US Army Corps of Engineers CD Canal Bridges
2
Philadelphia District
  • Tony DePasquale P.E. Chief of Operations
  • Timothy Rooney Project Manager
  • Edward Voigt Chief of Public Affairs
  • Susan Anderson Public Affairs

3
Summit Bridge
  • - Cantilever truss bridge
  • - Four-lane structure, Delaware
    Rte. 896 US Rte. 301
  • - 2,058 feet in length
  • - ADT 30,000
  • - Constructed 1957-1959

4
Time Line of Actions
  • September 2007 - Federal Highway Administration
    recommends to conduct additional inspection
    following I-35 Minneapolis Bridge failure.
  • November 2007 US Army Corps hires Dr. Keating
    to conduct inspection on Summit Bridge, a steel
    cantilever truss bridges similar in construction
    to I-35 Bridge.
  • March 2008 - A temporary clamp assembly followed
    by a permanent replacement should be installed at
    both bearings as soon as possible.
  • April 2008 - Corps begins design to award
    contract by the end of the fiscal year (September
    2008).

5
Temporary Clamp SystemMarch 26, 2008
6
Summit Bridge Critical Needs
  • North Anchor Span Anchor Pin Plate
  • Pin Plate is distorted and pushed toward edge of
    pin
  • Connection is Fracture Critical
  • Significant corrosion deterioration of various
    critical members and connections

7
Summit Bridge North Anchor Span Anchor Pin Plate
Pin should extend by ½ inch
8
Crevice corrosion pushes pin plateNO POSITIVE
CONNECTIONFRACTURE CRITICAL
9
Inside pin plate same condition
10
Critical Needs Contracts for 2009
  • 1. Summit Bridge Anchor Pin Plate
  • A. Temporary fix - complete
  • B. Permanent fix
  • - Notice To Proceed October 2008
  • - 7 Day Full Bridge Closure February 2009
  • 2. Summit Bridge Approach Roadway Replacement
    Phase II (Northbound lanes)
  • A. Notice To Proceed January 2009
  • B. Lane Restrictions April 2009
  • C. Completion - January 2010

11
QUESTIONS FROM THE BOARD?
  • Thank You for your time and understanding