Slide 0 - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Slide 0

Description:

CO2 emissions & Electricity Sector in Mauritius. Bagasse co-generation & co-firing ... Roadmap for the Mauritius Sugarcane Industry for the 21st Century ... – PowerPoint PPT presentation

Number of Views:180
Avg rating:3.0/5.0
Slides: 25
Provided by: UND6
Category:
Tags: mauritius

less

Transcript and Presenter's Notes

Title: Slide 0


1
Bio-energy in Mauritius lessons learned
Sanju Deenapanray CDM National Project Coordinato
r, Mauritius
prakash.deenapanray_at_undp.org
Bio-carbon in Eastern Southern Africa, Addis
Ababa, Ethiopia (24 April 2009)
2
Overview
  • CO2 emissions Electricity Sector in Mauritius
  • Bagasse co-generation co-firing
  • Potential for CDM in Africa

3
Dependence on Fossil Fuel
4
CO2 Emissions
Per capita CO2 emission 2.7 tonnes (2007)
5
Sectoral CO2 Emissions (1995 - 2007)
Electricity Transport accounted for 83 of
total emissions in 2007
6
Electricity Supply
Demand growing at 5-6 per annum
over the past decade
78 of electricity produced from fossil fuels
7
Role of Independent Power Producers
  • In 2007, IPPs generated around 66.5 of total
    thermal electricity in Mauritius (1461.5 GWh out
    of 2464.6 GWh)
  • Internal consumption of IPPs was 234.8 GWh
  • Exported 1226.7 GWh to the gird (i.e. 56 of all
    grid electricity) and CEB generated 972.3 GWh (or
    44)
  • Thermal electricity is produced in 3 ways by
    IPPs
  • 1. Bagasse only (continuous power)
  • 2. Bagasse/Coal (firm power)
  • 3. Coal only (firm power)

8
Overview
  • CO2 emissions Electricity Sector in Mauritius
  • Bagasse co-generation co-firing
  • Potential for CDM in Africa

9
Cogeneration the concept
10
(No Transcript)
11
(No Transcript)
12
Key Enabling Factors
  • Economic fiscal incentives
  • Power Purchase Agreements (attractive sale price
    of electricity for firm power)
  • Research Development (technology transfer
    bio-engineering etc )
  • Equity Participation (of small in cogeneration
    plants through the State Investment Trust up to
    25)

13
Increase in Efficiency in Cogeneration
14
Increase in Generation of Firm Power
15
Reduction in CO2 Emissions
  • Grid Emission Factor, EFgrid,2007 1.1773
    tCO2/MWh
  • In 2007, a total of 346.8 GWh generated from
    bagasse (_at_ 242.5 kWh/TB)
  • Avoided CO2 emissions 408,300 tonnes (2007)
  • Considering an average efficiency 374.6 kWh/TB
    (_at_82 bars)
  • Potential for avoided CO2 emissions 630,705
    tonnes

16
How dirty is the grid?
EFgrid,CM,y EFgrid,OM,y X wOM EFgrid,BM,y X
wBM
Generation-weighted average CO2 emissions net of
electricity generated (excludes low-cost, must
run plants CDM projects)
Generation-weighted average CO2 emissions net of
electricity generated of either 5 most recently
built plants or 20 of last power generated
(whichever is larger)
wOM wBM 50 (1st crediting period)
For Mauritius (2007) EFgrid,OM,y 1.0886 tCO2 /
MWh EFgrid,BM,y 1.2659 tCO2 / MWh
EFgrid,CM,y 1.1773 tCO2 / MWh
?
VERY DIRTY GRID
17
Overview
  • CO2 emissions Electricity Sector in Mauritius
  • Bagasse co-generation co-firing
  • Potential for CDM in Africa

18
Bagasse Cogeneration in Africa
  • 10,000 GWh/yr (or 10 TWh/yr) in 2005 90 million
    tonnes of cane
  • In 2005, total demand of electricity in Africa
    was 533 TWh
  • Potential to generate 2 of electricity demand
    from bagasse
  • Potential could be much larger considering
    availability of other renewable biomass in Africa
    (e.g. crop residues, woody biomass - quantity?)
  • Biomass can also be used to provide only thermal
    energy (process steam and heat) for industrial
    processes

19
Example - Mozambique
  • 596,271 TB produced in 2007
  • Assuming a conversion efficiency of 374.6 kWh/TB
  • EFgrid,2005 0.045 MWh/tCO2

18
20
Clean Development Mechanism
  • Several bagasse (biomass) cogeneration projects
    have successfully generated CERs
  • Approved baseline monitoring methodologies
    exist. For example
  • ACM0006 Consolidated methodology for electricity
    generation from biomass residues Version 8
  • Several Small-Scale methodologies in Categories
    I.A, I.C and I.D

 
19
21
ACM0006 Consolidated methodology for
electricity generation from biomass residues
Version 8
22
ACM0006 Consolidated methodology for
electricity generation from biomass residues
Version 8
23
Additionality
Reductions in emissions must be additional to
any that would occur in the absence of the
project activity
  • Most registered CDM projects (biomass
    cogeneration / thermal energy production) have
    employed Barrier Analysis to justify
    additionality. Some barriers are
  • Investment barrier (high upfront CapEx)
  • Technological barrier
  • Barrier due to prevailing practice (cultural
    barrier)
  • Institutional barrier (e.g. access to grid,
    feed-in tariff)
  • Price risk of biomass residue
  • Biomass collection and storage barriers

24
End
Sanju Deenapanray CDM National Project Coordinato
r, UNDP prakash.deenapanray_at_undp.org Tel 230 2
08 2416
Fax 230 208 4871
Write a Comment
User Comments (0)
About PowerShow.com