Title: Electricity Reforms
1Electricity Reforms
- Global Experiences The first few pages of a long
story
Presentation to media 7th July 2005, ITDG
2Electricity Reforms History
- Started in 1980s with reforms in Chile in 1983
- Has become a worldwide trend (a World Bank survey
conducted in 1999 shows a world wide trend in
electricity reforms)
- Reforms have brought mixed results with serious
re-thinking on future shapes of reforms
3Nature of Reforms
- Market driven Brings state-owned electricity
industries into market logic
- Unbundling of the integrated industry
- Independent regulation
4Unbundling the Industry
- Vertical Unbundling
- Horizontal unbundling
5Vertical Unbundling
Stage 4 Complete vertical unbundling
Stage 3 Unbundled generation and distribution,
common transmission
Stage 2 Unbundled generation, common
transmission and distribution
Stage 1 Vertically Integrated Utility
6Horizontal Unbundling
1 2 3 4 5
6 7 8 9 10
stage
Stage 1 Ministry Department Stage 2 Parastatal
Stage 3 Corporatization Stage 4
Commercialization Stage 5 Contract management S
tage 6 Amendment of the Electricity Act
Stage 7 Establishment of independent regulatory
body Stage 8 IPPs Privatization of generation
Stage 9 Privatization of generation and
distribution Stage 10 Privatization of generatio
n, transmission and distribution
7- Ministry Department
- Power Utilitys parent ministry/department
manages the utility directly and also makes key
capital investment decisions
- Parastatal
- The utility becomes a state body with its own
management with more powers to decide and
implement investments with the parent
ministry/dept. providing policy directives - Corporatization
- Utility is accorded the status of a limited
liability corporate body. As a corporate body the
utility may seek alternative financing through
floatation of shares on the stock market or
issuing bonds. However, the government may retain
majority shares.
8- Commercialization
- The utility operates on a commercial basis,
ceasing to be a welfare-oriented organization.
The utility would focus on profitability.
- Contract management
- The management of the utility is contracted out
to a private entity. The utility, however, still
remains the owner of the assets.
9Guidelines for Assessing Success of Reforms
- Assessment of financial performance of the
industry
- (e.g. financial stability, efficiency
improvements of the system, etc.)
- Assessment of electricity supply as a service to
public
- (e.g. access, affordability, quality, etc.)
- Assessment of the performance not in isolation
but in integration to development of the country
- (e.g. bulk prices, sustainability, sovereignty,
job creation, etc.)
10Hegemonic Focus of Assessment
Financial Performance
Service to public
Development of the country
11Focus of this Presentation
Financial Performance
Service to Public
Development of the Country
Poor
Status of Renewables and Off-grid Electrification
12References
- Karekezi, S and Sihag, A (eds.) (2004). Energy
Access theme results. Energy Access working
Group Global Network on Energy for Sustainable
Development, Denmark - Thomas et al (2005). Turning Off the Lights The
Threat to Community Electricity in Sri Lanka.
ITDG, London
- Dubash N (eds.) (2002). Power Politics Equity
and Environment in Electricity Reform. World
Resource Institute
- Cho A and Dubash N (2003). Will Investment Rules
Shrink Policy Space for Sustainable development?
Evidence from Electricity Sector. World Resource
Institute Working Paper. World Resource
Institute. - FDC (2004). Privatization of the Philippines
Power Industry Issues and Struggles. Freedom
from Debt Coalition. Manila
- WGPSR (2004). Press Release The Constitutional
Court Decision to Annul the Electricity Law
No.20/2002. Working Group on Power Sector
Restructuring. Indonesia. - Prayas (2004). Know Your Power A Citizens
Primer on the Electricity Sector. Prayas Energy
Group. Pune
13Countries investigated
- Argentina Ghana Bulgaria India
- Indonesia South Africa Chile
- Morocco Kenya
- Uganda Senegal Mali
- Zimbabwe Philippines
- Thailand Bangladesh Vietnam
- China Peru El Salvador
- Brazil
California
14Aspects Investigated
- history of reforms access affordability
efficiency improvements of the system
financial performance of the utility
environmental impacts inflow of private
capital political uprisings motivations for
reform degree of consultation in reforms
lock-in corruption involved with reforms
IFI role in reforms
regulation integration of interests
of poor in reforms / special programs to increase
electrification
15Impacts of Electricity Reforms in Improving
Access to Poor
16Impacts of Electricity Reforms in Improving
Access to Poor
- Overall levels of electrification, in general,
are either not affected or on the increase from
pre-reforms to post-reforms
- However, reforms have been detrimental to
electrification of the poor especially in the
rural areas since rural electrification was not
given enough attention by the profit-oriented
companies in many developing countries (e.g.
Asia, Africa, Latin America and Caribbean) - (Karekezi and Sihag, 2004)
-
continued.
17Impacts of Electricity Reforms in Improving
Access to Poor
- In fact there are examples of even drop of
electrification levels for poor in India
(Karnataka, Himachal Pradesh and Orissa, the
states the study was conducted) and Kenya as a
result of disconnecting mass scale, poor illegal
consumers. Electrification levels have got
stagnated in Mali and in El Salvador. - Kenya provides examples of the partly privatized
utility confiscated funds meant for rural
electrification and used the funds to cover
operating costs. By this the utility confined its
attention to its urban relatively rich
consumers. -
continued...
18Impacts of Electricity Reforms in Improving
Access to Poor
- Improvements in the level of electrification for
poor are achieved only in countries where the
government paid special attention to rural
electrification outside the market logic -
19Status of Grid-connected Electrification in Sri
Lanka
- By the end of 2003
- National electrification level (grid connected)
67.9
- By 2002
- National electrification level 60
- Average rural electrification level 47
- District variation of the level of
electrification 20 (in some districts of the
North) 92 (in Colombo)
20How Affordable is Electricity for Poor After
Reforms?
21How Affordable is Electricity for Poor After
Reforms?
- Reduction in bulk electricity prices can be
expected with reforms..
-
- - In Argentina price for large consumers fell
significantly (by 71).
-
- (However California provides the opposite side
of the story where whole sale prices went up from
5 to 52 to 140 cents/unit during the power crisis
generated as a result of reforms)
-
continued
22How Affordable is Electricity for Poor After
Reforms?
- The general trend in almost all the countries is
the increase of electricity prices for the
domestic sector and especially for the poor
consumers. -
- e.g. Argentina, Kenya, Uganda, India, Indonesia,
Mali, Philippines, Thailand, Brazil, Peru, El
Salvador and California
-
- Vietnam (prices for the poor stayed unchanged)
-
continued
23How Affordable is Electricity for Poor After
Reforms?
-
- There can be various reasons for prices hikes.
However the fact that these studies were done at
different time periods and especially the fact
that reforms nowhere has brought prices down
suggests that - rather than competition among
companies bringing down prices the possibility is
for the removal of subsidies to push prices up
-
continued
24How Affordable is Electricity for Poor After
Reforms?
- Sudden or gradual removal of cross-subsidies stay
as a main reason for the increase in electricity
prices for the poor.
25a brief visit on some other aspects
- Motivations for reforms
- Industry in real markets
- The independent regulator
26Motivations for reforms
- Donor conditionality
- Has played a main role in almost all the
developing countries
- Poor financial performance/financial crisis of
the sector
- e.g. Argentina, Ghana, India, Indonesia,
Senegal, Mali, Philippines, California, etc.
-
continued
27Motivations for reforms
- Theoritical attraction for competition
- Even with the availability of both positive and
negative experiences related to market-based
reforms, theoretical attraction to competition
(to make the sector highly efficient and to bring
down prices) stays as a major motivating factor.
- As a part of national agenda
- South Africa and China are rare examples
28Reform related corruption Industry in real
markets
- Behavior of the sector in real markets is
different that from the behavior under textbook
conditions
29Reform related corruption Industry in real
markets
- Market power is having the ability of raising
prices and elbow out competition.
- Market power could be exercised even by small
power generators, due to the peculiar
characteristics of electricity namely that
- - electricity cannot be stored
- - new plants need time for construction (hence
- entry into the market is not immediate), and
- - transmission of electricity is constrained by
- available transmission capacity.
30Enron story from India
- In 1992 Maharashtra state entered into an MoU
with US muilinational Enron to set up a LNG plant
of 2000-2400MW. GE and Bechtel also joined Enron
to set up Dabhol Power Company (DPC). A PPA was
signed in 1993 for the project designed in 2
phases, 1st 695MW, 2nd 1320MW (against the
reservations of World Bank and CEA). PPA was a
secret for 15 months. In 1995 government changed
and the cabinet decided to scrap the project.
Construction stopped. But under the pressure from
different channels, including international
agencies, negotiations re-started, Enron invited
back and a new PPA was signed. This was worse
than the earlier one with higher costs. MSEB
could not make timely payments. MSEB later
cancelled the PPA with DPC on the issue of
mis-declaration of plant characteristics by DPC
and the plant was shut down. In December 2001
Enron in the US collapsed. Even by 2004 the plant
was not generating any power.
31Exercise of market-power in Philippines
- Manila Electricity Company (meralco) breached
the contact with the state-owned NPC and buys
power at a much higher rate from its IPPS (IPP
rate is P4.21/kWh compared to NPCs P2.46/kWh).
This is charged from consumers. Now the said
settlement be approved the cost of Meralcos
un-brought power from NPC amounting to P 20
billion would be paid for by the consumers just
the same, even when that same un-bought power was
already paid for by the consumers through the
PPA. In the end it is the consumers again that
are penalized for the offense of a business
empire that seems to have the favor of the
current administration, even to the detriment of
the people.
32Californian power crisis
- IPPs created artificial generation scarcity
resulting hiking up of peak power prices.
Generation capacity was withheld by some
companies to create artificial shortages. Using
monopoly (market) power, the generators exploited
the consumers. It was reported that the designers
of the ISO software (controlling market
operations) had leaked some design limitations to
generators, who used it to their advantage.
33Non-payment issues in Orissa, India
- According to the state government appointed
Kanungo committee in 2001, private distribution
companies did not pay GRIDCO in time, the cost of
generation went up and GRIDCO debt burden went
up. AES, which took over distribution of the
Central Zone behaved in a high handed fashion and
ultimately left in August 2001.
34Independent regulation
- Independent regulation is expected to play a
decisive role in electricity reforms
- Questions are raised about the adequacy of
resources and infrastructure the developing
countries are having for a successfully
operational independent regulator - Regulators are also criticized for its narrow
approach used in regulation with strict
separation of economic decisions with
environmental and other socially and nationally
important decisions. Training of regulators by
international consultants is said to promote this
narrow approach.
35Sri Lankan Regulatory Commission
- The Commission shall consists of five members
appointed by the Minister (part II, 3). The
members of the Commission shall be persons with
ability and integrity and have shown capacity in
addressing problems relating to engineering, law,
economics, business management, accountancy or
administration (part II, 5) - Public Utilities Commission of Sri Lanka Act,
No.35 of 2002
36Sri Lankan Regulatory Commission
- However according to the Electricity Reform Act,
No.28 of 2002, which defines in particular the
electricity related regulation of the Public
Utilities Commission - The functions of the Commission shall be to ..
- a. To advice the government , on all matters
concerning the generation, transmission,
distribution, supply and use of electricity in
Sri Lanka .. - l. To undertake all incidental or ancillary
measures that it considers appropriate for the
effective discharge of its functions
37Independent regulation
- regulation
- Electrification program was aggressively
monitored by the National Electricity Regulator
(NER) in South Africa
- - regulation
- The Supreme Court of Philippines recently
declared illegal the Manila Electric Companys
(Meralco) provisional tariff increase in January
2004, ruling that the Energy Regulation
Commission (ERC) committed grave abuse of
discretion in granting the increase. - In California poor regulation resulted in
private players creating artificial generation
scarcity and hiking up peak power prices.
38Strategies for Defending the Interests of
Marginalized
- Improving access and making electricity
affordable to poor
- Off-grid electrification
- and sustainable energy
- technologies
39Improving access and making electricity
affordable to poor
-
- Majority of the world population, poor, are more
or less seriously affected by market-driven
reforms . Additional measures through state
intervention is needed to look after the
interests of them.
40Improving access and making electricity
affordable to poor
- Committed rural electrification targets
- Special units to look after the interests of the
poor
- Special funds and programs to look after the
needs of the poor
- New laws safeguarding better service
- Subsidization
41Committed rural electrification targets
- India Power to all by 2012
- Zimbabwe Performance Improvement Program
included explicit rural and urban electrification
targets that the utility was obliged to meet.
- Philippines Government has set electrification
of all villages as a target for 2006.
- Brazil Luz no Campo is a program to extend
grid to a million new rural customers.
42Special units to look after the interests of the
poor
- Uganda Is in the process of creating an
Electrification Board to promote rural
electrification and expand the use of mini-grid
and PV systems. - Senegal and Mali Rural electrification agency
has been established recently.
- Vietnam A special office for rural
electrification was set up in 1995 parallel to
the formation of the company Electricity of
Vietnam.
43Special funds and programs to look after the
needs of the poor
- India Rural Electrification Supply Technology
Mission was launched by the Prime Minister in
2002. Approaches for rural electrification are
on-grid, off-grid and hybrid systems. - South Africa Special measures were taken for
rural electrification from 1994 to 2001.
- Uganda Government has recently introduced a
Rural Electrification Strategy and Plan for the
2001-2010, period.
- Zimbabwe Rural electrification fund was
established
- Thailand Thailand is having a 98.5
electrification level by 2003 (In early 1970s the
level was only 7). This was a result of an
Accelerated Rural Electrification (ARE) program
initiated in1974. - China In 2001, government allocates funds for
the National Township Electrification Program to
provide electricity to more than 1000 townships
using hybrid systems, small hydro, solar and
wind.
44New laws safeguarding better service
- Brazil
- - In 1996, an additional law made
concessionaires responsible of the cost of
providing services to new customers.
- - In the same year law that created ANEEL also
required that half of the RGR financing for rural
electrification be directed to the regions with
lowest electrification levels and half be
allocated to programs for rural electrification,
energy efficiency, and electrical power for
low-income users. - - In 1997, legislation stipulated that national
energy policies must aim to identify the most
suitable solutions to supply electricity to the
different regions. - - A law passed in 2002 which tightens universal
service obligations on concessionaires, defined
low income consumers, established an energy
development account to promote universal access
and use of renewables and provides new consumers
a partial connection cost subsidy.
45Subsidization
- India A massive central government subsidy to
facilitate power to all by 2012 plan
- South Africa In 2002 a poverty tariff was
introduced to provide with consumers in 20-50 kWh
category, electricity free of charge.
- Brazil provides new consumers a partial
connection cost subsidy.
- China Village renewable energy systems receive
subsidies.
46Off-grid electrification
-
- Electricity Act 2003, India
-
- For rural areas stand-alone systems for
generation and distribution are allowed.
47Off-grid electrification IN Sri Lanka
- Under the Electricity Reform Act, No.28 of 2002
- Illegal
48Off-grid electrification
- Electricity Reform Act, No.28 of 2002
- Chapter III, Part I, 12 (3), (4)
- A person shall not be granted both a transmission
license and
- (a) a generation license or
- (b) a distribution license
- A person shall not be granted both a generation
license and a distribution license
49Sustainable Energy Technologies
Demand for sustainable energy
Sustainable energy technology development
Price fall
To have this cycle in operation there is a need
for external inputs
50Sustainable Energy Technologies
- Examples for external inputs that are generally
not facilitated by market driven reforms (e.g.
Arizona, Denmark)
-
- Supply-side
- Subsidizing R D
- Investment in generation equipment
Demand-side - Fee-in laws guaranteeing minimum
prices - Renewable portfolio standards certain
portion of energy comes from renewables
51 to be continued..
52(No Transcript)
53(No Transcript)
54(No Transcript)