Oracle HR Implementation Best Practices - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

Oracle HR Implementation Best Practices

Description:

Functional Project Manager for the Oracle HRMS application at the University of ... while other Oracle applications (excluding OLM) remained on current platform ... – PowerPoint PPT presentation

Number of Views:3965
Avg rating:3.0/5.0
Slides: 49
Provided by: rick287
Category:

less

Transcript and Presenter's Notes

Title: Oracle HR Implementation Best Practices


1
Oracle HR Implementation Best Practices
  • English Room
  • August 15, 2008
  • NCOAUG Training Day
  • Drury Lane Hilton Suites
  • Oakbrook Terrace, IL

2
Mario C. Ellis
  • Director Compensation HR Systems University of
    Chicago Medical Center
  • Functional Project Manager for the Oracle HRMS
    application at the University of Chicago Medical
    Center.
  • 20 years experience, has re-engineered legacy
    business processes from mainframe technology to
    client/server relational systems

3
Overview
  • Challenge to implement Oracle HR application
  • Limited budget and resources
  • Lack of a dedicated Project Manager
  • Mandate from senior management
  • Implement a fully functioning application
  • Manager self-service
  • Compensation Workbench.
  • No customizations
  • Coming from a customized legacy system
  • Intensive paper driven processes
  • Limited consulting resources

4
Agenda/Contents
  • Background
  • Decisions Made
  • Overall Objectives
  • Challenge
  • Lessons Learned
  • Summary
  • Questions

5
University of Chicago Medical Center
  • At the forefront of medicine for more than 75
    years--delivering extraordinary care to patients
    from all parts of the world. 2nd largest medical
    center in Chicago.
  • U.S.News World Report named UCMC to the
    prestigious Honor Roll of America's Best
    Hospitals--the top 18 hospitals in the nation.

6
Oracle Applications Implemented
  • Oracle eBusiness Suite 11.5.10
  • Core HR
  • Manager Self-Service
  • Employee Self-Service
  • Compensation Workbench
  • Performance Management
  • Supply Chain
  • iExpense
  • iProcurment
  • Learning Management

7
Background
8
Background
  • The initial project began as a full install of
    the Oracle Supply Chain, Finance and Human
    Resources modules in 2001.
  • The initial project identified over 400 gaps for
    all applications, resulting in high cost
    estimates, expanded scope and delay in
    implementation.

9
Background
  • UCMC reassessed the project to reduce the scope
    and stay within budget. As a result
  • Scope reduced to implement Supply Chain
  • Scope reduced to implement limited HR and Finance
    to support Supply Chain
  • Supply Chain phase went live in June 2003,
    on-time and budget.
  • HR, Payroll and G.L. modules were to be scheduled
    for future implementation.

10
Background
  • The success of the initial project resulted in
    cost savings for materials management - however
    limited project budget remained approximately
    1 Million

11
Background
  • Concerns from initial project
  • Management was not convinced that the remaining
    Oracle applications were necessary
  • The HR department lacked the talent and expertise
    to provide key sponsorship and decision making
    for the project

12
Background
  • UCMC was still faced with the following
    challenges
  • The hospitals has more than 6,000 employees,
    with staff as the largest expense
  • Difficult to obtain accurate and timely employee
    information
  • Lack of reporting tools hinders the ability for
    management reporting
  • Disparate systems do not allow for workflow or
    integration of data
  • Inability to efficiently support
    accreditation/compliance reviews
  • Changes in employee information was time
    consuming and paper intensive

13
Background
  • Heavy reliance on Third Party Vendors to provide
    needed business functionality
  • The hospital had a need for a true HRIS
    application
  • Information maintained in multiple spread sheets,
    Access Databases, and shadow systems that were
    not integrated
  • No one source of truth for reporting
  • Legacy system was a payroll system and did not
    allow for the necessary storing and reporting of
    needed HR related data

14
Decisions Made
15
Decisions Made
  • A new VP of Human Resources was hired, who also
    hired more experienced staff
  • A fit gap analysis was conducted in June 2005
  • Validated need to implement Oracle HR (payroll
    would be a separate project)
  • Helped to structure the scope, project team,
    project methodology and deliverables based on
    internal resources and remaining project budget
  • Project approved in fall of 2005 and work began
    June of 2006

16
Overall Objectives
17
Overall Objectives
  • Implement Core HR functionality
  • Integrate with Oracle Learning Management, Supply
    Chain and Legacy Financial applications
  • Restructure work elements Job, Positions,
    Grades and Benefit Groups
  • Improve automation of Union Contracts including
    Grade Step progression

18
Overall Objectives
  • Introduce a phased rollout of Self Service
    applications for managers
  • Institute Merit Award Distribution through Oracle
    Compensation Workbench
  • Institute a Directors Incentive Plan Distribution
    through Oracle Compensation Workbench

19
Challenge
20
Challenge
  • Meet the Overall Objectives with
  • Limited IT and HR staff resources, especially
    with extensive Oracle experience
  • No dedicated Project Manager
  • Need to upgrade platform of HR applications while
    other Oracle applications (excluding OLM)
    remained on current platform
  • Budget remained at approximately 1 million

21
Expected State after Implementation
BIS/Customer Access Discover (Roll-Out at Module
Level Available)
Budgeting
EDI
Fixed Assets
iExpense
P-Cards
Agency
iSupplier
HR Self Service
Capital Budget
Balanced Scorecard
Learning Management
Payroll
iRecruitment
Accounts Payable
Compensation Workbench
Cash Management
Kronos
Mobile SC
iProcurement
Inventory
Purchasing
Human Resources - Employee Hierarchy for
Approval Routing
General Ledger - Accounting Structure Foundation
In Production
To be Implemented
UCMC Licenses
Additional Products
22
Lessons Learned
23
Lessons Learned
  • Must Have Senior Management Commitment
  • Developed Steering Committee that provided
    overall project governance, budget oversight and
    were actively involved in project planning
  • Senior Management committed to making quick
    decisions
  • Senior Management was committed to allowing
    funding to be spent creatively to meet project
    objectives

24
Lessons Learned
  • Must Have Dedicated and Skilled Project Team
  • Team members must be flexible enough to wear more
    than one hat effectively
  • No dedicated PM resulted in shared responsibility
    between UCMC IT, HR and acquired consulting
    services
  • Subject Matter Experts are Key
  • Departments filled analyst roles as needed
  • Results in strong ownership of final solution

25
Lessons Learned
  • Must Have Dedicated and Skilled Project Team
  • Ensure team is fully integrated
  • Improves final product
  • Avoids silos
  • Enhances communication
  • Team members must be able to think outside the
    box BUT within the application to make choices
    without customizations

26
Lessons Learned
  • Must Have Dedicated and Skilled Project Team
  • Team members must be provided sufficient training
    (preferably in-house) during key phases of the
    project
  • Use consultants wisely
  • UCMC engaged 3 consulting firms based on need and
    budget Oracle being the prime
  • Consultants were used in initial phases then
    disengaged before final phases
  • Important that knowledge is transferred to staff

27
Lessons Learned
28
Lessons Learned
  • Must Have A Strong and Proven Project
    Methodology
  • UCMC utilized a unique project structure allowing
    for three successive projects to run at once
  • Platform Upgrade
  • Integration into Oracle Learning Management
  • HR Implementation

29
Lessons Learned
  • UCMC followed basic System Lifecycle Development
    methodology in addition to Oracle AIM for
    Business Flows (Healthcare) and AIM Phases,
    Definition and Elaboration

30
Lessons Learned
31
Lessons Learned
  • Must Manage SCOPE
  • Focus on core issues deferring wish list items
  • Senior Management must make the hard decisions to
    change and be able to say NO
  • Do Not concede to the 20 of the 80/20 rule
  • Understand the scale of 1-10 philosophy
  • A 5 is always better than a 2
  • No need to always shoot for a 10

32
Lessons Learned
  • Must Manage SCOPE
  • Get key decision makers involved in requirements
    gathering
  • Validate requirements
  • Trust but VERIFY
  • Key message to stakeholders Vanilla is good

33
Lessons Learned
  • Allow application best practices to govern
    business process

Strapping new technology onto current processes
will negate the value of the technology !!!
34
Lessons Learned
  • Must Manage SCOPE
  • No customizations - We like the word Extensions

Customizations
35
Lessons Learned
  • Must Manage SCOPE
  • Oracle Developed a RICE list (Reports,
    Interfaces, Conversion and Extension)
  • Used to identify and manage requirements
  • Clearly defines what type of requirement
  • If an item was defined as a gap it was removed
    and considered out of scope

36
Lessons Learned
  • Must Follow Project Plan
  • UCMC used a phased approach
  • Core foundation applications rolled out first
    followed by specialty applications such as
    Compensation Workbench and Self Service
  • Recommended for in-house implementations that are
    low on resources and can be spread over an
    extended time
  • Regular meetings with entire team is critical
  • Communicate potential risks EARLY

37
Lessons Learned
  • Must Follow Project Plan
  • Set overall project timeline at the beginning of
    the project
  • Use project plan versioning as each phase
    progresses
  • Track project deliverables in one week cycles
    with team reviews on a regular schedule

38
Lessons Learned
  • Test Often
  • Since UCMC used Oracles Accelerator methodology
  • Testing was a natural progression of the process
  • Conference Room Pilots were used to validate
    results of testing

39
Lessons Learned
  • Test Often
  • UCMC utilized HR constituents as part of the
    testing and CRP sessions (Very Important)
  • Able to manage expectations company wide
  • Minimizes the squeaky wheel
  • Acquire buy-in before roll out
  • This became the official HR core user group to
    be used for subsequent HR implementations and
    pilots

40
Lessons Learned
  • Test Often
  • Do Not overlook parallel testing to validate
  • Migration of configurations and code
  • Time required for cutover
  • Execution of conversions and interfaces
  • User interaction in real-life situations
  • System performance
  • Comparison of results with production
  • Uncovers issues with system, training or
    communications

41
Lessons Learned
  • Follow a formal Change Management Process
  • Follow change control process for changes to
    scope, overall timeline or budget
  • Follow a formal Risk Management Project review
    Process
  • Building in reviews of large deliverables as they
    are worked on will confirm approach across the
    entire team and measure progress

42
Lessons Learned
  • Communicate, Communicate, Communicate
  • Bring project team together on a regular basis
  • Hold multiple design sessions with key
    stakeholders in attendance
  • Distribute meeting minutes for full team review
    not just to those in attendance
  • Develop a communication plan for internal project
    members, management and external users

43
Lessons Learned
  • Timing is Everything
  • If this would have remained a part of original
    2003 implementation it would have failed
  • Lack of HR expertise
  • More customizations
  • Would have been considered a lower priority than
    supply chain
  • The success was due to HR being the only
    application implemented in 2007 within Oracle
    eBusiness Suite

44
Summary
45
Summary
  • Implementation was on time and under budget
  • 20 was returned to project contingency
  • Core HR live in March 2007 with limited Manager
    Self-Service
  • Compensation Workbench live in June 2007
  • The components that were rolled out to UCMC
    employees was received favorably
  • Over 6000 users impacted
  • Over 110 departments impacted

46
Summary
  • Core implementation created a solid foundation
    and methodology for further implementations
  • Online Performance Management (2008)
  • Increased Manager Self-Service (2008)
  • Employee Self Service (2008)
  • Payroll (2009)
  • General Ledger (2009)
  • The implementation fostered a strong and
    successful working relationship between UCMC HR
    and IT

47
Questions?
48
Contacts
  • Mario Ellis
  • Director, Compensation HR Systems
  • University of Chicago Medical Center
  • E-mail mario.ellis_at_uchospitals.edu
Write a Comment
User Comments (0)
About PowerShow.com