Title: NSTAR 345KV TRANSMISSION RELIABILITY PROJECT PLAN
1NSTAR 345KV TRANSMISSION RELIABILITY PROJECT PLAN
Presentation to the New England
Stakeholders January 31, 2005
2AGENDA
- 345 kV Project Overview
- Project Need
- Project Cost
- Project Alternatives
- Project Design
3345 KV PROJECT OVERVIEW
4Planned 345kV Supply To Downtown Boston Mitigates
These Concerns
Proposed 345 kV Transmission Cable
5NSTAR 345 kV Reliability Project One-Line Diagram
6CONSTRUCTION SEQUENCE
Stage I Construction - 2006 Stage II Construction
- 2007
7PROJECT NEED
8Emerging Transmission Concerns 2004-2010
115 kV Cable to Brighton overloads for loss of
companion cable 2005-2008
115 kV Lines to Lexington overload for loss of
DCT Line from Framingham 2004-2006
115 kV Cable to K Street overloads for loss of
companion cable 2005-2007
345 kV Cable to Kingston overloads for loss of
companion cable 2005-2007
115 kV Cable to K Street overloads for loss of
companion cable 2006-2008
Framingham 230A Auto overloads under normal
conditions 2008-2010
115 kV Cables to Baker St. overload for loss of
Needham DCT Lines 2005-2007
Medway 345A Auto overloads under normal
conditions 2008-2010
115 kV Line to Needham overloads under normal
conditions 2007-2009
9NEMA/BOSTON AREA
2006 SYSTEM
Transfer Capability Increased by 1000 MW
10Project Cost
11Project Cost Breakdown
12PROJECT ALTERNATIVES
13Alternatives Considered
- Upgrade Overloaded Facilities
- Requires 14 individual upgrades including
- 2 New Mystic to Kingston 345 kV underground
circuits (5 miles) - 2 New Needham to Newton 115 kV underground
circuits (5 miles) - 2 New Waltham to Watertown 115 kV underground
circuits (10 miles) - 1 New Walpole to Needham 115 kV overhead circuit
(10 miles) - Addition of 3 new autotransformers
- Replacement of 2 existing autotransformers
- Requires 4 simultaneous regulatory review
proceedings - Provides minimal transfer capability improvement
14Alternatives Considered
- Construct New 115 kV or 345 kV Overhead Facility
- New 115 kV lines lack sufficient capacity
- New 345 kV lines would require the following
- Expansion of existing ROW from Walpole to Needham
(10 miles) from 100 foot width to 300 foot width - Existing Right of Way ends 4 miles from Baker
Street Station, obtaining new ROW over this 4
mile section is estimated to cost over 60 M and
would require at least 3 years to obtain and
license - Overhead routes from Baker Street into Boston
unattainable and very costly - Highly congested area of the system
- All existing utilities are underground
- Licensing and eminent domain proceeding would
take many years - Numerous Underground 345 kV Facility Route
Alternatives Were Evaluated
15- South Boston Area
- Densely populated area of the city
- No overhead facilities exist in these areas
- Property takings and removal of structures would
be required -
16Overhead TransmissionCost of Right of Way
Acquisition
17PROJECT SCHEDULE
18PRELIMINARY PROJECT SCHEDULE
DEC 2003
DESIGN
MAR 2005
PERMITTING
JUN 2006
STATION CONST
MAR 2006
STREET CIVIL
JUNE 2006 In-service
CABLE SPLICING
19Appendix
20Transient Analysis Results
21What Was Studied
- Frequency Scan / Harmonic Resonance Analysis
- Energization Cases
- Cables Transformers
- Synchronous closing versus pre-insertion resistor
breakers - Fault Clearing Cases
- 1 ph-gnd 3 ph faults
- Reclosing OH lines
- 15 fault locations
22EMTP Model
Transmission System Study Area
23Harmonic Resonance Screening
- Analysis used to identify locations to monitor
- Harmonic resonance below 3rd can aggravate
transient problems but is not a problem itself - Value and intent is to target locations where
overvoltage conditions may be introduced
24Study Results
- Energizing cases simulated for
- 345 kV cables from Stoughton to K Street and Hyde
Park - 345/115 kV Transformers at K Street, Hyde Park
Holbrook - Above cases with Stoughton - Walpole / Stoughton
- Holbrook out of service - Above cases for closing into a fault
- Results indicate need for point on wave switching
(i.e. synchronous closing) or pre-insertion
resistors for breakers at Stoughton - Fault clearing cases for faults at K Street, Hyde
Park, Stoughton, Walpole Holbrook - Results indicate that line out of service
conditions at Stoughton call for a Special
Protection System
25Breaker Selection
- Based on results for equipment energization the
following breaker types will be employed - Stoughton 345 kV Ring Bus Pre-Insertion
Resistor - Stoughton 345 kV Reactors Synchronous Closing
- K Street 345 kV Bus / Reactors Synchronous
Closing - Hyde Park 345 kV Bus Normal Closing
- The 345 kV cables will only be energized from the
Stoughton 345 kV bus
26Study Results No SPS
27Study Results With SPS
28SPS Design
- SPS will be armed whenever either the Stoughton
to Walpole or the Stoughton to Holbrook 345 kV
lines are out of service - Reclosing for the 345 kV line that remains in
service will be disabled when the SPS is armed - 345 kV Reactors will be set to a total
compensation level of at least 400 MVAR any time
the Stoughton Walpole line is out. (Insures
acceptable response for faults at Holbrook)