Mitigating Traffic Impacts on Utah

About This Presentation
Title:

Mitigating Traffic Impacts on Utah

Description:

Title: PowerPoint Presentation Author: Jeremy Rephlo Last modified by: PDPC Created Date: 12/17/2003 4:49:21 AM Document presentation format: On-screen Show – PowerPoint PPT presentation

Number of Views:14
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: Mitigating Traffic Impacts on Utah


1
Mitigating Traffic Impacts on Utahs I-15
  • Making Work Zones Work Better Workshop

John Leonard, PE Utah Department of Transportation
2
Utah - Crossroads of the West
3
Project Limits
4
Project Scope
  • 17 miles of Interstate Highway
  • Utahs First Car Pool Lanes
  • 8 Major Interchanges Reconstructed
  • 3 Freeway to Freeway Junctions Rebuilt
  • 144 Bridges Replaced
  • 9 Million Cubic Yards of Embankment
  • 3.4 Million Square Yards of Pavement
  • Program Cost 1.59 Billion

5
Social and Traffic Trends
6
(No Transcript)
7
Background
  • Early Public Perception
  • Freeway is working OKwhy do we need to rebuild?
  • No public will to endure major construction
  • No public desire to fund major project
  • We will take care of it when it gets bad

8
Background
  • By 1994, public begins to believe freeway needs
    to be rebuilt
  • Congestion and travel times increasing
  • Major deterioration visible
  • 1995, UDOT created a team to lead the Project and
    move it to completion
  • Project Director
  • Financial Manager
  • Structures
  • Design
  • MOT/Operations
  • Staff Support

9
Background
  • FEIS process
  • Formal public meetings
  • Open houses
  • Community Councils
  • Citizens groups
  • NEPA process
  • Over 130 separate meetings

10
Conclusion of Research (1995)
The public would prefer a greater level of
impact in exchange for a shorter construction
duration
11
Research
Get in, Get it Done, And Get out!!
12
Background
  • Original concept was traditional construction
  • Design-Bid-Build
  • 8-10 year duration
  • Investigated different and innovative design and
    construction strategies
  • Design/Build was chosen in January 96
  • Construct project in 4 ½ years

13
Maintenance of Traffic
14
Maintenance of Traffic
  • Large impact to traffic patterns
  • We need to take a different approach to managing
    traffic during construction

15
Maintenance of Traffic
  • The UDOT I-15 Team Approach
  • UDOT
  • Contractor
  • DAQ
  • Local Communities
  • Emergency Services
  • Public!!!!

16
Team Approach
  • Maintenance of Traffic
  • Transportation Demand Management
  • Public Information Plan

17
Maintenance of Traffic
  • Development of impact mitigation alternatives
  • Parallel street projects
  • Capacity improvements on corridors

18
Cost Influence Curve
Conceptual Planning
High
High
Design
Ability to Influence Cost
Project Expenditures
Procurement
Construction
Start-up
Low
Low
Complete
Start
Time
DBIA
19
Process
  • Involvement process began early
  • Met with mayors, city engineers, and public works
    directors of affected jurisdictions
  • 6 Cities, 1 County on corridor
  • 8 Cities, 1 County off corridor
  • Received endorsement for D/B concept
  • Presented preferred alternative and potential
    construction schedule

20
Parallel Streets
  • Reviewed routes along the corridor
  • Identified capacity constraints, community
    issues, and possible alternate routes
  • Identified 21 potential projects to make
    improvements
  • Used a macroscopic model to evaluate potential
    improvements
  • 9 projects recommended for construction, with a
    value of 50 Million

21
Parallel Street Projects
  • 2 projects were on the shelf
  • Had completed EISs
  • Widened a parallel route from 2 to 6 lanes
  • Remainder were spot improvements
  • Removed choke points
  • Removed medians and added lanes
  • Enhanced intersection capacity

22
Parallel Street Projects
  • All projects were to be fast track advertised
    by early 1996, with required completion prior to
    major construction beginning in summer 1997
  • UDOT Region assisted both with design and project
    oversight

23
Emergency Responders
  • Facilitated cooperative meetings among all
    emergency agencies
  • Law enforcement
  • Fire
  • Medical

24
Emergency Responders
  • Created command structure, and created cross
    jurisdictional responses
  • Best able to respond
  • Utah Highway Patrol was lead law enforcement
    agency
  • Alleviated fears of increased response time

25
Trucking Industry
  • Large impacts to interstate travel
  • Crossroads of the west
  • Need to coordinate with closures
  • Provide real time information for routing
  • Detours to local streets for LCVs and Hazmat
    carriers

26
Business Community
  • Hosted business fairs
  • Encouraged flexible schedules
  • Car pools
  • Telecommuting
  • how to cope seminars
  • Print ready materials

27
Transportation Demand Management
  • A variety of methods for reducing transportation
    demand on the street system.
  • Coordination with existing Utah Transit Authority
    programs
  • Employee-sponsored bus passes (deep discount
    program)
  • Rideshare (carpooling) - computerized rider
    matching program
  • Vanpool (UTA financed van purchase or lease)
  • Other trip reduction strategies
  • Flextime
  • Telecommuting
  • Public Information Plan

28
Public Information Plan Challenges
  • Creating partnerships with the media,
    Communities, Businesses, and Public
  • Convincing a change in driver habits -- promoting
    the benefits
  • Communicating the vision

29
Public Information Plan
  • Information to the public
  • Whats the schedule?
  • What is open and closed?
  • How do we cope?
  • Information from the public

30
  • Design/Build

31
Request for Proposals
  • Set the framework for the contract
  • Laid down the ground rules
  • Provided contractor with flexibility, but with
    constraints
  • Assigned risk to those who could best handle it
  • Issued October, 1996
  • Best and Final Offer in February, 1997

32
Request for Proposals
  • Maintenance of Traffic Specification
  • Responded to community concerns
  • Provided maximum flexibility
  • Allowed for innovation

33
Maintenance of TrafficPerformance Specification
  • I-15 Mainline
  • 2 lanes open each direction during peak hours
  • Peak Hours
  • 6 AM to 10 PM weekdays
  • 8 AM to 7 PM weekends
  • Junctions
  • maintain freeway to freeway movements through
    existing ramps or freeway detours
  • Downtown
  • 2 accesses open at all times

34
Maintenance of TrafficPerformance Specification
  • Interchanges
  • cross streets at interchanges may be closed for a
    maximum of 6 months
  • This may occur IF one is south of the I-15/I-215
    Junction, and one is north of it.
  • complete remaining construction in following 6
    months
  • close movement if it is available at adjacent
    interchange

35
Maintenance of TrafficPerformance Specification
  • Other
  • Coordination with ATMS system
  • Provide off-duty uniformed officer and car on the
    corridor
  • Provide motorist guidance
  • Aid in emergency response
  • Provide a courtesy patrol
  • Provide emergency pullouts every km

36
The Selection Process
Technical Proposal
Price
37
Proposal Evaluation
  • Price and technical proposals had equal weight
  • Maintenance of traffic was 1 of 6 technical areas
  • Proposals were evaluated for Best Value

38
EVALUATION FACTORS
  • Technical Solutions
  • Maintenance of Traffic
  • Geotechnical
  • Structures
  • Pavement
  • Maintainability
  • Aesthetics, Drainage, Roadway Geometry, Lighting,
    Traffic Signals, Signing, Water Quality,
    Harmful/Hazardous Materials Remediation, Concrete
    Barriers, and ATMS
  • Work Plan/Schedule
  • Management
  • Organizational Qualifications
  • Price

39
Proposals
  • Enhancements by successful proposer
  • Maintain 3 lanes on southern end of project
    through junction with I-215
  • Restripe west side of I-215 belt route to 4 lanes
    each direction
  • Required modification and enhancements
  • Reduce interchange cross street closure to 4
    months
  • Expanded use of night operations
  • Freeway closures in the off-peak hours

40
Proposals
  • Enhancements by successful proposer
  • Added courtesy patrol to west side belt route
  • Expanded use of off-duty law enforcement
  • Much simpler construction phasing
  • Better driver expectancy
  • Opened south end of project 1 year early

41
Proposals
  • Enhancements by successful proposer
  • Provided glare screen entire length of corridor
    to reduce construction gawking and improving
    capacity
  • Use of ITS elements as they became available
  • Dedicated staff for both design and
    implementation of MOT

42
Coordination
  • Weekly meetings with UDOT, the contractor,
    design, UHP, all Segments, public information,
    and local jurisdications
  • Coordinated proposed work schedule for following
    week corridor wide
  • No conflicts or overlaps
  • Conformance with contract

43
Coordination
  • Web site and phone tree up to date
  • Constant interaction with local entities
  • Personal visits to affected neighborhoods
  • Personal visits to affected businesses
  • Photo-ready maps and materials
  • Respond to individual requests
  • Dedicated contractor staff to work out any issues
  • Hot line
  • Interactive
  • Could leave message or talk to real person

44
How the Public is Informed
  • 60 of Drivers get information from the Media
  • 15 from the Internet
  • 9 from UDOT
  • 3 from I-15 Hotline (1-888-INFO-I15)
  • Only 7 dont know where to get information
  • this number continues to decline

45
Deseret News/Dan Jones PollJuly 28, 1997
  • 82 inconvenienced
  • 86 are well informed
  • 70 still agree with design/build decision

46
Traffic Conditions
47
Corridor Traffic Conditions
  • 209,000 vehicles per weekday on I-15 in June,
    1996
  • Lane use of 17,400 vplpd in 12 lanes
  • 24 hour per day use
  • 12 lanes, full shoulders
  • 93,500 vehicles per weekday on I-15 in June, 1999
  • Lane use of 23,400 vplpd in four lanes
  • 16 hour per day use (closed 10 pm to 6 am)
  • 11 lanes, 2 shoulders
  • 115,500 vpwd displaced

48
(No Transcript)
49
(No Transcript)
50
Results
  • This indicated traffic was not entering local
    neighborhoods, as originally feared by residents
  • Parallel street projects provided route
    continuity and capacity
  • Public education informed motorists which routes
    were available

51
Summary
  • The decision to fast track the project was driven
    by the public, not the Department
  • The public was a partner in the development of
    the MOT specification, through many outreach
    meetings and focus groups

52
Summary
  • Local governments were a partner in the process,
    including the determination of early action item
    improvements to surface streets
  • Emergency responders were partners in the
    determination of restrictions on adjacent
    movements, and were involved intimately
    throughout the Project

53
Summary
  • Other transportation industry stakeholders were
    partners, including the trucking industry, the
    recreation industry, bus transit, light rail, and
    the cab/private hire industry
  • The business community were partners in changing
    work and delivery schedules

54
Summary
  • The media was a partner in providing up to date
    and accurate information to the public
  • Traffic reporters were in the loop on what was
    going to happen
  • The approval rating of UDOT was higher than it
    had ever been
  • Seen as responsive to the public needs

55
Summary
  • Communication is the key
  • If you arent sick of communicating, you are not
    communicating enough
  • Work with all stakeholders, find common ground,
    and keep all commitments
  • Be proactive when possible
  • Be reactive when necessary

56
Summary
  • Maintain flexibility
  • Allow innovation
  • Think outside the box
  • Project mitigation begins long before the first
    barrel hits the pavement

57
Questions?
  • John Leonard, PE
  • Operations Engineer
  • Division of Traffic and Safety
  • Utah Department of Transportation
  • 801-965-4045

jleonard_at_utah.gov
Write a Comment
User Comments (0)