NEPAL MULTIMODAL TRANSIT AND TRADE FACILITATION PROJECT CASE STUDY - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

NEPAL MULTIMODAL TRANSIT AND TRADE FACILITATION PROJECT CASE STUDY

Description:

Nepal's remote and landlocked geographical location, sandwiched between China ... Without a negotiated Nepal-India Rail Service Agreement, leasing out of the ICD ... – PowerPoint PPT presentation

Number of Views:259
Avg rating:3.0/5.0
Slides: 15
Provided by: wbiu
Category:

less

Transcript and Presenter's Notes

Title: NEPAL MULTIMODAL TRANSIT AND TRADE FACILITATION PROJECT CASE STUDY


1
NEPAL MULTIMODAL TRANSIT AND TRADE FACILITATION
PROJECTCASE STUDY
  •  FABIO GALLI
  • SASEI
  • TRANSPORT FORUM 2005

2
PROJECT GENESIS
  • Nepals remote and landlocked geographical
    location, sandwiched between China and India, has
    been a major cause limiting its economic
    development.
  •  

3
(No Transcript)
4
PROJECT GENESIS
  • Poor transport infrastructure cumbersome
    customs procedures have caused
  • Very high transport costs
  • Substantial pilferage loss
  • Unreliable and slow movement of import/export
    goods
  • Trade diversion and smuggling

5
PROJECT GENESIS
  • To improve trade competitiveness, Nepal
  • negotiated an improved India-Nepal Trade
    Transit Treaty, and
  • planned a set of integrated transport
    infrastructure improvements (road, customs and
    dry port facilities) on its side of the
    Nepal-India transit corridor.

6
PROJECT OBJECTIVES
  • Project Development Objectives (PDO)
  • Reduce import and export transport costs
  • Streamline transit and trade procedures

7
PROJECT COMPONENTS
  • Construction of new road/rail Inland Container
    Depot (ICD) near Birgunj
  • Reconstruction of existing road only ICD at
    Biratnagar and Bhairahawa
  • Construction of railway spur from Raxaul (India)
    to Birgunj (Nepal)

8
PROJECT COMPONENTS
  • TA for trade facilitation
  • Installation of Automated Systems for Customs
    Data (ASYCUDA) at Birgunj, Biratnagar
    Bhairahawa
  • Installation of Advanced Cargo Information System
    (ACIS) at Birgunj, Biratnagar Bhairahawa

9
PROJECT COST DURATION
  •  
  • Total project cost estimated at US28.5 million
    (actual cost US21.4 million)
  • Implementation period was supposed to be about 4
    (four) years starting from early 1998 to end-2001
    (actual time 5.5 years)

10
EXPECTED PROJECT BENEFITS
  • Lower transport costs on the 1000 km transport
    corridors between Nepal and Kolkatta
  • More efficient customs procedures
  • Connection to Indian Railways rail network
  • Less pilferage damage to cargo
  • More reliable secure carriage of goods
  • Private sector development through leasing out of
    three facilities
  • Safer more environmentally sustainable carriage
    of goods

11
WHAT WAS ACHIEVED AT PROJECT CLOSURE
  • Reconstruction/construction of the ICDs
    ancillary infrastructure to a reasonable
    standard, on time below budget
  • Introduction of Single Administrative Document
    (SAD) ASYCUDA
  • Rolling out of a scaled down version of ACIS
  • Leasing out of the improved ICDs at Bhairahawa
    Biratnagar to the private sector
  • Streamlining of some of the transit procedures
    (i.e., intro of one time lock for containers)

12
WHAT WAS NOT ACHIEVED AT PROJECT CLOSURE
  • Leasing out of the ICD at Birgunj to the private
    sector was not completed
  • The Railway, Carriage of Goods by Road,
    Multimodal Transport and Marine Insurance Acts
    were not enacted

13
WHY WERE THE PROJECT PDOs NOT FULLY ACHIEVED
  • It took over 3 years to negotiate a Nepal-India
    Rail Service Agreement to enable train services
    to operate into the ICD at Birgunj
  • Without a negotiated Nepal-India Rail Service
    Agreement, leasing out of the ICD at Birgunj
    could not be completed by end of project
  • Delays in finalizing the Nepal-India Rail Service
    Agreement resulted in a 3.5 years gap between the
    completion of the ICD at Birgunj and its actual
    operation

14
LESSONS LEARNED
  • Regional transit corridor projects require solid
    upfront and continued commitment by
    countries/parties involved
  • There needs to be a high degree of symmetry in
    the perceived benefits by all countries/parties
    involved in a regional transit corridor project
  • Better sequencing of physical (civil works) with
    non-civil works components is essential to avoid
    initial underutilization of assets
Write a Comment
User Comments (0)
About PowerShow.com