
1Patrick ReinRichard Armstrong
- Enhanced Biological Phosphorus Removal
- at the
- Fergus Falls WWTP
2OVERVIEW
- Background/ Review Theory
- Operations Review
- Some parameters to keep an eye on
- P in MLSS Test
- How do we know if we are getting EBPR?
- How we are doing at Fergus Falls
- Plant configuration
- Results
- Shock load test
- Conclusions
3Background
- EBPR (enhanced biological phosphorus removal) is
not new!!! - Stress Organisms-anaerobic / aerobic in presence
of a carbon source (BOD). - Timmerman 1979, Krichten et. al., 1978 Refling et
al 1977 and others 1974 - Old Patented Processes
- A/O process
- Bardenpho process.
4EBPR Just Makes Good Sense
- Reduction / Elimination of Chemicals
- Reduced Sludge Production (lower growth)
- Control of Filaments
- Improved SVI
- Reduced Operating Costs
5EBPR Defined
- When organisms store more phosphorus than their
normal requirements - What are normal requirements
- Bugs are 2 phosphorus by weight
- Will remove 20 of P coming out of primary
- This is due to normal growth!!!
- With EBPR
- Bugs can be over 15 phosphorus by weight
- Can remove over 60 removal of P coming out of
primary
6 Review of EBPR Theory
- The Anaerobic Zone
- Sufficient Biomass
- MCRT gt 10
- No Oxygen or Nitrate
- Store Food
- Food VFAs
- Energy for Storage comes from P Release
7Review of EBPR Theory
- The Aerobic Zone
- Bugs
- Use D.O.
- Consume Stored Food (VFAs)
- Generate Energy for P Uptake
- Cell Growth
- P Uptake (recharge the battery)
8Operations Review
- What operating parameters must I be concerned
about?
9OPERATIONS REVIEW
- What we have observed that affects EBPR
performance the most - Return Flow Rate-Nitrate and DO
- Secondary P release
- Wastewater Characteristics Entering Anaerobic
- BOD/P
10(No Transcript)
11Secondary Release of P
- THESE ARE NOT GOOD RELEASES!!!
- Anaerobic P Release
- P release without uptake of VFAs
- Control time in zone (we have 2 hr HRT)
- Aerobic P Release
- Long HRT could result in P release due to
endogenous destruction (we have 5 hr HRT)
12The Eff. Primary Clarifier (PC) RatioBOD/P
- You Dont even need EBPR. Still get 20 P
removal. Eff. P maybe lt1 due to normal growth. - Now you need EBPR (going beyond normal growth p
uptake) - Youll get even better EBPR but will not meet
limit of 1.0 mg/L
- 100/1 100
- 100/5 20
- 100/10 10
13(No Transcript)
14As Effluent PC Ratio Goes Down
- Anaerobic Zone
- Small change in COD taken up
- Large change in P Release
- In other words, P release per unit of COD
increases - (Shock increase in P Load)
- Aerobic Zone
- More food more energy for P uptake
- Phosphorus uptake increase
- P in the MLVSS increases (as high as 18)
- More Anaerobic P Release More Aerobic P
Uptake
15Eff. PC Ratio Affects Release and Uptake
16What is the Best Method to Measure EBPR ?
- PHOSPHORUS in MLVSS
- Do the bugs contain more than the normal
requirement of 2-3?
17 P in MLVSS Test
- Hach Test N Tube Method 8190
- Run Total P on Mixed Liquor (MLSS-TP)
- Run Effluent Total P (Eff-TP)
- filtered MLSS sample
- typically we just use composite Eff. P value
- represents soluble orthophosphate
- P in Bugs MLSS-TP Eff-TP
- P in MLVSS (P in Bugs) / (MLVSS) X 100
18Bio-P Testing Examples
19A Comparison
CONFIGURED FOR BIO P ( OAK VALLEY
BODP17/EFF P14--Fergus Falls BODP37/ EFF P
lt1)
20Is the Process Working?
- How do you know if you are getting EBPR?
- If Effluent P lt 1.0 mg/L
- Maybecould be because Influent PC ratio is very
high - If Phosphorus in MLSS, RAS or WAS
- 3 to 5 (YOU ARE GETTING EBPR)
- BUT still Eff. P maybe gt 1.0 mg/L
- Due to operations (i.e. high Eff. TSS or
secondary p releases)
21How can we get Effluent P lt 1.0 mg/L
- For Typical Domestic WW
- Entering the Anaerobic Zone
- BOD5/P of at least 20 (COD/P40) (higher the
better) - 20 mg/L COD to remove 1 mg/L Phosphorus
- Remember Domestic WW
- Normally P Limited (4-6 P for bugs)
- Control other Parameters Mentioned Earlier
22Removal at Fergus Falls
23Fergus Falls WWTP
- 2.81 MGD 1988 Extended aeration Plant
- Design
- 2 Aeration Basins 12 hours
- Chemical Phosphorus Removal
- Design Included Operational Options
- (1)Contact Stabilization, (2) Parallel Flow, and
(3) Plug Flow
241999 Operation Changes
- Reduced Aeration Volume (1/2)
- Reduced RAS (500 gpm to 240 gpm)
- Turned Air Off in Mix Well
- Tried One Primary Clarifier (abandoned)
25ANAEROBIC
AEROBIC
AEROBIC
26Process Schematic
Q QR
Q QR
Q Influent
Q QR
Q Effluent
Mix Well
QR Recycle
QR
QR
No Air, Mix Zone 1 0.183 MG
Air Zone 2 0.183 MG
Air Zone 3 0.183 MG
Settle/Decant Zone 4 0.596 MG
27Zone Times
- Total HRT 17.2 hrs
- No Air 2.74 hours
- Air 5.49 hours
- Settle 8.94 hours
- Graph Shows Percentages of Total HRT
28RESULTS
- How have we done at Fergus Falls?
29FF Primary Clarifier Effluent
- BOD 133 mg/L
- P 3.6 mg/L (40 Removal)
- BOD/P (entering the anaerobic zone)
- BOD/P 37.0 mg/L
- So it should work!
- Only needs an anaerobic zone
30Operating Conditions
- Anaerobic Zone
- ORP
- IN -25
- Out -240
- BOD/P
- In 37
- COD (soluble)
- In 130 mg/L
- Out 13 mg/L
- Aeration Plug Flow (2) Channels
- DO 2.0 mg/L _at_ end
- MLSS 5,000 or gt
- NO3 lt 6 8 mg/L
- ORP 100
31BOD Variability
32Phosphorus Variability
33 P in MLVSS
- 2004 Averages
- Influent P 6.5
- Effluent P 0.6
- P/MLVSS 4.55
- 2003
- P/MLVSS 5.29
- 2002
- P/MLVSS 4.83
34Current Phosphorus Balance--no chemical being
added!
Influent Q 1.5 MGD BOD 221 mg/L BOD 2764
lb/day P 6.0 mg/L P 75 lb/day
Effluent Q 1.5 MGD BOD 3 mg/L P 0.6 mg/L P
8.0 lb/day
BOD 133 mg/L BOD 1,664 lb/day P 4.4 mg/L P
45 lb/day
Primary Clarifier
Secondary Clarifier
Activated Sludge Tank
Primary Sludge Q 8,000 gpd TS 5 P 30 lb/day
RAS
WAS 832 lb/day P 4.55 P 37 lb/day
P/VS 4.55
35(No Transcript)
36Effluent P Results 2002-2004
- We always meet Total Phosphorus limit of lt1.0
with some chemical addition - Typically run without any chemical when not
dewatering (5 months/year) - P in MLSS say we are getting EBPR even though
we use chemical
37Shock Load Test 2004
- From Biosolids Dewatering
- Influent P 10 mg/L (was running 6.5 mg/L)
- 35 Increase in four days!!
- Eff. PC ratio went from 37 to 25
- Effluent 1.0 mg/L (was 0.5 mg/L)
- MLVSS/P 7.1 (was running 4.5)
38Shock Load P Balance no chemical being added!
Influent Q 1.6 MGD BOD 250 mg/L BOD 3336
lb/day P 10 mg/L P 133 lb/day
Effluent Q 1.6 MGD BOD 3 mg/L P 1.0 mg/L P
13.0 lb/day
BOD 150 mg/L BOD 2000 lb/day P 6.0 mg/L P
80 lb/day
Primary Clarifier
Secondary Clarifier
Activated Sludge Tank
Primary Sludge Q 10,000 gpd TS 5 P 53
lb/day
RAS
WAS 1000 lb/day P 7.1 P 71 lb/day
P/VS 7.1
39Conclusions
- Enhanced Biological Phosphorus Removal Works!
- Eff. PC can vary and system will adapt quickly
(shock load test) - Need to pay attention
- (DO and NO3)
- Side Streams
- Chemical back up if limit is a monthly average
(If we are getting Eff. P of .7, chemical will
come on) - QUESTIONSemail Rein and Associates at
rein_at_cableone.net or phone 218-233-8463