Sectors, Rings, Frame Assembly and Installation - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Sectors, Rings, Frame Assembly and Installation

Description:

Internal End Cone (2) LBNL responsibilities shown in red (Services not shown) ... No costs for CERN operations(cranes, consumables) yet included. M. Gilchriese. 16 ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 17
Provided by: Gilch
Category:

less

Transcript and Presenter's Notes

Title: Sectors, Rings, Frame Assembly and Installation


1
Sectors, Rings, Frame Assembly and Installation
  • July 18

2
WBS 1.1.1.1 Mechanics Part I
Center Frame Section (1)
Disk Section (2)
Disk sectors (8)
Internal End Cone (2)
Interior Barrel Layers
LBNL responsibilities shown in red (Services not
shown)
Disk Rings
3
Overview
  • Costs are in FY02 K.
  • All costs shown for sectors, rings and frame are
    in FY03 only.
  • Disk assembly. Mounting sectors with
    modules/cables on to rings and testing.
  • Disk final assembly. Putting these real disks
    into frame, testing and shipping to CERN
  • Installation in FY05 only covers surface
    integration labor. Tooling for integration either
    supplied by European collaborators or will have
    already been made and shipped to CERN. Note that
    all installation costs in FY05 are currently in
    management contingency.

4
Sectors
  • Deliverable 48 sectors available for experiment,
    60 will be started.
  • 1.1.1.1.1 Design complete
  • 1.1.1.1.2 Prototyping complete
  • 1.1.1.1.3 Production
  • One part made with production tooling(but not
    with fittings).
  • Materials (13K) and shop labor
  • All parts in hand. All tooling in hand but have
    budgeted some for maintenance/replacement of some
    parts that may wear out(2K). Supplies(2K).
    Thermal QA fixture /completionreplacement
    parts(5K). Storage boxes(1K). Parylene
    coating(3K)
  • Shop labor of 210 hours.
  • Other labor(see summary later in talk)
  • Assembly by J. Wirth and T. Johnson(part time).
  • QA by them T. Weber, students(part time)
  • Schedule
  • Substantial delay from problems laser welding.
  • ETC02 completion date 9/27/02
  • ETC03 completion date 3/31/03
  • Float remaining about 1 year for production
    modules, but will need some sectors earlier for
    practicing module mounting and system tests. Not
    a problem if laser welding is successful.

5
Rings and Related(1)
  • Deliverable 6 rings with mounts, insertable into
    frame available
  • 1.1.1.1.1 Design
  • Ring-only design is complete, including of mounts
    to frame. Remaining production design oversight
    to be completed by Hytec(10K)
  • Strain-reliefs of sector tubes to ring to be
    designed J. Wirth(see summary at end)
  • Ring insertion-into-frame tooling. Prototype
    completed and tried successfully but with
    different ring size. Design modifications to be
    done by F. Goozen(see summary at end).
  • 1.1.1.1.2 Prototyping complete apart from
    strain reliefs, included in production for
    convenience.
  • 1.1.1.1.3 Production
  • Rings only(92K)
  • Preproduction ring has been fabricated
    successfully. All materials in hand for
    production rings. Production contract placed but
    only costed in FY03(70K). Final
    inspection(survey) to be done at LBL(6K). Storage
    and shipping boxes(must include provision for
    sectors with real modules)(6K). Mounts to
    frame(10K)
  • Strain reliefs(10K)
  • 10K for materials and fabrication only. Labor to
    put on rings from J. Wirth and T. Johnson(see
    summary at end).

6
Rings and Related(2)
  • 1.1.1.1.3 Production(continued)
  • Ring insertion(10K)
  • Revised tooling(includes shop labor) for
    production rings
  • Labor from F. Goozen(see summary at end)
  • Schedule
  • ETC02 completion date 9/27/02
  • ETC03 completion date 12/15/02(rings only, which
    is what is needed for drilling holes in frame).
    6/15/03(with strain reliefs)
  • Float remaining gt4 months(rings only) for
    starting dry fit of frame. About 1 year for
    production modules.

7
Frame(1)
  • Deliverable support frame, three pieces. Barrel
    delivered to CERN empty. Disks active(see disk
    final assembly).
  • 1.1.1.1.1 Design
  • Frame only. Complete apart from production
    oversight by Hytec(70K)
  • Dry fit, survey and shipping design to be done by
    F. Goozen
  • 1.1.1.1.2 Prototyping complete apart from minor
    items
  • 1.1.1.1.3 Production
  • Frame only(121K)
  • Tooling(11K). Contracts placed and will be
    delivered and costed before end FY02 apart from
    endplate tooling.
  • Materials. All ordered and will be delivered by
    end of FY02.
  • Assembly(110K). Contract placed. We assume all to
    be costed in FY03.
  • Dry fit(5K)
  • Miscellaneous parts and tooling for simple dry
    fit.

8
Frame(2)
  • 1.1.1.1.3 Production(continued)
  • Survey(15K).
  • We dont know yet know exactly how this will be
    done
  • Shipping(1K)
  • Barrel only
  • Disks covered under Final Assembly
  • Schedule
  • ETC02 completion date 4/7/03(frame only), dry
    fit complete(9/22/03)
  • ETC03 completion date 4/7/03 and 9/22/03

9
Disk Assembly
  • Deliverable 4 operational disks ready for
    insertion into frame
  • 1.1.1.1.1 Design
  • No significant design done. See labor table at
    end.
  • 1.1.1.1.2 Prototyping
  • None planned. Only real items.
  • 1.1.1.1.3 Production
  • All tooling and materials in FY04. Labor-see
    table at end.
  • Sector pick up and place tooling
  • Survey and storage tooling for each disk
  • Test fixtures(dry/dark box, chillers, does not
    include readout electronics or power supplies)
  • Storage and shipment boxes
  • ETC02 estimate of 50K, not including technician
    labor still looks OK. Need more design and
    experience(system test) to update.

10
Disk Final Assembly
  • Deliverable Disk regions at CERN
  • 1.1.1.1.1 Design
  • No significant design done. See labor table at
    end.
  • 1.1.1.1.2 Prototyping
  • None planned. Only real items.
  • 1.1.1.1.3 Production
  • We assume all tooling and materials are done in
    FY04. Labor see table
  • Disk frame support, temporary cable support and
    assembly table/guides
  • Cable/pipe strain reliefs
  • Disk insertion tooling, including cable holding
  • Testing tooling(dry box, temporary supports for
    pipes, cables)
  • Shipping boxes and shipping
  • ETC02 estimate of 107K, not including technician
    labor still looks OK. Requires more design and
    experience(system) test to update.

11
Disk Final Assembly
  • Production(more)
  • Final assembly and testing will occur in clean
    room (Bldg. 77) at LBL
  • Expectation is that results from evolving system
    testing to start end this year will guide scope
    of testing during and after assembly.
  • We dont understand yet how to cool any
    significant part and actually complete the final
    assembly. No evaporative cooling available at
    LBL. So we either test with temporary inlet
    cooling fittings or figure out some way to cool
    with the capillary fittings in place. Note that
    disk testing will be done with temporary fittings
    and liquid cooling.
  • Conservative assumption is that we disassemble
    disks from frame and ship individually to CERN
    and then reassemble there.

12
Preliminary Summary
  • Significant cost increase(roughly 100K), but will
    take to October to get better
  • 6 month delay in sector completion, much more
    prototype work, laser welding problems, much more
    labor required in FY03.
  • Basic cost of rings and frame very close to
    estimate, but forgotten items(survey, strain
    reliefs, ) now added
  • Reduced base program support at LBL projected.

13
Integration/Installation
  • Initial support tube installation(barrel) in
    FY04. Final in FY05.
  • Conservative assumption is that we have to put
    disks into frame at CERN
  • Unpack tooling sent from US and setup up
  • Unpack testing equipment sent from US and setup
    or duplicate at CERN or some combination
  • Unpack disks and test each one
  • Put disks into frames and test separately from
    barrels
  • Integrate disks and barrels, testing(somehow) as
    we go
  • Partial test of barrels disks without service
    panels
  • Integrate beam pipe/service panel support
  • Install service panels/PP1
  • Test as one goes.
  • Final 10 cold test before lowering into pit
    for installation
  • Slide in, hook up and test

14
FY04/FY05/FY06
  • Preliminary plan produced and sent to
    Rossi/Stapnes based on this schedule. Note
    schedule is in calendar years.

15
Installation Costs
  • Personnel-related costs in FY02 K.
  • Costs for SR building and other infrastructure
    covered under MO(we hope). No costs for CERN
    operations(cranes, consumables) yet included.

16
Design Labor(1.1.1.1.1)
  • Engineers, designers, engineering interns
    travel/supplies
  • Includes external contracts eg. Hytec who has
    been responsible for ring and frame design
    completely.
  • FY02 manpower is about(in FTE)
  • 3 engineers
  • 1 designer
  • 1.5 mechanical engineering student(multiple
    people)
  • Beam pipe support is currently separately funded
    project but only for FY02 at the moment.
  • Installation is not included here.
  • Increase in FY04/FY05 results from reduced
    expectations for base support, delays and better
    understanding of scope
Write a Comment
User Comments (0)
About PowerShow.com