Title: MITTAL STEEL SOUTH AFRICA CAPITAL PROJECTS INFORMATION DAY
1MITTAL STEEL SOUTH AFRICACAPITAL PROJECTS
INFORMATION DAY
- Programme 30 November 2005
- 1000 1015 Opening and welcoming by the CEO
- 1015 1045 Presentation by General Manager,
Procurement Logistics - 1045 1115 Presentation by Manager, Relines
- 1115 1200 Closure by General Manager,
Procurement Logistics
2Todays discussion
- Mittal Steel South Africa Strategic Goals and
Throughput Strategy - Overview of Capital Projects planned by Mittal
Steel South Africa Limited (2006 2010) - Blast Furnace D Reline 2006
- BEE and areas of concern
3Strategic Goals and Throughput Strategy of Mittal
Steel South Africa
4Strategic Goals
- Industry leading value-creation for our
shareholders - - Positive EVA over the cycle
- Improve operating Capabilities
- - Value-creating throughput increases of 2 Mtpa
- - 20 reduction in HRC/billet cash cost by 2007
- Build a high performance culture
- - Create an environment that generates true
employee pride attracts, develops retains
top-performing people - Be a responsible corporate citizen
5Throughput Strategy
- Increase production by 1,5 Mtpa by end 2007
with initial capex - - 325 ktpa 2 new DRI kilns at Vanderbijlpark
by 2H/07 - - 660 ktpa efficiency improvements by 2H/06
- - 445 ktpa Blast furnace D reline at
Vanderbijlpark by 2H/06 - - Expand sinter capacity at Vanderbijlpark by
1H/08 - Utilize opportunities to increase throughput by
further 1Mtpa with capital expenditure - - 505 ktpa Additional DRI kilns at
Vanderbijlpark by 2H/09 - - 355 ktpa Blast Furnace C reline at
Vanderbijlpark by 2012 - - 105 ktpa Smaller capital projects at
Saldanha and Vereeniging - Rationalization of other facilities to follow
6Overview of Capital Projects planned by Mittal
Steel South Africa Limited(2006 2010)
7Distribution per Geographical area
8Vanderbijlpark Steel
- An overview of the projects planned at
Vanderbijlpark Steel is the following - 30 Projects gt R 20m
- 17 Projects R10m to R20m
- 200 Projects lt R10m
9Saldanha Steel
- An overview of the projects planned at Saldanha
Steel is the following - 8 Projects gt R20m
- 5 Projects R10m to R 20m
- 90 Projects lt R10m
10Newcastle Steel
- An overview of the projects planned at Newcastle
Steel is the following - 14 Projects gt R20m
- 11 Projects R10m to R 20m
- 80 Projects lt R10m
11Vereeniging Steel
- An overview of the projects planned at
Vereeniging Steel is the following - 6 Projects gt R20m
- 4 Projects R10m to R 20m
- 110 Projects lt R10m
12Mittal Coke Chemicals
- An overview of the projects planned at Mittal
Coke Chemicals is the following - 2 Projects gt R20m
- 5 Projects R10m to R 20m
- 96 Projects lt R10m
13Overview on 2 new DRI Kilns 5 6 and additional
sinter strand
14Kiln 5 6 Project ScopeThe project is an
integral part of our expansion strategy and
consists of five main components
- Material Handling
- Raw Materials Handling
- Product Handling
- Ash Handling
- Kiln and Cooler Proper (2 off)
- 80 m Kiln, 4.8 m diam
- 50 m Cooler, 3.2 m diam
- After Burner Chamber (ABC) and Dust Settling
Chamber (DSC) - Various bought out items fans,motors,gearboxes,p
umps. - 66 Bar Waist Heat Boilers (2 off)
- Electrostatic Precipitators (2 off)
- Power Plant (Turbo Alternator Set)
15Kiln 5 6 Project Activities
- Design
- Project Management of total or portions of
project - Site establishment
- Civil Construction
- Electrical supply and control equipment
- Various bought out items fans, motors,
gearboxes, pumps. - Erection of buildings, kiln and coolers, Boilers,
ESP - Transport and cranes
16Sinter Upgrade Project ScopeThis project is an
integral part of the expansion strategy and
consists of the following elements.
- Raw Material Handling
- Extend Fine Material Blending bed by 150 m
- Install new Tippler
- Install raw material buffer facility
- New conveyors ca 2500 m
- Sinter Plant proper
- 159 m² Sintering area, 130 pallet cars
- Off strand rotary Cooler
- Extend cold screening, crushers and screens
- 4 x 400 m3 steel bins and mixing drum
- Various bought out items fans,motors,gearboxes,p
umps. - Install extra power supply capacity ca 20 MWh
17Blast Furnace D Reline 2006
18Blast Furnace D Reline 2006
- Index
- Objective of reline
- Background
- Overview of scope
-
19Blast Furnace D Reline 2006Objective of Reline
- Campaign life of 20 years.
- Minimum downtime - 90 days.
- Production capacity 5700tHM/day after sinter
plant increased production. - An improved hot metal quality level and lower
standard deviation with respect to hot metal
silicon, sulphur and temperature. - Increased availability
20Blast Furnace D Reline 2006Background
- Blast Furnace D was relined in 1990 and since
then it has received 3 intermediate repairs - In 1997 the refractory material in the hearth
walls, the bosh, the belly of the furnace, and
the ceramic burners in all hot blast stoves were
replaced - In 2000 the refractory material in the lower
shaft, the throat armour, part of the furnace
shell and three segments of the bustle pipe were
replaced - In 2004 the cooling elements in the lower shaft
were replaced with staves, the furnace was
shotcreted, a water cooled under hearth system
was installed and the Paul Wurth gearbox was
replaced
21Blast Furnace D Reline 2006Background
- The project will be handled in the following
phases - Phase 0
- Conceptual study completed
- Phase 1
- Fixing of scope and budget - completed
- Phase 2
- Engineering and procurement - present
- Phase 3
- Reline start 1 July 2006
- Phase 4
- Project closure
22Blast Furnace D Reline 2006Overview of Scope
- Stockhouse and Furnace Charging
- Furnace Proper
- Casthouse
- Raw Gas System
- Electrical, Instrumentation Control
23Blast Furnace D Reline 2006Overview of Scope
- Stockhouse and Furnace Charging
- Refurbish existing equipment
- Increase coke storage capacity from 5 hours to
12 hours - Replace the redundant skip charging system with
a conveyor charging system - Install an additional dust extraction system
24Blast Furnace D Reline 2006Overview of Scope
- Furnace Proper
- Replace the complete furnace shell as the
existing bottom plate is cracked - Replaced the furnace hearth refractory material
- Install a copper and cast iron staves cooling
system - Install a closed cooled water system
- Replace damaged uptakes
- Replace the bustle main on a new elevation
25Blast Furnace D Reline 2006Overview of Scope
- Casthouse
- Increase the length of the iron troughs
- The cast house floor will be leveled for mobile
access - Install a ramp from ground level to the cast
house floor - Install air cooled troughs
- Install a new tuyere platform
- Install new slag runners to accommodate a new
casthouse layout
26Blast Furnace D Reline 2006Overview of Scope
- Raw Gas System
- Replace the primary dust catcher internal
trumpet - Replace the dust discharge equipment
- Refurbish the existing gas scrubber
- Install a new cooling tower
27Blast Furnace D Reline 2006Overview of Scope
- Electrical, Instrumentation Control
- Supply new electrical system for all new
equipment - Refurbish existing electrical systems
28BEE and Areas of Concern
29BEE Policy
- Realising that Black Economic Empowerment (BEE)
are the cornerstone of a strong and sustainable
economy, Mittal Steel South Africa Ltd commits
itself to actively support and contribute to the
development and growth of BEEs in the Republic
of South Africa. - We believe that the active development and the
participation of BEEs will ensure broad based
growth of the economy and the achievement of
sustainable development, job creation and general
prosperity in our country. - A BEE policy is in place that will enable Mittal
Steel South Africa Ltd and its employees the
opportunity to contribute effectively to a better
South Africa. - Mittal Steel South Africa Ltd commits itself to
pursue and actively promote this process.
30The objectives of the BEE policy
- To facilitate access of BEE Vendors, to Mittal
Steel South Africa Ltd procurement activities - To contribute to development and growth of BEE
- To establish, monitor and report progress against
annual targets for goods/services procured - To encourage major non-BEE vendors to establish
and implement BEE initiatives - The following shall not be compromised in the
process of giving effect to this policy - The expertise and experience of persons supplying
services - The specifications and quality of goods to be
supplied - Delivery reliability
- Pricing
31BEE Management
- Preferential treatment of BEE vendors
- In the process of awarding tenders by Mittal
Steel South Africa Ltd, preference shall be given
to BEE Vendors who meet all the tender
requirements. - Mittal Steel South Africa Ltd spend R1,023
Billion on BEE suppliers in 2004 - Projected spend on BEE suppliers for 2005 will
be R 1,615 Billion - During 2006 Mittal shall align its supplier
database with the new codes of Good Practice as
determined by the DTI
32Areas of Concern
- General skills shortage in the country due to
Engineers and artisans seeking international
employment during the last 10 years - Infrastructure and other expansion projects in
South Africa sucking up most of the Engineering,
Project Management and Manufacturing Capacity - Delivery Reliability due to the tight
deadlines, commitments to equipment delivery and
commissioning of projects must be adhered to at
all times - Sub-contracting of work Mittal Steel SA Ltd
conduct business with reliable vendors that are
capable of rendering a quality, affordable and
timely service. In the event of subcontracting
work, main contractors should verify the
capabilities of sub-contractors to perform the
work - Safety of contractors high activity at the
business units due to capital expansions leads to
a higher safety risk. Proof of section 16.1 or
16.2 responsible person appointments in terms of
the OSHACT is compulsory