Title: THE NEW GENERAL TERMS


1
THE NEW GENERAL TERMS
  • Jim Cownie
  • Mn/DOT Contract Management

2
THANKS!
  • ACEC/MnDOT Liaison Committee
  • ACEC Transportation Committee
  • Glenn Purdue, Purdue Law Firm
  • Jodi Norman, Braun Intertec Corp.
  • Dawn Thompson Alyssa Murray, Mn/DOT
  • Many ACEC Members

3
General Improvements
  • Editorial and organizational improvements
  • Limit use of subjective (and probably
    uninsurable) terms such as satisfactory and
    acceptable
  • More even-handed in many places protects
    taxpayers but acknowledges nature of professional
    services

4
In Your Folders
  • Guide by Article Numbers
  • Article-by-article summary of the new general
    terms

5
Highlights
  • Article 11 Referenced Standards
  • When a standard (e.g. aMn/DOT manual) is
    referenced, clarifies that it is the version in
    effect on the date the contract is signed.

6
Highlights
  • Article 15 Schedule Adjustments
  • Force Majeure delay - will negotiate equitable
    adjustment
  • Other delay discretionary adjustment by Mn/DOT

7
Highlights
  • Article 16 Amendments
  • Sets forth obligations regarding providing notice
    when an amendment appears necessary
  • Mn/DOT may disallow a claim for extra costs due
    to extra work unless approved by Mn/DOT and
    evidenced by a written amendment

8
Highlights
  • Article 18 Conditions of Payment
  • Payment tied to conformance with contract
    requirements, rather than satisfactory
    performance
  • Specifies when final retainage is due and payable
    note retainage will still be dealt with in
    special terms

9
Highlights
  • Article 23 Standard of Care
  • Provides a defined standard of care, provides for
    consultant liability when standard of care and
    contract requirements arent met.
  • Eliminates ambiguous standards like
    satisfactory

10
Highlights
  • Article 24 Errors and Omissions
  • Defines defective work, and outlines the
    consequences that flow from defective work
  • Replaces time is of essence clause with
    language acknowledging professional constraints,
    excuses force majeure delays
  • Details obligations regarding plan
    interpretation, correction, even after contract
    has ended (e.g. during the construction project)

11
Highlights
  • Article 34 Publicity
  • Without running afoul of the publicity clause, a
    consultant can provide notice of contract award,
    and can use fact of contract award in proposals /
    SOQs submitted to government agencies

12
Highlights
  • Articles 35 36 Hazardous Materials and Safety
    these are new articles dealing with safety issues
    when on-site work is necessary
  • Specifies each partys rights and obligations
    regarding known or suspected hazards
  • Mn/DOT must provide legal access to job sites
  • Places clear limits on consultants responsibility

13
Highlights
  • Article 37 Termination / Suspension
  • Provides clear authority for suspension of work

14
Implementation?
  • ASAP
  • RFPs pending we plan to use the new general
    terms
  • Insurance limits will need to be reviewed in each
    of the next two years as tort claims limits
    increase

15
Questions