Title: RiskInformed InService Inspection RIISI Using RISK
1Risk-Informed In-ServiceInspection
(RI-ISI)Using _at_RISK
2RI-ISI at Turkey Point
- Turkey Points application of RI-ISI is limited
to Class 1 piping inside containment.
- The purpose of in-service inspection is to
identify conditions, such as flaw indications,
that are precursors to leaks and ruptures which
violate pressure boundary integrity principles. - In-service inspection (ISI) activities include
ultrasonic testing, surface testing, and liquid
penetrant testing.
3Objectives
- More Effective and Efficient Use of _at_Risk to
Streamlize the Analysis Work
- Prioritize Turkey Points ISI Activities by Risk
- Decrease cost of outage inspections, and
- Decrease personnel radiation exposure during
outage inspections, while
- increasing or maintaining personnel safety
- increasing or maintaining unit reliability
4Risk-Informed ISIProcess Overview
Expert Panel Categorization
Consequence Evaluation
Element/ NDE Selection
Scope and Segment Definition
Risk- Evaluation
Implement Program
Structural Element Failure Probability Assessmen
t
Feedback Loop
_at_RISK
5Turkey Point PRA LOCA Events and Nominal Pipe
Sizes
- Small-Small LOCA 3/8
- Small LOCA 2
- Medium LOCA 6
- Large LOCA 13.5
- Any piping with a nominal diameter less than or
equal to 3/8 is assumed not to result in a LOCA
event, which could lead to core damage.
6Failure ProbabilityAssessment Process
PLANT INFORMATION (LAYOUT, MATERIALS, OPERATING
CONDITIONS,
PLANT OPERATING EXPERIENCE)
IDENTIFICATION OF POTENTIAL FAILURE MODES AND CA
USES
INDUSTRY EXPERIENCE
ENGINEERING TEAM
SRRA TOOL
- Engineering Team
- ISI/NDE Engineering
- Materials Engineering
- Design Stress Engineering
- (Engineering Mechanics)
- -Plant System Engineer
ESTIMATED LEAK AND BREAK PROBABILITIES
7Piping Segment Definition
- Segment
- Section of pipe for which a failure at any point
has the same consequences
- Over 200 individual segments for each unit
8Piping Failure Probability
- SRRA Code used to predict piping failure
probability
- Factors used in SRRA Piping Failure Probability
Calculation
- Pipe Segment Dimensions
- Material Stresses
- Pressure, Temperature
9Consequences Evaluation
- Calculated using the Turkey Point Probabilistic
Safety Assessment (PSA).
- Postulated different size breaks in each
segment.
- Calculated Conditional Core Damage Probability
(CCDP) and Conditional Large Early Release
Probability (CLERP) for each segment and break
size.
10Risk Evaluation
- SRRA Code used to predict piping failure
frequency.
- Calculated Conditional Core Damage Probability
(CCDP) and Conditional Large Early Release
Probability (CLERP) for each segment and break
size using the PTN PSA model. - Multiplied the segment piping failure frequencies
from SRRA by their CCDPs and CLERPs to obtain the
CDFs and LERFs for each segment.
- Calculated risk importance measures for each
segment Using _at_RISK .
- Assigned a preliminary risk category to each
segment based on the RRW.
11Expert Panel
- Convened a panel of experts from ISI/NDE, Plant
Engineering, Risk Assessment, Operations,
Maintenance, etc.
- Provided each Expert Panel member with all of the
risk-related and other information calculated
and/or collected for each pipe segment.
- Reviewed, discussed, and eventually assigned a
final risk category to each pipe segment.
- Documented the basis of the determination.
12Results
- Weld Inspection Reduction 84
- Radiation Dose Reduction 20 man-rem
- Role of _at_RISK Methodology approved by the NRC
requires doing Monte-Carlo Simulation and use
mean values for the ranking of each segment
- A sensitivity study to compare Point Estimate and
Monte-Carlo Generated Mean provides useful
insights for the sensitivity of changes in the
input parameters - A function RiskMean() used saved many
hours of manual work
13Other Benefits
- Avoidance of potential personnel injury by
reduction of
- Scaffold Construction
- Asbestos Removal
- Insulation Removal
- Weld Grinding and Buffing
14Expert Panel
- Scope limited to changes in program new
segments, modified segments, and segments whose
risk ranking changed from Low to High or Medium
to High. - Risk ranking change due to changes in SRRA
analysis of pipe segment failure frequency,
changes in consequence assumptions, and/or
changes in PTN PSA model. - Expert Panel members will be provided with all of
the risk-related and other information calculated
or collected for the relevant pipe segments.
- Expert Panel will review, discuss, and eventually
assign a final risk category to each pipe
segment.