ITEC 3010

1 / 62
About This Presentation
Title:

ITEC 3010

Description:

ITEC 3010 Systems Analysis and Design, I LECTURE 3: The Analyst as a Project Manager [Prof. Peter Khaiter] – PowerPoint PPT presentation

Number of Views:5
Avg rating:3.0/5.0
Slides: 63
Provided by: Khai150

less

Transcript and Presenter's Notes

Title: ITEC 3010


1
ITEC 3010 Systems Analysis and Design,
I LECTURE 3The Analyst as a Project Manager
Prof. Peter Khaiter
2
Lecture Outline
  • IS Projects Success and Failure
  • Role of the Project Manager
  • Project Management Tasks in SDLC
  • Project Initiation and Project Planning
  • Project Planning Activities
  • Project Schedule
  • Risks Management and Project Feasibility
  • Financial Calculations
  • Tangible and Intangible Benefits
  • Staffing the Project
  • Launching the Project

3
Project Success Factors
  • Project management important for success of
    system development project
  • 2000 Standish Group Study
  • Only 28 of system development projects
    successful
  • 72 of projects cancelled, completed late,
    completed over budget, and/or limited in
    functionality
  • Thus, project requires careful planning, control,
    and execution

4
Reasons for Project Failure
  • Incomplete or changing requirements
  • Limited user involvement
  • Lack of executive support
  • Lack of technical support
  • Poor project planning
  • Unclear objectives
  • Lack of required resources

5
Reasons for Project Success
  • Clear system requirement definitions
  • Substantial user involvement
  • Support from upper management
  • Thorough and detailed project plans
  • Realistic work schedules and milestones

6
Role of the Project Manager
  • Project management organizing and directing
    people to achieve a planned result within budget
    and on schedule
  • Project manager a person has primary
    responsibility for the functioning of the team.
  • Success or failure of project depends on skills
    of the project manager
  • Beginning of project plan and organize
  • During project monitor and control
  • Responsibilities are both internal and external

7
Internal Responsibilities
  • Identify project tasks and build a work breakdown
    structure
  • Define the milestones (i.e., key events in a
    project which can be identified by a specific
    pieces of documentation or a specific status
    review meeting) and deliverables to monitor
    progress.
  • Develop the project schedule
  • Recruit and train team members
  • Assign team members to tasks
  • Coordinate activities of team members and
    subteams
  • Assess project risks
  • Monitor and control project deliverables and
    milestones
  • Verify the quality of project deliverables

8
External Responsibilities
  • Report the projects status and progress
  • Establish good working relationships with those
    who identify the needed system requirements
  • The people who will use the system
  • Work directly with the client (the projects
    sponsor) and other stakeholders
  • Identify resource needs and obtain resources

9
Participants in a System Development Project ?
  • A project manager reports to and woks with
    several groups of people
  • The client is a person or group of people who
    will be paying for the development of the new
    system the customer. The client releases funds
    and ultimately approves the project. For in-house
    development, the client can be an executive
    committee or a particular vice president who is
    funding the project
  • For large project, an oversight committee may
    be formed. This committee consists of clients and
    other key executives who have a vision of the
    strategic direction of the organization and have
    a strong interest in the success of the project
  • Users are the people who will actually be
    using the new system. The user typically provides
    information about the detailed functions and
    operations of the new system

10
Participants in a System Development Project ?
11
Various Titles/Roles of Project Managers
12
Project Management Tasks throughout the SDLC
  • Overlap with SDLC phases
  • Beginning of project
  • Overall project planning
  • During project
  • Project execution management
  • Project control management
  • Project closeout
  • Project management approach differs for
  • Predictive SDLC (linear, concurrently with SDLC
    activities)
  • Adaptive SDLC (in cycle, planning is distributed
    across the entire SDLC)

13
Project Management Tasks in SDLC
14
Project Execution Management
  • Following the project schedule
  • Assigning and coordinating the work of project
    team
  • Communicating with all project stakeholders

15
Project Control
  • Determining progress and taking corrective
    actions when necessary
  • Assessing whether requests for scope changes are
    necessary
  • Maintaining an outstanding issues list
  • Resolving problems

16
Project Closeout
  • To smooth project shutdown
  • Releasing team members for other assignments
  • Finalizing the budget
  • Reviewing or auditing the results of the projects

17
Project Management and SDLC Tasks for a
Predictive Project
18
Project Management and SDLC Tasks for an Adaptive
Project
19
Project Management Body of Knowledge (PMBOK)
  • Developed by The Project Management Institute
    (PMI)
  • 9 knowledge areas foundation information for
    every project manager
  • Scope management
  • control functions included in system
  • control scope of work done by team
  • Time management
  • Build detailed schedule of all project tasks
  • Monitor progress of project against milestones
  • Cost management
  • Calculate initial cost/benefit analysis
  • Monitor expenses

20
Project Management Body of Knowledge (contd)
  • Quality management
  • Establish quality plan and control activities for
    each project phase
  • Human resource management
  • Recruit and hire project team members
  • Train, motivate, team build
  • Communications management
  • Identify stakeholders and their communications
  • Establish team communications

21
Project Management Body of Knowledge (contd)
  • Risk management
  • Identify and review risks for failure
  • Develop plans to reduce these risks
  • Procurement management
  • Develop requests for proposals (RFPs)?
  • Evaluate bids, write contracts, monitor
    performance
  • Integration management

22
Project Initiation and Project Planning
  • Driving forces/Reasons to start project
  • Respond to opportunity
  • Resolve problem
  • Conform to directive

23
Project initiation
  • Top-down projects. The optimal method is through
    the long-term IS strategic plan, that identifies
    the overall efforts of the organization to
    maintain a competitive positions and results in
    specific projects.
  • Bottom-up projects. Individual department
    managers or process managers are close to the
    daily work. They often identify IS problems
    within their respective areas. Brought to the
    attention of the strategic planning committee,
    these needs are integrated into the overall
    business strategy. In case of immediate needs
    that cannot wait for the strategic plan (such as
    a new sales commission schedule or a new
    productivity report), the process manager may
    request initiation of individual development
    projects.
  • Outside-forces project. Projects can be initiated
    to respond to outside forces. One common outside
    pressure is legislative changes such as changes
    in tax or labor law. These changes affect the
    strategic plan, resulting in an urgent need for
    new IS.

24
CASE STUDY CSS Project initiation for Rocky
Mountain Outfitters
  • Strategic IS plan directs project development
    priorities
  • RMOs strategic plan is to build more direct
    customer contact, improve service, and expand the
    marketing presence
  • Customer support system development selected as a
    top priority
  • Customer support system (CSS) selected
  • John MacMurty creates project charter
  • Barbara Halifax project manager
  • Steven Deerfield senior systems analyst
  • Goal is to support multiple types of customer
    services (ordering, returns, online catalogs)?
  • Project charter describes key participants

25
RMO Project Charter
26
Project Planning Activities
27
Project Planning Activities and their key
questions
28
Defining the Problem
  • Review business needs
  • Use strategic plan documents
  • Consult key users
  • Develop list of expected business benefits (i.e.,
    results organization expects to achieve from the
    new IS)
  • Identify expected system capabilities (at a
    general level)
  • Define scope in terms of requirements
  • Create system scope document (3 components
    problem description, business benefits, system
    capabilities)
  • Build proof of concept prototype (if new
    technology or new solutions) to show they are
    feasible and possible
  • Create context diagram (scope of the IS) an IS,
    external entities and input/output information
    flows

29
System Scope Document
30
Context Diagram for Customer Support System
31
CASE STUDY Defining the Problem at RMO
  • Barbara and Steven, the CSS project team,
    developed the list of business benefits and
    system capabilities and the context diagram after
    talking to William McDougal, vice president of
    marketing and sales
  • Steven did some preliminary investigation on
    possible alternative solutions (researched the
    trade magazines, the Internet, and other sources
    to determine whether there were sales and
    customer support systems that could be bought and
    installed rapidly. None seemed to have the exact
    match of capabilities that RMO needs)
  • They decided to proceed with the analysis phase
    before making any final decisions about solutions
  • They began developing a schedule, budget, and
    feasibility statement for the new system.

32
Producing the Project Schedule
  • Each project consists of tasks, activities and
    phases.
  • A phase is made up of a group of related
    activities
  • An activity is made up of a group of related
    tasks
  • A task is a smallest piece of work that is
    identified, named and scheduled
  • The development of a project schedule involves
    three main steps
  • Develop work breakdown schedule
  • Build a PERT/Gantt chart
  • Develop resource requirements and staffing plan

33
Work Breakdown Structure (WBS)
  • A work breakdown structure (WBS) is a hierarchy
    of tasks, activities and phases for the project.
  • It is used as a foundation for developing the
    project schedule, identifying milestones in the
    schedule and for managing the costs
  • Each task has an associated duration (sometimes
    three different values expected, pessimistic and
    optimistic) and number of resources required)
  • How to identify tasks
  • Top-down identify major activities first, then
    internal tasks
  • Bottom-up list all the tasks and organize them
  • Analogy from similar projects

34
RMO Work Breakdown Structure
35
Project Scheduling
  • Developing a project schedule is a four-step
    process
  • (1) Project members identify all tasks for
    each activity
  • (2) Estimation the size of the task number of
    human resources, person-day required, calendar
    time required and any other specific resources
  • (3) Determining the sequence of the tasks
  • (4) Scheduling the tasks themselves
  • There are special techniques and tools for
    project scheduling (e.g., MS Project)

36
PERT/CPM Chart
  • PERT/CPM (Project Evaluation and Review
    Technique/Critical Path Method) chart
  • shows the relationships among tasks
  • defines tasks that can be done concurrently
  • shows the critical path ( the longest path of
    dependent tasks from the first task to the last
    task, i.e. the shortest completion period for the
    project)
  • If any task on that path slips, then the entire
    project schedule will slip
  • Other tasks (not on the critical path) usually
    have some slack time (the amount of time that the
    task can slip without affecting the schedule)
  • Good to show dependencies and critical path but
    it is not easy to see the projects progress on a
    PERT chart

37
Partial PERT/CPM chart for the CSS project
38
Gantt chart
  • Gantt Chart shows information for each task as
    horizontal bar chart where the vertical tick
    marks are calendar days and weeks
  • Doesnt show the dependencies of tasks
  • A good tool for monitoring the progress of the
    project
  • Tasks represented by horizontal bars
  • Vertical tick marks are calendar days and weeks
  • Shows calendar information in a way that is easy
    to track
  • Bars may be colored or darkened to show completed
    tasks
  • Vertical line indicates todays date

39
Partial Gantt chart for the CSS project
40
Importance of the Proper Project Scheduling
  • In 1984, Microsoft planned to develop MS Word for
    one year
  • At that time, this was two months less than the
    most optimistic estimated deadline for a project
    of its size
  • In reality, it took Microsoft five years to
    complete Word
  • Ultimately, the overly aggressive schedule for
    Word slowed its development for a number of
    reasons
  • The project experienced high turnover due to
    unreasonable pressure and work hours
  • Code was finalized prematurely, and the
    software spent much longer in stabilization
    (i.e., fixing bugs) than was originally expected
    (i.e., 12 months versus 3 months).
  • Aggressive scheduling resulted in poor planning
    the delivery date consistently was off by more
    than 60 for the first four years of the project

41
Just For Fun
http//www.getfunnypictures.com/crt052.html
MS software release
42
Risks Management and Project Feasibility
  • Risk management
  • Organizational and cultural feasibility
  • Technological feasibility
  • Schedule feasibility
  • Resource feasibility
  • Economic feasibility
  • Cost/benefit analysis
  • Sources of funds (cash flow, long-term capital)?

43
Risk Analysis
44
Organizational and Cultural Feasibility
  • Each company has own culture
  • New system must fit into culture
  • Evaluate related issues for potential risks
  • Low level of computer competency
  • Computer phobia
  • Perceived loss of control
  • Shift in power
  • Fear of job change or employment loss
  • Reversal of established work procedures
  • Positive steps should be undertaken to reduce the
    risks
  • E.g. additional training can be held to teach
    new procedures and provide increased computer
    skills

45
Technological Feasibility
  • Does system stretch state-of-the-art technology?
  • Does in-house expertise presently exist for
    development?
  • Does an outside vendor need to be involved?
  • Solutions include
  • Training or hiring more experienced employees
  • Hiring consultants
  • Changing scope and project approach

46
Schedule Feasibility
  • Estimates needed without complete information
  • Management deadlines may not be realistic
  • Project managers
  • Drive realistic assumptions and estimates
  • Recommend completion date flexibility
  • Assign interim milestones to periodically
    reassess completion dates
  • Involve experienced personnel
  • Manage proper allocation of resources

47
Resource Feasibility
  • Team member availability
  • Team skill levels
  • Computers, equipment, and supplies
  • Support staff time and availability
  • Physical facilities

48
Economic Feasibility
  • Cost/benefit analysis
  • Estimate project development costs
  • Estimate operational costs after project
  • Estimate financial benefits based on annual
    savings and increased revenues
  • Calculate using table of costs and benefits
  • Uses net present value (NPV), payback period,
    return on investment (ROI) techniques

49
Development Costs for RMO
  • The project manager has responsibility for
    estimating the cost of development
  • Salaries and wages
  • Equipment and installation
  •  Software and licenses
  • Consulting fees and payments to third parties
  • Training
  • Facilities
  • Utilities and tools
  • Support staff
  • Travel and miscellaneous

50
Supporting details of salary and wages for the
CSS project
51
Summary of Development Costs for RMO
52
Operating Costs
  • The following list identifies the major
    categories of costs that may be allocated to the
    operation of the new system
  • connectivity
  • equipment maintenance
  • computer operations
  • programming support
  • amortization of equipment
  • training and ongoing assistance (e.g., help
    desk)
  • supplies

53
Summary of Annual Operating Costs for RMO
54
Just For Fun
Technical support
55
Sources of Benefits
  • Benefits usually come from two major sources
  • decreased costs
  • increased revenues
  • Unlike development costs, there are no standard
    benefits
  • Sample of reduced costs
  • Reducing staff due to automating manual
    functions or increasing efficiency
  • Maintaining constant staff with increasing
    volumes of work
  • Decreasing operating expenses, such as
    shipping charges for emergency shipments
  • Ensuring quicker processing and turnaround of
    documents or transactions
  • Capturing lost discounts on money management
  • Reducing bad accounts or bad credit losses
  • Reducing inventory or merchandise losses due
    to tighter controls
  • Collecting accounts receivables more quickly
  • Capturing income lost due to stock outs
    with better inventory management
  • Reducing the cost of goods with volume
    discounts and purchases
  • Reducing paperwork costs with electronic data
    interchange and other automation

56
Sample Benefits for RMO
57
Financial Calculations
  • Companies use a combination of methods
  • Fist approach, called the net present value
    (NPV), has two concepts
  • (1) all benefits and costs are calculated in
    terms of todays dollars (present value)
  • (2) the future streams of benefits and costs are
    netted together and then discounted by a certain
    factor for each year in the future
  • Second method to determine whether investments
    will be beneficial is to determine the payback
    period, sometimes called the breakeven point.
    This is the point in time at which benefits
    becomes equal to the cost of development and
    operation
  • Third economic measure is the return on
    investment (ROI). ROI shows a percentage return
    needed so that the costs and benefits are exactly
    equal over the specified time period.

58
RMO Cost Benefit Analysis
59
Tangible vs. Intangible Benefits
  • Tangible benefits can be measured or estimated
    in terms of dollars
  • Intangible benefit cant be directly measured
    or estimated in dollars
  • In some instance, the intangible benefits far
    exceed the tangible costs
  • Examples of intangible benefits
  • Increased levels of service (in ways that
    cannot be measured)
  • Increased customer satisfaction (not
    measurable)
  • Survival (a standard capability common in the
    industry, or common to many competitors)
  • The need to develop in-house expertise (such as
    with a pilot program with new technology)
  • Examples of intangible costs
  • Reduced employee moral
  • Lost productivity (inestimable)
  • Lost customers or sales (during some period
    of time)

60
Staffing the Project
  • There are five tasks within this activity
  • Develop a resource plan
  • Identify and request technical staff
  • Identify and request specific user staff
  • Organize the project team into work groups
  • Conduct preliminary training and team-building

61
Launching the Project
  • Scope defined, risks identified, project is
    feasible, schedule developed, team members
    identified and ready
  • Oversight committee finalized, meet to give
    go-ahead, and release funds
  • Formal announcement made to all involved parties
    within organization

62
Readings
Todays lecture Chapter 3 The Analyst as A
Project Manager For next week Chapter 4
Investigating System Requirements
Thank you !!!