By John Liedig - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

By John Liedig

Description:

Tower cranes are a common fixture at any major construction site. ... To use Strand 7 on a complicated structure such as a tower crane ... – PowerPoint PPT presentation

Number of Views:120
Avg rating:3.0/5.0
Slides: 31
Provided by: generalpur
Category:
Tags: cranes | john | liedig

less

Transcript and Presenter's Notes

Title: By John Liedig


1
Tower Crane
  • By John Liedig Jouline Nour

2
(No Transcript)
3
Counter Weight
Cables
Main Tower
4
Jib
5
Introduction
  • Tower cranes are a common fixture at any major
    construction site.
  • They often rise hundreds of feet into the air,
    and can reach out just as far.
  • Tower cranes are used to lift steel, concrete,
    large tools like acetylene torches and
    generators, and a wide variety of other building
    materials.

6
Arm and Tower Sections
Tower Section
Jib section
7
Dimensions
  • The tower crane is approximately 120m tall
  • 10m wide
  • The counter weighted arm is 60m long
  • And the main jib can be as long as 90m

8
Modelled Tower Crane
  • Looked at 2 scenarios
  • 2d
  • 3d
  • The aim was to determine the differences in both
    2D and 3D cases in relation to displacement and
    stress analysis

9
Objectives
  • To use Strand 7 on a complicated structure such
    as a tower crane
  • Model the tower crane to the dimensions given
    from relevant data
  • Determine stresses and displacements associated
    from various locations of loads on the structure
  • Try and improve the structure

10
Objectives
  • To see if there was a better way of modelling the
    tower crane on Strand 7
  • Through using different materials
  • Modifying the shape

11
Method
  • Determined the dimensions of the tower crane
    using data from the internet and other relevant
    crane construction guides
  • Determined various components involved in the
    tower crane
  • Identified the materials for each of the various
    components and then selected these from the
    strand 7 library

12
Method
  • Drew a 2D representation of the tower then the
    arm and then used strand 7 commands to convert
    into a 3D structure
  • Entered various loading scenarios
  • Ran analysis
  • Modified the elements accordingly to meet
    acceptable limits in the results.

13
Materials
  • The materials used were predominantly structural
    steel of various sizes
  • The cable also is made from steel with a free
    length ranging from 50 to 80m
  • All sections are circular hollow sections

14
Load Cases
  • Taken a variety of load cases
  • Loads were placed at individual nodes along the
    arm of the tower crane
  • In the final report the natural frequency is also
    going to be considered but hasnt been included
    now due to time constraints

15
Simplifications
  • The main simplifications were
  • Simplifying the concrete counterweights into a
    few point loads
  • Not having a pivoting base. I.e. the nodes at the
    bottom of the tower are fixed in all directions
    and rotations
  • The 3d case didnt incorporate the service crane
    and the extra cables

16
2D Tower Crane
Service Crane
Cables
17
3D Tower Crane
Cables
Loads
Fixed Nodes
18
2D Displacement Analysis Case1
19
2D Displacement Analysis Case 2
20
Displacement Analysis
1ST Case load at the end of the jib Maximum
displacement 1.5m
Loads counterweight 3x 30kN Jib 150kN
21
Displacement Analysis 3D
Load case 2 Maximum Displacement 0.41m
Loads counterweight 4x 20kN Jib 150kN
22
Displacement Analysis 3D
Third Load Case Maximum Displacement 0.6m
Loads counterweight 4x 20kN Jib 150kN
23
Displacement Analysis
  • The 2 and 3D cases give quite similar
    displacements
  • Up to 1.5m depending on the loads applied
  • The worst case is when the load is applied at the
    end of the jib, which is what is to be expected.

24
Stress Analysis
The stresses observed are not realistic ie. In
the thousands of MPa This result is evident in
all of the load cases
25
2D Stress Analysis Case 1
26
2D Stress Analysis Case 2
27
Stress Analysis
  • In all cases the stress is beyond the yield
    strength of the steel used.
  • Therefore there are errors that need to be
    corrected.
  • This will be done by making the critical tension
    members solid and looking at the weights of each
    member.

28
Errors
  • The main errors involved so far have been in
    relation to the units associated with the loads
    applied to the structure.
  • The high stress involved may be due to the weight
    of the structure as a whole.
  • Initially we were faced with problems relating to
    the stiffness matrix K.
  • This involved, free or unconnected elements and
    also defining an element more than once in the
    same position.

29
Modifications
  • Main modification factors are
  • Modifying the cross-sections of some members to
    decrease the high stresses observed
  • Wind load scenario
  • Natural frequency analysis
  • Seeing the effect of other materials and how they
    affect the results.

30
Thank you for listeningAny Questions??
Write a Comment
User Comments (0)
About PowerShow.com