Title: Restructured Accelerated Power Development and Reforms Programme
1Restructured Accelerated Power Development and
Reforms Programme
R-APDRP Implementation in Uttar Pradesh
Noida, UP 23rd December 2011
2Implementation Status in Uttar Pradesh
1.0 Sanction Implementation Status
Eligible towns Sanctioned Nos. / cost Sanction date Disbursement 3 Years from Sanction
Part-A (IT) 168 168/ Rs. 680.27 Cr June 09 Rs.190.27 Cr June 2012
Part-A(SCADA) 11 11/Rs. 246.55 Cr June 11/Oct 11 Nil June 2014
Part-B 167 161/Rs. 3283.59 Cr Aug. 10/Dec. 10 /June 11 Rs. 274.75 Cr Aug. 2013
- 2.0 Town Integration Schedule with DC
- Pilot Town Four Pilot Towns one in each DISCOM
expected in Dec. 2011
Month Actual Nov. 11 Dec.11 Jan. 12 Feb.12 March12 onwards
No. Of Towns 0 04 26 30 108
Cumulative Towns 0 04 30 60 168
3.0 Integration Of Towns other Activities
Major Activities For Integration Current Status Area Of Concern
Development of Application software and its integration. 12 modules are currently in production run for some of the consumers of pilot towns. Running of all the modules in integrated way is yet to be completed.
GIS (CI AM) CI-6 Towns/ AM-6 Towns Utility Approval 15 CI 19 AM only
Establishment of Baseline ATC Losses 1 town verified report submitted. Baseline data submitted for 134 towns is not proper for most of the towns
Award Of Part-B Towns RfP floated/Yet to be awarded. Utility needs to expedite.
3Implementation Status in Uttar Pradesh
Eligible towns Sanctioned Nos. / cost Sanction date Disbursement
Part-A (IT) 168 168/680.27 Cr. 30.06.2009/18.10.2011 190.27 Cr.
Part-A (SCADA) 11 11/246.35 Cr. 15.06.2011/18.10.2011 Nil
Part-B 167 161/3283.59 Cr. 16.08.2010/08.12.2010/15.06.2011/18.10.2011 274.75 Cr.
ITC Infosys ITIA HCL Technologies
(appointed in February 2010) SDC NDPL SIA
RfP for Bids yet to be issued TPIEA-EA
WAPCOS DC/DR Lucknow/Noida Pilot
Towns Lucknow, Meerut, Aligarh, Varanasi Ring
Fencing To Re-do Ring fencing in 33 towns based
on the gaps pointed out by TPIEA, by 15th
Nov.11. Baseline ATC 1 town.
Baseline data submitted for 134 towns but, the
data verification is not proper are to be re
done for most of these towns.
4Implementation status , Major Issues and
Intervention required in UP
-
- DC Hardware Installation Completed, All
Softwares are loaded, Datacenter is commissioned - 12 Modules (M, B, C, NC, DC, IDMS, GIS, MIS,
System Security, AM, MM, WSS) are currently in
production run and being used. - Rest of the modules acceptance testing has been
completed. - DR Center Hardware Installation completed, all
SW are loaded, DR is commissioned - CCC All 4 Call Centers are ready for GO LIVE
(Agra, Lucknow, Varansi and Meerut). -
- GIS Maps 161 towns available, Balance orders
have been placed on NRSC (Critical) - GIS survey Consumer survey WIP 57.0 (48
towns) (Critical) - , Asset survey WIP 60 (50 towns)
(Critical) -
- , IDMS Identity Management Services WSS
- Web self service
5Implementation status , Major Issues and
Intervention required in UP
Progress GIS Survey Summary
6Implementation Status in Uttar Pradesh
7Implementation Status in Uttar Pradesh
8Implementation status , Major Issues and
Intervention required in UP
- AMR Installation 8200 no of modems out of
45000 modems installed - Meter Installation All legacy meters are in
place. However, these are being replaced with
DLMS Complaint meters progressively as and when
the supplies are being received. Utilities
to complete meter installation so that modem can
be installed as per revised schedule. - End Location Site Readiness over 80 of the
non-Pilot sites/towns not ready to host the IT
Infrastructure - Part B Status Bid evaluation under process ,
to be completed by December 2011. To
commence the work so as to complete in
three years. (Critical) - Ring fencing To complete Ring fencing in 33
towns by Dec. 11, after addressing gaps
pointed out by TPIEA. (Critical) - Base Line Data Baseline data submitted for 134
towns being examined by TPIEA. DISCOMs have to
correct the gaps. (Critical) - Part A SCADA 1 DPR of Bareilly Town (added
recently) to be submitted by MVVNL. - RfP to be floated for appointment of SCADA
Implementation Agency - Incentive scheme Submitted by MVVNL, PuVVNL
and DVVNL.