Title: Transition from SKADS to PrepSKA


1
Transition from SKADS to PrepSKA
  • Richard Schilizzi
  • Lisbon, 3 October 2008

2
PrepSKA deliverables
  • Produce a deployment plan for the full SKA and a
    detailed costed system design for Phase 1
  • Integrate all of the activities, reports, and
    outputs of the various working groups to form an
    SKA implementation plan including a build plan
  • proposal for construction funding in 2012

3
PrepSKA Work Program
  • WP1 PrepSKA management
  • WP2 Costed telescope design
  • WP3 Further site characterization in Australia
    and Southern Africa
  • WP4 Governance
  • WP5 Procurement and involvement of industry
  • WP6 Options for funding
  • WP7 Impact on broad government priorities

4
PrepSKA
5
SKA timeline
SKA-midlow Complete
Site Select
Reference Design selected
SKA Pathfinders Complete
Phase 1 complete
Preliminary SKA specs
External Engineering Review of design
Sites short-listed
Pathfinder science
Full science operations SKA midlow
Early Science SKA midlow
06 08 10 12 14 16 18 20
22 24
System Design
SKA mid low construction and commissioning
Concept Design
Detailed Design/Phase 1 construction and
commissioning
SKA-high Construction
Design Studies /Pathfinder Suite Construction
System design SKA-hi
Concept design for SKA-high
6
WP2 deliverables(Peter Dewdney Guiding
Principles, Activities and Targets for WP2)
  • Technology selection
  • System Design
  • including operational construction tradeoffs
  • Science Performance vs Reference Science Mission
  • Total cost estimate for Baseline Design (incl.
    contingency)
  • Risk assessment
  • Design and deployment plan
  • Top-level build schedule
  • Upgrade paths

7
National PrepSKA SKADS TDP LOFAR ASKAP KAT7
ATA EVLA MWA eMERLIN eEVN Path2SKA
8
Approach
  • Focus WP2 Description of Work in a different way
  • Move from 40 technology development tasks,
    including an ill-defined IVS to assembly and
    verification of large SKA sub-systems
  • identify and fill gaps
  • Note Need an integrated systems approach at
    sub-unit level, eg
  • Feed dish design LNA feed design
  • Dish Verification Program
  • PAF Verification Program
  • AA Verification Program
  • Signal transport Verification Program
  • ..

9
Original WP2 technology matrix
10
Dish Verification Program
11
WP2 approach
  • Required parameter space can be covered with a
    small no. of models
  • Contributing institutions contribute designs to
    several models
  • Verification Programs will need to include a
    build and test phase, on the way to deriving the
    cost by 2012Q1 (end of PrepSKA)
  • VPs are self-evaluating
  • SKA Design Studies and Pathfinders provide the
    RD basis for the VPs
  • Need to target those aspects that map into the
    SKA
  • Documentation essential
  • Effectively evaluate the feasibility of
    implementations outlined in Memo 100

12
Representative implementations Phase 1
13
Representative implementations Phase 2
14
SPDO in the PrepSKA era
15
SPDO Engineering Team
  • Project Engineer Peter Dewdney
  • System Engineer Kobus Cloete
  • Domain Specialist Receptors Neil Roddis
  • Domain Specialist Signal Transport Roshene McCool
  • Domain Specialist Computing Duncan Hall
  • Software
  • Domain Specialist Signal Processing advertised
  • Site Engineer Rob Millenaar
  • Project Management Officer interviews next week

16
Liaison Engineers
  • Senior engineering managers
  • Roles
  • Lead design teams for which the Lead Institution
    has assumed responsibility
  • Serve as communication person for relations
    between SPDO and Lead Institution

17
WP2 Schedule
  • SPDO staffing, familiarisation and training
    (ongoing)
  • Appoint liaison engineers (ongoing)
  • WP2 Kickoff meeting, 10-14 Nov (Deliverable 1)
  • MoAs with organisations/lead institutions
    (ongoing)
  • Review Reference Science Mission, Dec08
  • State of SKA technology
  • call for documentation (Jan 09)
  • Review by International Engineering Advisory
    Committee, Mar 09 (Deliverable 2)

18
WP2 deliverables