Resource Requirements Planning:

About This Presentation
Title:

Resource Requirements Planning:

Description:

Gaither Chapter 11 12/19/95 ... Title: Chapter 11 Subject: Resource Requirements Planning Author: Sheri Nemeth and Mick Peters – PowerPoint PPT presentation

Number of Views:8
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: Resource Requirements Planning:


1
Chapter 15
  • Resource Requirements Planning
  • MRP and CRP

2
Overview
  • Resource Requirements Planning
  • Material Requirements Planning (MRP)
  • Capacity Requirements Planning (CRP)
  • Wrap-Up What World-Class Companies Do

3
Resource Requirements Planning
Aggregate Planning
Chapter 13
Master Production Scheduling (MPS)
Resource Requirements Planning
Material Requirements Planning (MRP)
Chapter 15
Capacity Requirements Planning (CRP)
4
  • Material Requirements Planning (MRP)

5
Materials Requirements Planning (MRP)
  • Computer based system
  • Explodes Master Schedule (MPS) into required
    amounts of raw materials and subassemblies to
    support MPS
  • Nets against current orders and inventories to
    develop production and purchased material
    ordering schedules

6
Objectives of MRP
  • Improve customer service
  • Reduce inventory investment
  • Improve plant operating efficiency

7
Elements of MRP
Inputs
Outputs
Inventory Transaction Data
Service-Parts Orders and Forecasts
Order Changes Order
Inventory Status File
Planned Order Schedule
MRP System
Master Production Schedule
Planning Report
Performance
Exception Reports
Bill of Materials File
8
MRP Computer Program
  • Begins with number of end items needed
  • Add service parts not included in MPS
  • Explode MPS into gross requirements by consulting
    bill of materials file
  • Modify gross requirements to get net
    requirements
  • Net Requirements Gross Requirements
  • Allocated Inventory
  • Safety Stock
  • - Inventory On Hand
  • Offset orders to allow for lead time

9
Outputs of MRP
  • Planned order schedule - quantity of material to
    be ordered in each time period
  • Changes to planned orders - modifications to
    previous planned orders
  • Secondary outputs
  • Exception reports
  • Performance reports
  • Planning reports

10
Example MRP Schedule
  • LocoMopeds is a manufacturer of off-road
    mopeds. The following product structure diagram
    represents the bill of materials for its
    dual-carburetor Model 442 moped.

MOPED
Level 0
ENGINE ASSEMBLY
GAS TANK
WHEEL ASSEMBLY (2)
FRAME
Level 1
MOTOR
CARBURETOR (2)
HUB ASSEMBLY
TIRE
Level 2
11
Example MRP Schedule
  • Bill of Material
  • Parent Component Level Compon.
  • Code Code Code Description Reqd
  • 442 0 442 Moped
  • 442 EA 1 Engine Assem. 1
  • GT 1 Gas Tank 1
  • WA 1 Wheel Assem. 2
  • F 1 Frame 1
  • EA M 2 Motor 1
  • C 2 Carburetor 2
  • WA HA 2 Hub Assem. 1
  • T 2 Tire 1

12
Example MRP Schedule
  • Inventory Status Report

Item Code On- Hand Safety Stock Lot Size Lead Time Sched. Receipts Qnty. Week Sched. Receipts Qnty. Week
442 500 200 LFL 1 -- --
EA 300 100 500 1 1000 10
GT 600 200 LFL 2 900 10
WA 500 400 500 1 2000 10
F 600 0 2000 3 2000 10
M 250 0 LFL 1 -- --
C 150 100 2500 2 -- --
HA 100 0 LFL 1 2400 11
T 500 500 1000 3 3000,2000 11,12
13
Example MRP Schedule
  • The company is currently planning production
    for weeks 10 through 16. Based on existing
    orders and demand forecasts, the master
    production schedule is as follows
  • Master Production Schedule 442 Moped
  • Determine the MRP schedule required to support
    the master production schedule for the Model 442
    moped in weeks 10-16.

14
Example MRP Schedule
  • MRP Schedule for 442 Mopeds for Weeks 10 - 16,
    considering that
  • Gross Requirements come from the moped MPS
  • There is an On-Hand balance of 500 mopeds at the
    end of week 9
  • There are no Scheduled Receipts for mopeds
  • A lot-for-lot rule is used for ordering mopeds
  • Safety stock of 200 mopeds is desired
  • Lead time for mopeds is one week

15
Example MRP Schedule
  • MRP Schedule for 442 Mopeds . . . Initially

16
Example MRP Schedule
  • MRP Schedule for 442 Mopeds . . . Completed

17
Example MRP Schedule
  • MRP Schedule for Gas Tanks for Weeks 10 - 16,
    considering that
  • Gross Requirements come from moped
    Planned-Order-Releases
  • There is an On-Hand balance of 600 gas tanks at
    the end of week 9
  • There is a Scheduled Receipt for 900 tanks in
    week 10
  • A lot-for-lot rule is used for ordering gas tanks
  • Safety stock of 200 gas tanks is desired
  • Lead time for gas tanks is two weeks

18
Example MRP Schedule
  • MRP Schedule for Gas Tanks . . . Initially

19
Example MRP Schedule
  • MRP Schedule for Gas Tanks . . . Completed

20
Example MRP Schedule
  • MRP Schedule for Frames for Weeks 10 - 16,
    considering that
  • Gross Requirements come from moped
    Planned-Order-Releases
  • There is an On-Hand balance of 600 frames at the
    end of week 9
  • There is a Scheduled Receipt for 2000 frames in
    week 10
  • The firm uses a Lot Size (multiple) of 2000 for
    ordering frames
  • No safety stock of frames is desired
  • Lead time for frames is 3 weeks

21
Example MRP Schedule
  • MRP Schedule for Frames . . . Initially

22
Example MRP Schedule
  • MRP Schedule for Frames . . . Completed

23
Example MRP Schedule
  • MRP Schedule for Engine Assemblies for Weeks 10 -
    16, considering that
  • Gross Requirements come from moped
    Planned-Order-Releases
  • There is an On-Hand balance of 300 engine
    assemblies at the end of week 9
  • There is a Scheduled Receipt for 1000 engine
    assemblies in week 10
  • The firm uses a Lot Size (multiple) of 500 for
    ordering engine assemblies
  • Safety Stock of 100 engine assemblies is desired
  • Lead time for engine assemblies is 1 week

24
Example MRP Schedule
  • MRP Schedule for Engine Assemblies . . . Initially

25
Example MRP Schedule
  • MRP Schedule for Engine Assemblies . . . Completed

26
Example MRP Schedule
  • MRP Schedule for Motors for Weeks 10 - 16,
    considering that
  • Gross Requirements come from engine assembly
    Planned-Order-Releases
  • There is an On-Hand balance of 250 motors at the
    end of week 9
  • There are no Scheduled Receipts for motors
  • A lot-for-lot rule is used for ordering motors
  • No Safety Stock of motors is desired
  • Lead time for motors is 1 week

27
Example MRP Schedule
  • MRP Schedule for Motors . . . Initially

28
Example MRP Schedule
  • MRP Schedule for Motors . . . Completed

29
Example MRP Schedule
  • MRP Schedule for Carburetors for Weeks 10 - 16,
    considering that
  • Gross Requirements come from engine assembly
    Planned-Order-Releases (times 2)
  • There is an On-Hand balance of 150 carburetors at
    the end of week 9
  • There are no Scheduled Receipts for carburetors
  • A Lot Size of 2500 is used for ordering
    carburetors
  • Safety Stock of 100 carburetors is desired
  • Lead time for carburetors is 2 weeks

30
Example MRP Schedule
  • MRP Schedule for Carburetors . . . Initially

31
Example MRP Schedule
  • MRP Schedule for Carburetors . . . Completed

32
Example MRP Schedule
  • MRP Schedule for Wheel Assemblies for Weeks 10 -
    16, considering that
  • Gross Requirements come from moped
    Planned-Order-Releases (times 2)
  • There is an On-Hand balance of 500 wheel
    assemblies at the end of week 9
  • There is a Scheduled Receipt for 2000 wheel
    assemblies in week 10
  • A Lot Size (multiple) of 500 is used for ordering
    wheel assemblies
  • Safety Stock of 400 wheel assemblies is desired
  • Lead time for wheel assemblies is 1 week

33
Example MRP Schedule
  • MRP Schedule for Wheel Assemblies . . . Initially

34
Example MRP Schedule
  • MRP Schedule for Wheel Assemblies . . . Completed

35
Example MRP Schedule
  • MRP Schedule for Hub Assemblies for Weeks 10 -
    16, considering that
  • Gross Requirements come from wheel assembly
    Planned-Order-Releases
  • There is an On-Hand balance of 100 hub assemblies
    at the end of week 9
  • There is a Scheduled Receipt of 2400 hub
    assemblies in week 11
  • A lot-for-lot rule is used for ordering hub
    assemblies
  • No Safety Stock of hub assemblies is desired
  • Lead time for hub assemblies is 1 week

36
Example MRP Schedule
  • MRP Schedule for Hub Assemblies . . . Initially

37
Example MRP Schedule
  • MRP Schedule for Hub Assemblies . . . Completed

38
Example MRP Schedule
  • MRP Schedule for Tires for Weeks 10 - 16,
    considering that
  • Gross Requirements come from wheel assembly
    Planned-Order-Releases
  • There is an On-Hand balance of 500 tires at the
    end of week 9
  • There are Scheduled Receipts for 3000 and 2000
    tires weeks 11 and 12, respectively
  • A Lot Size (multiple) of 1000 is used for
    ordering tires
  • Safety Stock of 500 tires is desired
  • Lead time for tires is 3 weeks

39
Example MRP Schedule
  • MRP Schedule for Tires . . . Initially

40
Example MRP Schedule
  • MRP Schedule for Tires . . . Completed

41
Lot-Sizing in MRP
  • Lot-size is the quantity ordered/produced at one
    time
  • Large lots are preferred because
  • Changeovers cost less and capacity greater
  • Annual cost of purchase orders less
  • Price breaks and transportation breaks can be
    utilized
  • Small lots are preferred because
  • Lower inventory carrying cost
  • Reduced risk of obsolescence
  • Shorter cycle time to produce customer order

42
Lot-Sizing Methods
  • Typical MRP methods
  • accommodates lumpy demand
  • Lot-for-Lot (LFL)
  • Period Order Quantity (POQ)
  • Comments on Economic Order Quantity (EOQ)
  • does not consider quantity discounts
  • does not always provide the most economical
    approach with lumpy demand

43
Example Lot-Sizing Decision
  • The net requirements for a material from an MRP
    schedule are
  • It costs 400 to change over the machines for
    this material in the affected work center. It
    costs 0.40 per unit when one unit of this
    material must be carried in inventory from one
    week to the next.
  • Identify the lot-sizing method that results in
    the least carrying and changeover costs for the
    8-week schedule.

44
Example Lot-Sizing Decision
  • Lot-for-Lot Method
  • Carrying Cost 0(.40) 0
  • Changeover Cost 6(400) 2,400
  • Total 2,400

45
Example Lot-Sizing Decision
  • Economic Order Quantity (EOQ) Method
  • S 400.00
  • D (Net Req. for 8 wks)/8 weeks)(50
    weeks/year)
  • (6400/8)(50) 40,000
  • C (0.40 per week)(50 weeks/year)
  • 20.00

46
Example Lot-Sizing Decision
  • Economic Order Quantity (EOQ) Method
  • Carrying Cost 4855(.40) 1,942
  • Changeover Cost 6(400) 2,400
  • Total 4,342

47
Example Lot-Sizing Decision
  • Period Order Quantity (POQ) Method
  • POQ ( Weeks/year)/( Orders/year)
  • 50/(D/EOQ)
  • 50/(40,000/1,265)
  • 1.58 or 2 weeks

48
Example Lot-Sizing Decision
  • Period Order Quantity (POQ) Method
  • Carrying Cost 2900(.40) 1,160
  • Changeover Cost 4(400) 1,600
  • Total 2,760

49
Example Lot-Sizing Decision
  • Summary
  • Carrying Chg.Ovr. Total
  • Method Cost Cost Cost
  • LFL 0 2,400 2,400
  • EOQ 1,942 2,400 4,342
  • POQ 1,160 1,600 2,760

50
Issues in MRP
  • Lot-Sizing
  • Useful at lower levels but may drive excess
    inventory when applied at higher levels
  • Net Change versus Regenerative MRP
  • Net change may generate too many action notices
  • Regenerative more costly to run but appears to be
    easier to manage
  • . . . more

51
Issues in MRP
  • Safety Stock
  • Use depends on uncertainty of demand..... more
    uncertain the greater the need for safety stock
  • Assemble-to-Order Firms
  • MPS and MRP treated separately from Final
    Assembly Schedule(FAS)
  • FAS is prepared 1-2 weeks ahead
  • Use Modular Bill of Material
  • For each option with a demand forecast

52
MRP I to MRP II
  • MRP I simply exploded demand (MPS) into required
    materials
  • MRP II became Manufacturing Resource Planning
    which provides a closed-loop business management
    system
  • Financial management
  • Shop floor control
  • Operations management
  • Simulation capability

53
Evaluation of MRP
  • Most beneficial to process-focused systems that
    have long processing times and complex multistage
    production steps
  • Lead times must be reliable
  • Must freeze MPS for some time before actual
    production... certain demand
  • Difficult to implement

54
Capacity Requirements Planning (CRP)
55
Capacity Requirements Planning (CRP)
  • Tests MPS for feasibility
  • Utilizes routings to determine labor/machine
    loads
  • If schedule feasible, recommends freezing
  • If schedule overloads resources, points out
    processes that are overscheduled

56
Load Schedules
  • Compares actual labor and machine hours against
    available hours
  • Offsets schedules between successive stages of
    production by lead times
  • Provides feasible MPS and economically loaded
    work centers
  • Promotes system operating efficiency ... lowers
    costs!

57
HW Chapter 15
  • HW 7 and 16 on page 612 and 617.

58
End of Chapter 15
Write a Comment
User Comments (0)