Title: Xenon Detector Hardware
1Xenon Detector Hardware
2Outline
- Detector in 2008
- Operation in 2008
- Hardware Upgrade and Schedule
- Summary
3Detector
4PMTs installation
- All PMTs were taken away for check and
reinstalled in the cryostat - New LED on the outer side for better calib. of
inner PMTs - Wire alpha sources are at staggered positions
- Better PMT calibration
- Alpha sources (all) on walls were removed
25mm
31mm
5New LEDs
- Higher voltage with attenuation by coating LEDS
- Stable against instability of the input voltage
6Problem in 2007 Operation
Watarus Design Solution for 2007 run
Air
Metal body
Glass insulator
Xe
- Production procedure
- Fix pins in the holes and fill with silica
- Bake in argon atmosphere
- Cool down
No need to change connector Replacement can be
done quickly Body made of insulator (not metal)
7HV Feedthru Modification
- Test of new feedthru
- 1000 V applied on all pins (48x6x4 pins)
- One feedthru (48 pins) was tested at 1500V
- Successfully installed
Kyocera Ultra High Vacuum Feedthrough
New HV feedthru
8New LN2 feedthru Installation
- Pressure was slowly increasing under normal
operating condition in 2007 runs - 6 new LN2 feedthru have been installed
- Stainless steel pipes instead of Cu pipes
- Pipes are precisely and strongly centered in
order not to touch the wall - Bellows connection for the cooling pipes on the
covers - 30-40W reduction of heat load was achieved
- But still pressure is slowly increasing.
!!!!!!!!!!
- Refrigerator cooling power 200W
9Liquid circulation (Original Design)
Purifier Cartridge Molecular sieves, 13X 25g water
Freq. Inverter OMRON
- Circulate xenon in liquid phase
- Circulation pump
- 100liter/h_at_3175rpm, Dp 0.2MPa
- Molecular sieves
- gt24 g water absorption
- Used in 2007 run
PT
10Electronegative Impurity Removal(Update in 2008
Run)
- O2 getter cartridge
- Developed for LAr use at CERN
- Mounted at the exit MEG liquid-phase purifier
with by-pass valves
11Liquid-phase Purifier Modification
- New purifier cartridge to remove water
- Oxidization-reduction of Cu
- Outside of the purifier cryostat
- MS is replaced to new pellet
- Particle filter has been installed
12Modification of Splitter-DRS Connections/Cables
- GND line from splitter floating ? grounding on
DRS board - Copper tape black tape
DRS pedestal distribution before/after
modification
13NaI Electronics Update
9 amplifiers prepared, installed all on 17/Jun
and checked all signal before connecting
to splitter
inverting amp.and timing filter
charge amp. gn0261 (hiroshima-univ.)
replaced only amplifiers
rising time 97ns for fast trigger 225ns
(in 2007) -gt175ns
energy outputby new setup
output for trigger
97ns
- output for energy measurement is also faster than
that in 2007
APD
Light guide
175ns
500ns
DRS
14New Scintillation Counters
COBRA
NaI
- Used for time calibration of LXe
- Scintillator x 2
- 70mm x 70mm x 7.4mm
- Fine mesh PMT x 4
- Hamamatsu H6152-70
- Pb converter
15Operation
16Gas/liquid system
Gas-phase purifier
Gas line
Liquid line
High pressure Storage
Detector
1000L dewar
Liquid-phase purifier
17Scintillation Light Yield
- In 2007 operation, there was an energy scale
discrepancy btw alpha and gamma - Too small light yield from g events ( lt 1/2)
- Purity seemed to be good because we observed
- Improvement and plateau of light yield of both
gammas and alphas - but ltQ/Agtg / ltQ/Agta was found to be smaller
than expectation and LP data
2007 Data
18Waveforms (Shown in 2008 Review)
- ?triplet 22 ns
- ?recomb 45 ns
ta 21 ns
tg 34 ns
! Careful treatment of electronics time constant
is necessary
2007 Data
Before purification
Q/A
was 1.93/-0.02 in LP test
A
Q
Electronegative impurity? Oxygen??
19Scintillation Light in 2008 Run
- Rapid increase at the beginning thanks to the
liquid-phase purification - Removal of water/oxygen
- LN2 cooling was necessary to help limited cooling
power during purification - Increase (14) in summer by gaseous
purification, however this was not significant - Large increase (46!) in Oct-Dec after replacing
the diaphragm of the gas-circulating pump
2007
205 h 2/Dec
180 h 23/Nov
70 h 14/Nov
20Why did it change in such way?
- LN2 cooling pipe
- In the cryostat
- On the inner vessel wall and covers
- Diaphragm
- found to be broken in September
21LED Light as a Monitor
- It is found that our LED system has very good
stability. - Much more stable than our calibration precision
- We can monitor the stability by a number of PMTs.
22PMT Gain Shift
- Gain decrease in pi0 runs
- PMT gain shift was found with muon beam on ( 23
) - Time constant short and long
- CR peak during MEG run
- LED run with normal muon beam
- LED constant intensity with open/close beam
blocker
Beam on
Beam off
23Hamamatsu Investigation
Too much alkali ?????
24Yet Another Way to Monitor the Light
- (Cosmic ray)
- Am-Be alpha source
25Hardware Upgradeand Schedule
26Work during the shutdown
- PMT/Cryostat
- Open the downstream cryostat cover
- Visual inspection of the cryostat
- Take a few PMT to be sent back to Hamamatsu for
further investigation of gain change - Installation of a new chimney cover with steel
cooling pipe (previous one was made of Cu) - Replacement of the 1000L dewar heater
- Recovery of xenon to the storage in Feb
- Replacement of the heater and warm up frozen
xenon in Mar - Liquefaction in April
- Installation of new getter in March on the top of
the cryostat - Installation of new Liquid Pump/Purifier in April
- 1000 L/hour circulation expected
- No electric noise
27Liquid filling schedule
- Detector
- 6-19/April
- Evacuation
- 20-22/April
- pre-cooling
- 23-24/April
- cold gas alpha DAQ
- 25-26/April
- Liquid transfer
- 27/April-10/May
- Electronics test
- Purifier test
- 11/May-
- Purification and test
- 1000L dewar
- 26/Jan-27/Feb
- Recovery of xenon to the storage
- 2/Mar-6/Mar
- Recovery of the gas in the dewar
- 9/Mar-13/Mar
- Repair work of the heater
- 14/Mar-1/April
- Evacuation
- 2/April-22/April
- Liquefaction
- Complete removal of impurities
28Summary
- Successful running in 2008
- Remaining problems
- Scintillation light yield (30 less than LP data)
- Cooling power
- Hardware upgrade/repair
- New Getter purifier
- New liquid pump
- Replacement of the top chimney cover
- LN2 cooling pipe Cu ? Stainless Steel
- Replacement of the heater in the 1000L dewar
- PMT gain shift investigation is in progress by
Hamamatsu - Detector will be ready in the middle of May