Title: Mitigating Traffic Impacts on Utah
1Mitigating Traffic Impacts on Utahs I-15
- Making Work Zones Work Better Workshop
John Leonard, PE Utah Department of Transportation
2Utah - Crossroads of the West
3Project Limits
4Project Scope
- 17 miles of Interstate Highway
- Utahs First Car Pool Lanes
- 8 Major Interchanges Reconstructed
- 3 Freeway to Freeway Junctions Rebuilt
- 144 Bridges Replaced
- 9 Million Cubic Yards of Embankment
- 3.4 Million Square Yards of Pavement
- Program Cost 1.59 Billion
5Social and Traffic Trends
6(No Transcript)
7Background
- Early Public Perception
- Freeway is working OKwhy do we need to rebuild?
- No public will to endure major construction
- No public desire to fund major project
- We will take care of it when it gets bad
8Background
- By 1994, public begins to believe freeway needs
to be rebuilt - Congestion and travel times increasing
- Major deterioration visible
- 1995, UDOT created a team to lead the Project and
move it to completion - Project Director
- Financial Manager
- Structures
- Design
- MOT/Operations
- Staff Support
9Background
- FEIS process
- Formal public meetings
- Open houses
- Community Councils
- Citizens groups
- NEPA process
- Over 130 separate meetings
10Conclusion of Research (1995)
The public would prefer a greater level of
impact in exchange for a shorter construction
duration
11Research
Get in, Get it Done, And Get out!!
12Background
- Original concept was traditional construction
- Design-Bid-Build
- 8-10 year duration
- Investigated different and innovative design and
construction strategies - Design/Build was chosen in January 96
- Construct project in 4 ½ years
13Maintenance of Traffic
14Maintenance of Traffic
- Large impact to traffic patterns
- We need to take a different approach to managing
traffic during construction
15Maintenance of Traffic
- The UDOT I-15 Team Approach
- UDOT
- Contractor
- DAQ
- Local Communities
- Emergency Services
- Public!!!!
16Team Approach
- Maintenance of Traffic
- Transportation Demand Management
- Public Information Plan
17Maintenance of Traffic
- Development of impact mitigation alternatives
- Parallel street projects
- Capacity improvements on corridors
18Cost Influence Curve
Conceptual Planning
High
High
Design
Ability to Influence Cost
Project Expenditures
Procurement
Construction
Start-up
Low
Low
Complete
Start
Time
DBIA
19Process
- Involvement process began early
- Met with mayors, city engineers, and public works
directors of affected jurisdictions - 6 Cities, 1 County on corridor
- 8 Cities, 1 County off corridor
- Received endorsement for D/B concept
- Presented preferred alternative and potential
construction schedule
20Parallel Streets
- Reviewed routes along the corridor
- Identified capacity constraints, community
issues, and possible alternate routes - Identified 21 potential projects to make
improvements - Used a macroscopic model to evaluate potential
improvements - 9 projects recommended for construction, with a
value of 50 Million
21Parallel Street Projects
- 2 projects were on the shelf
- Had completed EISs
- Widened a parallel route from 2 to 6 lanes
- Remainder were spot improvements
- Removed choke points
- Removed medians and added lanes
- Enhanced intersection capacity
22Parallel Street Projects
- All projects were to be fast track advertised
by early 1996, with required completion prior to
major construction beginning in summer 1997 - UDOT Region assisted both with design and project
oversight
23Emergency Responders
- Facilitated cooperative meetings among all
emergency agencies - Law enforcement
- Fire
- Medical
24Emergency Responders
- Created command structure, and created cross
jurisdictional responses - Best able to respond
- Utah Highway Patrol was lead law enforcement
agency - Alleviated fears of increased response time
25Trucking Industry
- Large impacts to interstate travel
- Crossroads of the west
- Need to coordinate with closures
- Provide real time information for routing
- Detours to local streets for LCVs and Hazmat
carriers
26Business Community
- Hosted business fairs
- Encouraged flexible schedules
- Car pools
- Telecommuting
- how to cope seminars
- Print ready materials
27Transportation Demand Management
- A variety of methods for reducing transportation
demand on the street system. - Coordination with existing Utah Transit Authority
programs - Employee-sponsored bus passes (deep discount
program) - Rideshare (carpooling) - computerized rider
matching program - Vanpool (UTA financed van purchase or lease)
- Other trip reduction strategies
- Flextime
- Telecommuting
- Public Information Plan
28Public Information Plan Challenges
- Creating partnerships with the media,
Communities, Businesses, and Public - Convincing a change in driver habits -- promoting
the benefits - Communicating the vision
29Public Information Plan
- Information to the public
- Whats the schedule?
- What is open and closed?
- How do we cope?
- Information from the public
30 31Request for Proposals
- Set the framework for the contract
- Laid down the ground rules
- Provided contractor with flexibility, but with
constraints - Assigned risk to those who could best handle it
- Issued October, 1996
- Best and Final Offer in February, 1997
32Request for Proposals
- Maintenance of Traffic Specification
- Responded to community concerns
- Provided maximum flexibility
- Allowed for innovation
33Maintenance of TrafficPerformance Specification
- I-15 Mainline
- 2 lanes open each direction during peak hours
- Peak Hours
- 6 AM to 10 PM weekdays
- 8 AM to 7 PM weekends
- Junctions
- maintain freeway to freeway movements through
existing ramps or freeway detours - Downtown
- 2 accesses open at all times
34Maintenance of TrafficPerformance Specification
- Interchanges
- cross streets at interchanges may be closed for a
maximum of 6 months - This may occur IF one is south of the I-15/I-215
Junction, and one is north of it. - complete remaining construction in following 6
months - close movement if it is available at adjacent
interchange
35Maintenance of TrafficPerformance Specification
- Other
- Coordination with ATMS system
- Provide off-duty uniformed officer and car on the
corridor - Provide motorist guidance
- Aid in emergency response
- Provide a courtesy patrol
- Provide emergency pullouts every km
36The Selection Process
Technical Proposal
Price
37Proposal Evaluation
- Price and technical proposals had equal weight
- Maintenance of traffic was 1 of 6 technical areas
- Proposals were evaluated for Best Value
38EVALUATION FACTORS
- Technical Solutions
- Maintenance of Traffic
- Geotechnical
- Structures
- Pavement
- Maintainability
- Aesthetics, Drainage, Roadway Geometry, Lighting,
Traffic Signals, Signing, Water Quality,
Harmful/Hazardous Materials Remediation, Concrete
Barriers, and ATMS - Work Plan/Schedule
- Management
- Organizational Qualifications
- Price
39Proposals
- Enhancements by successful proposer
- Maintain 3 lanes on southern end of project
through junction with I-215 - Restripe west side of I-215 belt route to 4 lanes
each direction - Required modification and enhancements
- Reduce interchange cross street closure to 4
months - Expanded use of night operations
- Freeway closures in the off-peak hours
40Proposals
- Enhancements by successful proposer
- Added courtesy patrol to west side belt route
- Expanded use of off-duty law enforcement
- Much simpler construction phasing
- Better driver expectancy
- Opened south end of project 1 year early
41Proposals
- Enhancements by successful proposer
- Provided glare screen entire length of corridor
to reduce construction gawking and improving
capacity - Use of ITS elements as they became available
- Dedicated staff for both design and
implementation of MOT
42Coordination
- Weekly meetings with UDOT, the contractor,
design, UHP, all Segments, public information,
and local jurisdications - Coordinated proposed work schedule for following
week corridor wide - No conflicts or overlaps
- Conformance with contract
43Coordination
- Web site and phone tree up to date
- Constant interaction with local entities
- Personal visits to affected neighborhoods
- Personal visits to affected businesses
- Photo-ready maps and materials
- Respond to individual requests
- Dedicated contractor staff to work out any issues
- Hot line
- Interactive
- Could leave message or talk to real person
44How the Public is Informed
- 60 of Drivers get information from the Media
- 15 from the Internet
- 9 from UDOT
- 3 from I-15 Hotline (1-888-INFO-I15)
- Only 7 dont know where to get information
- this number continues to decline
45Deseret News/Dan Jones PollJuly 28, 1997
- 82 inconvenienced
- 86 are well informed
- 70 still agree with design/build decision
46Traffic Conditions
47Corridor Traffic Conditions
- 209,000 vehicles per weekday on I-15 in June,
1996 - Lane use of 17,400 vplpd in 12 lanes
- 24 hour per day use
- 12 lanes, full shoulders
- 93,500 vehicles per weekday on I-15 in June, 1999
- Lane use of 23,400 vplpd in four lanes
- 16 hour per day use (closed 10 pm to 6 am)
- 11 lanes, 2 shoulders
- 115,500 vpwd displaced
48(No Transcript)
49(No Transcript)
50Results
- This indicated traffic was not entering local
neighborhoods, as originally feared by residents - Parallel street projects provided route
continuity and capacity - Public education informed motorists which routes
were available
51Summary
- The decision to fast track the project was driven
by the public, not the Department - The public was a partner in the development of
the MOT specification, through many outreach
meetings and focus groups
52Summary
- Local governments were a partner in the process,
including the determination of early action item
improvements to surface streets - Emergency responders were partners in the
determination of restrictions on adjacent
movements, and were involved intimately
throughout the Project
53Summary
- Other transportation industry stakeholders were
partners, including the trucking industry, the
recreation industry, bus transit, light rail, and
the cab/private hire industry - The business community were partners in changing
work and delivery schedules
54Summary
- The media was a partner in providing up to date
and accurate information to the public - Traffic reporters were in the loop on what was
going to happen - The approval rating of UDOT was higher than it
had ever been - Seen as responsive to the public needs
55Summary
- Communication is the key
- If you arent sick of communicating, you are not
communicating enough - Work with all stakeholders, find common ground,
and keep all commitments - Be proactive when possible
- Be reactive when necessary
56Summary
- Maintain flexibility
- Allow innovation
- Think outside the box
- Project mitigation begins long before the first
barrel hits the pavement
57Questions?
- John Leonard, PE
- Operations Engineer
- Division of Traffic and Safety
- Utah Department of Transportation
- 801-965-4045
-
jleonard_at_utah.gov