Title: Project Managers Benefits
1 Project Managers Benefits
Project Coordination with ETAT
- Programming Summary Report w/ Class of Action
Determination
- Established working relationship w/ ETAT
2 Project Managers Benefits
Project Coordination with ETAT
- Commitments/Requests to resolve issues identified
- Results in customized Scope of Services
3 Project Managers Role
Project Coordination with ETAT
- Scope development
- Coordinate w/ District ETDM Coordinator
- Review Commitments/Requests from ETAT review
4 Project Managers Role
Project Coordination with ETAT
- Coordinate w/ District Permit Coordinator
- Continue coordination w/ ETAT members
5Project Coordination with ETAT
- Continued Throughout PDE
- Workshops to Address Specific Issues
- Field Reviews
- Gain information/Assist in Resolution of Issues
6Annual ETAT Workshops
- Present Upcoming Projects Prior to Submittal into
ETDM Tool - ETAT Members have Background of Project Prior to
Submittal - Promotes Consistency in Reviews
7Annual ETAT Workshops
- Current PDE Projects Update
- Promotes Awareness of
Project Schedule - Identification of any Additional
Issues Resulting from PDE Analyses or Subsequent
Phases
8Annual ETAT Workshops
- Identification of issues Associated w/ the ETDM
Process (DOT or Agency) - Forum for Discussion or Resolution
9Coordination with ETAT PDE
- Pond Apple Slough Wetland
- Project specific Agency Workshop prior to document
- Issues and acceptable mitigation methods agreed
upon
10Coordination with ETAT PDE
- Reduced scope for Wetland Report, Cultural
Resources Listed Species
- Field review for Jurisdictional Wetlands
11Coordination with ETAT PDE
- Flagler Bridge Replacement
- Field reviews with NMFS SHPO
- Project specific Agency Summit Meeting
- Discussion of mitigation options
- Cultural Resource Committee
12Coordination with ETAT PDE
- Project specific Agency Workshop
- Review and comment on the Draft PEIS
- Wetlands, EFH,Air Quality, Habitat, USCG Permits
13Develop Pond Alternatives Early
Pond Siting and Permit Processes
- Pond Alternatives Coordination Meeting w/ ETAT
Members
- Identify Preferred Pond Sites
- Prepare Pond Siting Report
- Prepare Permit Application if Design Phase Follows
14(No Transcript)
15LDCA
Permit Process
- Continued Coordination w/ Permitting Agencies
16Design Phase
- Coordination of Changes from the Approved PDE w/
the ETAT
- Pond Siting Coordination if not Completed in PDE
- Continued Coordination of Environmental Issues
17Coordination with ETAT - Design
- New pond sites identified
- Field reviews with ACOE USFWS
- Concurrence for no adverse effect to listed
species
- Acceptable construction methods agreed upon
18Coordination with ETAT - Design
- Design change increases wetland impact
- Suggestions for acceptable mitigation methods
agreed upon
19Coordination with ETAT - Design
20Construction Phase
- Unexpected Encounters (i.e. bats, birds, bodies,
tanks)
- Contractor change proposals
- Coordination w/ ETDM Coordinator and
Environmental Specialist
21Coordination with ETAT - Construction
- SR A1A Little Mud Creek Bridge Emergency Repairs
- Utilized ETAT members (USFWS, NMFS, USACE)
- Field review w/ identification of required
approval actions
22Coordination with ETAT - Construction
- SR A1A Little Mud Creek Bridge Permanent Repairs
- Contractor change proposals
- Articulated block instead of rubble rip-rap
- Time Money and Constructability