SEQUOIA Overview - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

SEQUOIA Overview

Description:

Jib crane. Sample. equipment. Equipment. shelf. Sample. Stick ... Jib crane to lift sample environment equipment, Fermi choppers. Sliding door for access. ... – PowerPoint PPT presentation

Number of Views:125
Avg rating:3.0/5.0
Slides: 25
Provided by: Ren984
Category:

less

Transcript and Presenter's Notes

Title: SEQUOIA Overview


1
  • SEQUOIA Overview
  • Garrett Granroth (Instrument Scientist)
  • David Vandergriff (Lead Engineer)
  • ARCS/SEQUOIA IDT meeting
  • March 20, 2005

2
Outline
  • Overview
  • Progress
  • Procurement Status
  • Installation Status
  • Specific items
  • T0 chopper
  • Sample Area
  • Magnetic shielding issues
  • Summary

3
SEQUOIA Overview
Beam Stop
Core Vessel insert
Shutter insert
Front End shielding
Beamline shielding
Get Lost Tube
Detectors
Fermi Chopper
Detector Vessel
To Chopper
Guide
Poured In-Place Shielding
Sample Vessel
4
Instrument Parameters
  • minimum Dw/Ei lt 1.2
  • Ei 10 2000 meV
  • Lengths
  • Moderator to Fermi chopper 18.0 m
  • Fermi Chopper to sample 2 m
  • Sample to Detector 5.5 m
  • 43m2 of detectors covering 1.2 Sr
  • Span -30o -3o, 3o 60o horizontal, -30o
    -3o, 3o 30o vertical.
  • 138,000 pixels

5
Instrument Performance
6
Location
SEQUOIA
7
SEQUOIA and ARCS
Beam Stop
Detector Array
Get-Lost Tube
Sample Vessel
Detector Vessel
5.5 m
Fermi Choppers
2 m
ARCS Beamstop
T0 Chopper
8 m
Shutter Insert
10 m
CVI
8
System Overview
  • Beamline 17/18 Pit Area

9
SEQUOIA Dates
  • Conceptual Design Review March 04
  • Shutter Insert Guide on Order with CILAS April
    04
  • Critical Decision - 1 (Alternative Selection and
    Cost Range) approved by DOE (CD-1) April 04
  • Preliminary Design Review May 04
  • Core Vessel Insert Installed July 04
  • Guide Design Review August 04
  • Post Doc Matthew Stone arrives at HFIR August
    04
  • IDT meeting October 04
  • CD-2A and CD-3A (long lead procurements) approved
    October 04
  • Shutter Inset Guide Installed December 04
  • Engineer Mark Overbay joins the SEQUOIA team to
    work on Choppers January 05
  • Detector Vessel and Sample Vessel Design Review
    February 05
  • Shutter installed February 05
  • IPR and CD-3 Review (all procurements) March 05
  • Guide vendor selected March 05
  • Joint ARCS /SEQUOIA IDT meeting March 05
  • Early procurement permitted because these
    items are time critical

10
Instrument Procurement Progress
Legend Awarded Vendor chosen Out for bid In next
6 months BOA component
Beam Stop
Front End shielding
Beamline shielding
Get Lost Tube
Detectors
Fermi Chopper
Detector Vessel
To Chopper
Guide
Poured in Place shielding
Sample Vessel
11
In-Monolith Component Installation
  • Shutter Insert(Feb 2005)
  • Core Vessel Insert (Aug 2004)
  • Shutter Insert guide (Nov 2004)

12
Core Vessel Insert Installed
Aug. 2004
Apr. 2004
Beamline 17
13
Shutter Guide and Insert Installation
14
T0 Chopper
  • Vertical axis narrow band width design.
  • Background reduction
  • Max Ei 2 eV
  • Up to 180 Hz operation.
  • Constant 31 cm Inconel X-750 to block beam.
  • Ultimate 160 ksi.
  • Yield 100 ksi.
  • Eliminates need for bandwidth chopper.
  • Working closely with ARCS team
  • Simplifies shielding design
  • Approximate spin up times
  • 5 min per increment of 30 Hz
  • Magnetic Bearings reduce maintenance frequency
  • Initial rotor analysis completed
  • Specification under preparation.

15
Crystal alignment with T0 chopper
  • 4 steps in phase to match white beam
  • operate at 31Hz to sweep profile 1/s

16
Sample Area Design
  • Vacuum Isolation during sample change out
  • Standard Flange with Rotary options
  • 1 Ton max weight for sample environment
    equipment
  • Non magnetic material
  • Ease of access for
  • Sample Change
  • Fermi Chopper Change
  • Cryogen Fills
  • Shielding for
  • Personnel protection
  • Background reduction
  • Reduction of stray magnetic fields

17
Sample area
Top access port
Sliding top cover
Quench vent
Magnetic shielding
Jib crane
Equipment shelf
Enclosure door
Sample Stick (oxford Magnet sized)
Sample equipment
18
Sample Area looking up
19
Sample Area
  • Enclosure dimensions
  • 108 w x 120 d
  • 96 inside height
  • 72 x 108 shelf
  • Jib crane to lift sample environment equipment,
    Fermi choppers.
  • Sliding door for access.
  • Sliding top access port for top loading and
    long sample sticks.
  • Mezzanine access on the ARCS side.
  • Equipment lift to raise and lower sample
    environment equipment.
  • Considerable coordination with the ARCS team!

20
Magnetic field Policy
  • General principal
  • Dont generate stray fields that mess with other
    beamlines
  • Multiple Approaches
  • Meet low limit (50 mGauss proposed limit)
  • Negotiate with affected neighbors for a different
    limit
  • Spin Echo is affected neighbor. They have
    calculations to show they need 50 mGauss.
  • We have calculations that show we cant meet 50
    mGauss with a15 T unshielded magnet.
  • Management decides on an experiment by experiment
    basis if you can temporarily violate above points
  • Self shielding compensated magnets are under
    development

21
Magnetic shielding - top
Incident beam
22
Magnetic shielding Front
23
Cut from closest interference
  • Plate on ARCS side makes matters worse
  • Rounded edges dont help in far field
  • 5cm is 200 layers of electric steel
  • Need IDTs opinion on the need for fields

24
Summary
  • Progressing on SEQUOIA
  • Guide vendor selected
  • Detector Vessel and Sample Vessel out for bid
  • Shielding, Fermi chopper, and T0 chopper to go
    out for bid in the next 6 months
  • In monolith components installed
  • A workable sample area has been proposed
  • T0 chopper allows crystal alignment
  • Magnetic shielding We need your input
Write a Comment
User Comments (0)
About PowerShow.com