Title: MACEDONIA IRRIGATION AND REHBAILITATION PROJECT


1
MACEDONIA IRRIGATION AND REHBAILITATION PROJECT
  • LILE SIMONOVSKA

2
Macedonia Irrigation Rehabilitation
Restructuring Project
REPUBLIC OF MACEDONIA MINISTRY OF AGRICULTURE, FO
RESTRY WATER ECONOMY
Governament support of Irrigation sector reform
  • Legislation framework
  • Establishing of new water economies (WE)
  • Establishing of Irrigation water comunities
    (IWC)
  • Rehabilitation of main irrigation
    infrastructure
  • Rehabilitation of IWC distributive network
  • WE Capacity buildig program
  • IWC Capacity buildig program

3
Macedonia Irrigation Rehabilitation
Restructuring Project
  • Water Economies Law
  • WE are resposible for OM of the main structures
    (dams) and chanals
  • WE may be established in order to supply water
    for irrigation drinking, domestic and
    commercial uses industrial uses, including power
    generation.
  • Autonomous self-funding public law bodies
  • Managed Board of water users
  • Irrigation Water Comunities Law
  • IWC is an association of owners or users of
    agricultural land associated and responsible for
    management, OM, construction, reconstruction or
    expansion of tertiary and/or secondary network or
    small irrigation schemes
  • IWC is legal entity and is non-profit
  • Management board (farmers and local self
    governament representatives)

4
Macedonia Irrigation Rehabilitation
Restructuring Project
Empowered IWC (WUAs)
  • IWC acctivities
  • Preparations for the irrigation season
  • Evaluation of previous irrigation season
  • System walk-through
  • Annual work plan
  •      the provisional cropping plan
  •     proposed maintenance and repair works
  •     proposed manner of water distribution
  •     proposed way of fee collection
  •     proposed schedule of Assembly meetings, and
  •     proposed hiring of staff and/or labour
  • WUA budget
  • Cash flow forecast


5
Macedonia Irrigation Rehabilitation
Restructuring Project
Empowered IWC (WUAs)
  • IWC acctivities
  • 2. Operation and maintenance
  • Cleaning/repair of irrigation infrastructure
  • Irrigation requests from farmers
  • Advance payment of water fees
  • Submit water needs to WE
  • Recruit a water masters
  • Publish irrigation requests on notice board
  • Prepare irrigation schedule
  • Field irrigation
  • Maintenance/repairs as needed

Rehabilitation of IWC distributive network
(first year suport from the Project)
6
Macedonia Irrigation Rehabilitation
Restructuring Project
Empowered IWC (WUAs)
  • IWC acctivities
  • 3. Collection of water fees
  • Irrigation requests from farmers
  • Collect advance payment of water fees from member
    farmers
  • Submit water needs to WE
  • Publish irrigation requests on notice board
  • Prepare irrigation schedule
  • Field irrigation
  • Collecting water fees during the irrigation (on
    the field)
  • Payment of monthly bill to WE
  • Reserve found

7
Macedonia Irrigation Rehabilitation
Restructuring Project
Empowered IWC (WUAs)
  • Elements of IWC water fee calculation
  • Water Economys price of water (m3)
  • IWC Yearly amount of water (m3) demanded from
    WE
  • IWC internal costs for MO
  • IWC is responsible for collecting of water fee
    from farmers
  • No money no water!!!
  • 100 of water fee payment

8
IWC organizational strengthening
9
Macedonia Irrigation Rehabilitation
Restructuring Project
Various functions looked after by the private
sector
  • Planning (irrigated area, crop pattern, required
    quantity of water)
  • IWC Management board
  • Construction (structures, network, compensation
    basins)
  • Construction firms
  • Design (extension of network, new irrigation
    methods and field irrigation equipment)
  • Extension agencies
  • Maintenance (annual maintenance, specific
    maintenance and repair of hydro equipment)
  • IWC private civil working firms
  • Capacity building program
  • National consultant firm
  • Financial management (preparation of invoices and
    financial statements, auditing)
  • Private accountant

10
Macedonia Irrigation Rehabilitation
Restructuring Project
Rehabilitation of irrigation infrastructure
  • HMS Tikves 13.400ha
  • Acumulation (dam), intake tunnel, joint chanal,
    right and left magistral chanal, distributive
    network (secundary chanals, pipelines)
  • Planned reconstruction of open trapez chanals
    90,98 km
  • Completed reconstruction and sanations of 67,88
    km(75)
  • Planned reconstruction of distributive network
    for 13.375 ha
  • On going reconstruction
  • HMS Bregalnica20.400ha
  • Accumulation (dam), right and left magistral
    chanal, distributive network (secundary chanals,
    papelines)
  • Planned reconstruction of open trapez chanals of
    74,50 km
  • Completed reconstruction and sanations of 50,50
    km(68)
  • Planned reconstruction of distributive network
    for 20.393 ha
  • On going reconstruction
  • HMS Polog8.000ha
  • Main irrigation chanals, distributive network
    (secundary chanals, papelines)
  • Planned reconstruction of open trapez chanals
    20,90 km
  • Completed reconstruction and sanations of 15,60
    km(75)
  • Planned reconstruction of distributive network
    for 8.000 ha
  • On going reconstruction