Title: April 6, 2006
1Orleans Parish School Board Accounting, Human
Resources and Financial Management Plan and
Status Report 17
April 6, 2006
2Table of Contents
- Section Page
-
- Working Group Updates
- Financial Management Accounting 2
- Human Resources 5
- Procurement 8
- Information Technology 11
- Facilities Maintenance 19
- Dispute Analysis and Forensics 23
- Appendix A Detailed Workplans
- Schedule A - Financial Management
Accounting 29 - Schedule B - Human Resources
30 - Schedule C - Procurement 33
- Schedule D - Information Technology
34 - Schedule E Facilities Maintenance
36
3Financial Management Accounting
- Post Katrina Key Accomplishments
- Coordinated with insurance carriers to collect
claims for hurricane damages. To date, 34.4M has
been collected. - Community Disaster Loan application was approved
with potential monies of approximately 20M. - Monitored daily cash receipts and disbursement
transactions in each of the Districts bank
accounts. - Developed preliminary projections of school and
other operating expenses as well as anticipated
revenue streams from federal, state and local
governments. - Modified weekly cash flow forecasts for material
changes caused by the post-hurricane environment.
These cash flow forecasts indicate that, based
on current assumptions, the Districts general
fund will still have positive cash at the end of
fiscal year 06 under the assumption that the
District will not have to pay the approximate
68M of unemployment benefits to the Louisiana
Department of Labor until sometime in calendar
year 07. - Obtained bond counsel opinion supporting the use
of existing capital project funds to fund
liquidity needs for the school building repair
efforts. - Segregated pre-Katrina payables from post-Katrina
liabilities for go-forward accounting purposes. - Supported payroll team in processing pre-Katrina
payroll in an off-line system as a result of the
damage to the District information systems as
well as continued implementation of interim
payroll processing solution with ADP.
4Financial Management Accounting (cont.)
- Post Katrina Key Accomplishments (cont.)
- Payroll
- Completed and transmitted over 10,000 Form W2s.
- Completed and transmitted approximately 600 Form
1099s. - Updated over 7,000 employee addresses.
- Addressed over 4,000 calls to our call center,
with issues ranging from multiple address
changes, benefits and retirement questions, to
payroll issues. - Developed and implemented a system of metrics to
use in identifying root causes and action items
for use with our call center operations. - Developing the ability to manage the payroll tax
function within the payroll department rather
than in the finance department. - Developing core competency within the payroll
department to handle retirement reporting. This
function is typically handled by the
retirement/benefits department. - Assisted the finance/accounting department in
closing long standing, open, and un-reconciled
issues. - Beginning the transition from ADP to the Munis
payroll system. - Developing, and constantly revising payroll
department quality and internal controls. - Prepared, and are constantly updating the
upcoming vacation/sick payout process. The
payment and distribution process is settled and
ready to go. - With the assistance of the LLA, we have
identified approximately 300 employees with
questionable stipend and assault pay issues,
which amounts will be offset against the
vacation/sick payouts. - Developing processes to go after potential
payroll, stipend, and assault pay overpayments.
5Financial Management Accounting (cont.)
- Key Deliverables to be Accomplished
- Design, implement and permanently staff a
scalable accounting/ finance department for a
reconstituted OPSB system by December 2006. - Design a Treasury/Cash Management system that
incorporates necessary controls to provide
timely and reliable reporting capabilities. - Create a Special Revenue department with
capabilities to develop, budget and timely
process reimbursement claims while complying with
all federal and state regulations. - Complete the termination process for all former
employees including process final payout of
sick/ vacation pay, prepare final W-2s and
reconcile all associated withholdings. - Identify and record all unrecorded liabilities,
compile and validate a complete accounts payable
listing and process all valid claims for payment. - Design and implement Tyler/ MUNIS as a scalable
and reliable financial reporting systems. -
- Develop alternatives to move toward a more
optimal debt structure for the District,
including potential refinancing/refunding options
on 250M of existing indebtedness. Conclude a
successful refinancing of all outstanding bond
obligations. - Obtain/recover all available funds from insurance
policies, Community Disaster Loan and other
Federal Assistance. Complete validation and
subsequent repayment of all outstanding
pre-Katrina liabilities, including
employee-related and vendor claims.
6Human Resources
- Post Katrina Key Accomplishments
- General Employee Communications and HR Operations
- Managed Call Center and HR related content on the
NOPS Website to include updating call center
scripts, FAQs, and responding to employees
questions and requests. - Responded to walk-ins and processed employment
verification requests, resignations, retirements,
mortgage/auto loan requests, payroll questions,
student records requests, benefits requests, etc.
- Processing verifications of unemployment
eligibility for the DOL. - Continue to approve/disapprove and process
administrative employees brought back from
disaster leave. Compile and maintain list of
all employees/salaries (administration
school-based). - Finalizing analysis and audit of final vacation
payouts for terminated employees less any
offsets. Researching stipend offsets
payments over 5,000 prior to any payment. - Executing on capacity building strategy, to
include - Identified skill gaps and human capital needs
- Drafting descriptions for identified position
needs - Interviewed candidates for accounting/payroll
functions, checked references, conducted
compensation market analysis. - Developed recruiting status matrix (See
Attachment). - Processed transferred sick balances to other
School districts upon employees request.
Transferred out and reduced OPSBs sick leave
liability by over 46,000 hours. - Updated preliminary 2006 2007 OPSB organization
charts and employee roll-off dates (See
Attachment). - Beginning implementation of Tyler-Munis
HR/Payroll module. - Contacted and hired permanent temporary at
will employees, as required. - Supporting finance with the preliminary
development of a 2006-2007 budget for
administration and school-based employees. - Continue to supporting school-based staffing
needs. - Continue to support finance cash flow forecasts
(i.e., payroll costs, benefit expenses,
unemployment benefit projections, workers
compensation costs, sick/vacation balances).
7Human Resources (cont.)
- Post Katrina Key Accomplishments
- Retirement/Benefits
- Began drafting healthcare RFP.
- Continued to administer the Self-Insured
Healthcare plan. Auditing account for claims
paid through March 29, 2006. - Completed the transfer of data to the COBRA and
Retiree direct billing vendor. COBRA elections
and notifications, as well as Retiree invoices
will by mailed to participants by March 31, 2006. - Reviewing Coventry invoice for claims prior to
the February 1st self-funded plan, including the
reconciliation of the December January COBRA
participants to the payments received by FBMC. - Received and recorded payments received in the
OPSB Healthcare P.O. Box from Retirees and
COBRA participants for February. Also recorded
cancellation notices from Retirees who are
switching from the district plan to another
provider. - Finalized the mediated Settlement Agreement with
Coventry regarding increased Retiree monthly
premiums. - Provided updated census information to the
Dental, Life and Vision providers for valuation
purposes. - Responded to requests for information from
various state agencies (TRSL, LSERS, LDI, etc.) - Approved the release of payments for March
Workers Compensation payments and the 1st Quarter
Retiree Life Insurance Payments. - Developed cost analysis to move OPSB retirees to
the Office of Group Benefits state plan (see
Attachment).
8Human Resources (cont.)
- Key Deliverables to be Accomplished / Next two
weeks - General Employee Communications and HR Operations
- Continue to oversee OPSB in-house call center
website to include updating call center scripts
and website FAQs and responding to researching
employees questions and requests. - Continue to respond to walk-ins and process OPSB
employment verification requests, resignations,
retirements, mortgage/auto loan requests, payroll
questions, student records requests, benefits
requests, etc. - Continue to process verifications of unemployment
eligibility for the DOL - Continue to audit and verify stipend
overpayments prior to any distribution. - Update 2006-07 organizational charts and the plan
for the estimated release dates for OPSB
employees. - Capacity Building Continue to develop job
descriptions, source, screen and interview
candidates to fill capacity gaps. - Continue to approved/disapprove and process
employees brought back from disaster leave. - Continue to process and transfer sick leave hours
upon employees request. - Finalize review and update of HR policies and
practices. - Provide finance with HR expenses to include
health insurance claims paid for last two years,
a SAS 70 report on the internal controls of the
TPA, and preparing a schedule of all employer
retirement contributions by month for all plans. - Finalize PIP payment reports (OPSB Type 4
Charters). - Finalize HR reports for financial Audit including
retirement and benefit information. - Continue to provide staffing support and
employment processing to schools and central
administration. - Continue to coordinate donor relation activities
and distribution of donated items. - Continue to support the budgeting process (i.e.,
headcount, payroll/benefit costs) - Retirement/Benefits
- Finalize and post/disseminate healthcare RFP.
9Procurement
- Post Katrina Key Accomplishments
- Arranged/Coordinated tours of the Council for the
Great City Schools at various school
facility/properties. - Worked with Facilities to properly procure
emergency repairs on nearly all NOPS schools. - Developed and maintained an interim, manual,
non-Oracle based Requisition and Purchasing
process. - Drafted, distributed, received and awarded RFPs
related to the following services - General Contracting Parsons
- Environmental Parsons
- HVAC Johnson Controls
- Custodial and Grounds Sodexho
- Assisted the IT department in the recovery of IT
assets from 3510 General DeGualle. - Assisted in the drafting and distribution of RFPs
for Transportation Services. - Assisted in the drafting and distribution of RFPs
for Food Services. - Assisted in the drafting and distribution of an
RFP for Security Services. - Assisted in the drafting and distribution of a
bid package for the sale of land. - Assisted in the drafting and distribution of an
RFP for an E-rate Service Provider - Discussed proposals related to waste/trash
removal and pest control with a few vendors. - Maintained interim contract management system.
10Procurement (cont.)
- Post Katrina Key Accomplishments (cont.)
- Worked with Real Estate group to procure services
and coordinate moves from Henderson Elementary to
McDonogh 7, then from McDonogh 7 to Arthur Ashe
Elementary. - Work with OPSB General Counsel to terminate
copier/printer leases with Xerox. Replaced with
Imagistics copier/printer leases to support NOPS
sites (Franklin Elementary, McMain H.S., McDonogh
35, Ashe, Bauduit) pursuant to state contract
rates. Agreement runs through June 30, 2006 at
which point it will be up to OPSB discretion to
renew or put out to public bid. - Installed agreement with Allied Waste to provide
waste removal services at current NOPS sites
(Franklin Elementary, McMain H.S., McDonogh 35,
Ashe, Bauduit). Agreement runs through end of
March, 2006. RFP for waste removal services
advertised and distributed on February 14, 2006. - Released, per Emergency Procurement guidelines,
RFPs for the repair and reconstruction of Bauduit
Elementary, Gaudet Elementary (RSD), Ashe
Elementary. - Released, per States Public Bid Policy, RFP for
the repair and reconstruction of Easton Senior
High School on February 17, 2006. - Preparing bid packages for Hynes Elementary as
well as other schools identified by the RSD to
open in August, 2006. - Attended the Mayors Contractor Seminar on
February 22, 2005 at the Convention Center,
whereby we made contact with over 100 local and
regional construction firms. We handed out
nearly 100 copies of the Easton RFP and informed
contractors on how they may obtain information in
the future on upcoming RFPs.
11Procurement (cont.)
- Key Deliverables to be Accomplished
- Continue to exercise joint authority with OPSB,
requiring written concurrence of both parties in
matters of procurement, execution, amendment and
termination of contracts. - Design and develop District procurement policies
and procedures - Ensure consistency with state, local and federal
laws and regulations. - Incorporate best practices from LDE, other
districts, other states. - Codify processes and procedures including a
written code of conduct for employees involved in
purchasing and contracting on behalf of the
District. - Codify areas of authority, delegation and ensure
actions require proper authorization. - Work on all the above in concert with MUNIS
implementation - Design and develop District policies and
procedures involving the bidding process from
informal bids (i.e. price verifications) to
formal Request-for-Proposals. - Design and develop the District Contract
Administration function. - Continued support of Real Estate Group with RFP
process for construction projects.
12 Information Technology
- Post Katrina Key Accomplishments
- Oracle Operations
- Submitted 2005 W2/1099 Electronic transmittal to
IRS and SSA using Oracle System - Submitted 2005 W2 Employer File successfully
uploaded to the SS Administration - 2005 LA L2 were successfully transmitted to the
Department of Revenue State of Louisiana - Prepared for master file update and termination
of 7500 employees in Oracle System for audit and
control purposes - Developed final scripts and completed data
extract of employees from Oracle System for final
termination Vacation/Sick payout file to ADP for
processing and payment - Continued contract revisions with Oracle to
implement reduction of monthly Oracle On-Demand
contract by an estimated 20 - Continued to manage production related business
requests and issues related to Oracle LINUX
conversion - Continued to revise and execute Oracle to MUNIS
Transition plan and key milestones, including
access to historical data - Tyler MUNIS Enterprise K-12 Design /
Implementation project GL, AP, Procurement,
Grants, and Budgeting - Finalized Finance roles responsibilities for
NOPS - Completed additional training needs for key users
in General Ledger, Accounts Payable, Purchasing
and Requisitions applications - Conducted successful systems test for GL, AP,
Procurement and Requisitions - Went Live on MUNIS GL, AP, Procurement and
Requisitions 4/3 -
13 Information Technology (cont.)
- Post Katrina Key Accomplishments (cont.)
- Tyler MUNIS Enterprise K-12 Design /
Implementation project Human Resources and
Payroll - Delayed implementation of Phase 1 MUNIS
Financials from 2/1 to 4/01, has delayed Phase 2
of HR/Payroll systems implementation from April
to May, 06 - Completed visit with NOPS HR/Payroll/IT
representatives to MUNIS development center in
Portland, Maine, to expedite design and
configuration of sub-systems - Continued to design and configure key HR and
Payroll business processes for MUNIS
implementation - Continued to define MUNIS security requirements
to determine which employees, deductions, pay
types and tables each user has access to view or
modify - Continued to finalized enhanced business process
outsourcing services with ADP, specifically
focused on - Check Printing and Distribution
- W2 Printing and Distribution
- Tax Reporting and Filing
- Garnishment Processing
- Help Desk / PC Support RFP
- Continued to initiate Help Desk / PC support
outsourcing end user capability - Completed communication plan and process
definition for the outsourced PC Support Help
Desk capability - Continued to build NOPS IT customer service
capacity
14 Information Technology (cont.)
- Post Katrina Key Accomplishments (cont.)
- IT Shared Services capability
- Continued to meet with each school to finalize IT
costs and budgeting - Issued final IT Shared Service center Endeavor
Agreements to Charter and RSD schools - Continued to support on-going IT operations
- Continued to build NOPS IT business capacity
- Issued first quarter invoices to customers
- Data Center Operations
- Continued to expand Microsoft Exchange email
service to specific charter schools requesting
NOPS K12 email accounts - Continued to implement VOIP telephone capability
at schools along with upgrades to the Cox Centrex
system - Continued to document NOPS data center assets at
Cox facility to support disaster recovery
planning - Implemented initial off-site storage rotation
with Iron Mountain - Summarize redundancy options
- Student Information Systems
- Continued to conduct on-site SASI training and
operations support for all charter and NOPS
schools in Orleans Parish, including SIS, Master
Schedule, and Grading. Recovery schools have
elected not to use SASI. - Implemented the technical support and training
calendar for SASI technical software support - Begin enrollment of RSD schools opening April 17,
2006 - E-Rate Filing and Management
15 Information Technology (cont.)
- Post Katrina Key Accomplishments (cont.)
- E-Rate Filing and Management
- Continued to follow up with the SLD on the status
of the Year 8 (2005/2006) selective review until
funding is approved - Prepare for E-Rate services and support RFP
- IT Asset Inventory
- Evaluated the potential storage facility for the
transfer of valuable IT assets - Completed Best Buy PC deployment for media event
in March
16 Information Technology (cont.)
- Key Activities to be Accomplished
- Oracle Operations
- Complete termination of 7500 employees in Oracle
System for audit and control purposes - Send final termination Vacation/Sick payout file
to ADP for processing and payment - Continue contract revisions with Oracle to
implement reduction of monthly Oracle On-Demand
contract by an estimated 20 - Continue to manage production related business
requests and issues related to Oracle LINUX
conversion - Continue to revise and execute Oracle to MUNIS
Transition plan and key milestones, including
access to historical data - Tyler MUNIS Enterprise K-12 Design /
Implementation project GL, AP, Procurement,
Grants, and Budgeting - Continue to monitor and train NOPS Finance and
Accounting capacity building for Tyler MUNIS
operations - Configure test Budget Grants applications
- Complete user procedures for budget set up,
grants set up closing the books - Define additional reports as needed
- Finalize the design framework of the combined AFR
and budget reporting for NOPS, Algiers and the
other charter schools with the LDE LLA
17 Information Technology (cont.)
- Key Activities to be Accomplished (cont.)
- Tyler MUNIS Enterprise K-12 Design /
Implementation project Human Resources and
Payroll - Continue design, definition and configuration of
key HR business processes for MUNIS design - Continue definition of MUNIS security
requirements to determine which employees,
deductions, pay types and tables each user has
access to view or modify - Continue design, definition and configuration of
key ADP business process outsourcing services - Continue to refine enhanced business process
outsourcing services from ADP
18 Information Technology (cont.)
- Key Activities to be Accomplished (cont.)
- Help Desk / PC Support RFP
- Fully deploy the Help Desk / PC support
outsourcing end user capability - Continue to build NOPS IT customer service
capacity - IT Shared Services capability
- Finalize the IT Shared Service Center Endeavor
Agreements to Charter and RSD schools - Continue to support on-going IT operations
- Continue to build NOPS IT business capacity
- Issue first quarter invoices to customers
- Data Center Operations
- Continue to expand Microsoft Exchange email
service to specific charter schools requesting
NOPS K12 email accounts - Continue to implement VOIP telephone capability
at schools along with upgrades to the Cox Centrex
system - Continue to document NOPS data center assets at
Cox facility to support disaster recovery
planning - Implement initial off-site storage rotation with
Iron Mountain - Begin requirements discussion for
server/application co-location that will support
disaster recovery procedures. - Student Information Systems
- Continue to conduct on-site SASI training and
operations support for all charter and NOPS
schools in Orleans Parish, including SIS, Master
Schedule, and Grading. Recovery schools have
elected not to use SASI. - Implement the technical support and training
calendar for SASI technical software support
19 Information Technology (cont.)
- Key Activities to be Accomplished (cont.)
- IT Asset Inventory
- Maintain PC distribution processes and school
site surveys - Execute storage facility agreement for 2006
- E-Rate Filing and Management
- Continue to follow up with the SLD on the status
of the Year 8 (2005/2006) selective review until
funding is approved - Prepare for E-Rate services and support RFP
20 Facilities Maintenance
- Key Accomplishments
- McMain
- Performed walk-through with new general
contractor foreman. Installed doors and window in
kitchen office. Re-installed warmers, ovens and
sinks into McMain kitchen. Completed scraping and
painting of kitchen area. Began installation of
18 external doors. Performed walk-through of
facility with Principal Frick. - Banneker
- Handed over keys to Recovery School District on
Monday, March 20th. Continued to make repairs,
including Installation of tile in the cafeteria,
East and West stairwell, room 313, teachers
lounge and 2nd and 3rd floor foyers. Repairing 2
lights on the outside of building. Installation
of new curtain wall in West stairwell. Demolition
and removal of walk-in freezer and 3 reach-in
refrigerators. Performed pre-fire marshal
walk-through review on Monday, March 20th.
Outstanding items addressed prior to final fire
marshal review, including 3 exit signs and
install of 6 fire rated doors. Registration began
at the school on March 29th. - Lusher
- Developed plan for performing permanent roof
repairs, including repairing clay tiles,
replacing gutters and downspouts, covering up
temporary vent repairs and installing roof
hatches. Plan was communicated to Principal.
Work began on Sunday, March 26th and will
continue through April 12th (dependent on weather
conditions). Provided FEMA PO with detailed
documentation to support reimbursement. - Ben Franklin Elementary
- Repaired roof issue over room 319 over the
weekend (March 18th and 19th) to address problem
prior to LEAP testing, which began on Monday,
March 20th. Repaired schoolyard fence. All
outstanding punch list items have been addressed.
Although original air quality testing was
negative, we followed the recommendations of the
environmental company to scrape and further dry a
wall in room 106. Addressed air conditioning
issues associated with condensation build-up on
pipes. - Capdau
- Completed all punch list repairs at Capdau with
the exception of some tile issues. Met with
moisture consultant to better understand root
cause of popping tile. Performed walk-through
of Capdau with FEMA project officers on March
27th. - Fischer
- Opened the school on Thursday March 30th for the
Algiers Charter. - McDonogh 15
- Released RFP for hurricane related repairs. Bids
are due on April 20. - Lafayette
- Continuing with damage assessment.
21 Facilities Maintenance (cont.)
- Key Accomplishments
- Booker T. Washington
- Damage assessment is scheduled to be complete on
April 14, 2006. - Gentilly Terrace
- Damage assessment is complete with the exception
of eleven rooms that were inaccessible. Damage
assessment of those eleven rooms is scheduled to
be complete on March 31, 2006. - Martin Luther King
- Damage assessment is continuing and scheduled to
be complete on April 5, 2006. - Benjamin Franklin High School
- Continue to make progress on first floor
restoration. Case goods orders are being placed
including lockers and built-in cabinetry. Roof
repairs to the gymnasium and auditorium complexes
are near completion. Gymnasium floor delivery is
on schedule and will arrive on April 17. Floor
preparations will commence a week prior to
delivery. Preparations are being made to scrape
and biocide paint Auditorium ceiling. Mechanical
equipment (air handlers, water tank) on order. - McDonogh 35 High School
- Continue to make progress on first floor
restoration. First floor lockers and door order
being placed. GC punch list / close out plan to
be developed on March 30. - Wicker
- Continue to make progress of general restoration.
Structural assessment received awaiting
contractor bids to address structural deficiency. - Tureaud
- Progress continues for a April 10th opening
(faculty only) general occupancy to be on April
17th per the States request. Mold abatement
complete included scraping and biocide painting.
Interior painting to commence week of April 3rd.
Electricity has been restored. Fire Marshal
walkthrough pending. - Craig
- Progress continues for April 10th occupancy
(faculty) and general occupancy on April 17th.
Floor tile replacement complete. Roof access area
and roof compromise being remediated. Fire
Marshal has approved the school for occupancy. - Clark
- NOPS Board resolved to let contract on an
emergency basis. GC award pending. School being
prepared for an April 17 general occupancy.
22 Facilities Maintenance (cont.)
- Key Accomplishments
- Warren Easton
- GC awarded to Construction Masters. Project
kick-off pending. Debris Removal (White Goods)
LVI Debris Removal progress continues. - Fortier
- Remediation and general construction continue.
Continued discussions with Lusher charter on
additional renovation plans. - Johnson and Nelson
- Detailed assessment completed and will be ready
to go out for RFP on April 5. - Frances Gaudet Elementary School
- Environmental remediation completed. Floor tile
has been removed. Debris has been removed from
the front of the school. Ceiling tile has been
removed. Temporary power has been provided for
the opening of the school. Met with Entergy and
OPSB facilities personnel to discuss the options
for establishing permanent power. Fire Marshal
inspection at Frances Gaudet Elementary is
scheduled for Friday March 31, 2006 at 1000
scheduled to open on April 3, 2006. Floor tile
will arrive Monday and will be installed after
school early next week. Fences to be repaired and
pool is to be cleaned. - Sarah T. Reed Senior High
- Completed detailed assessment. Awaiting
reassignment of a FEMA PO to Reed High School. - Village de Lest
- Completed detailed assessment.
- Various
- Performed kitchen equipment assessments at Sophie
B. Wright, McMain, Capdau, Green and Audobon. - Performed walk-through of Green with new FEMA
project officer on March 27th. - Continued repairs on all West Bank schools.
- Debris Removal progress continues for white
goods. - Corp of Engineers continues to progress on
external debris removal.
23 Facilities Maintenance
Facilities Maintenance (cont.)
- Key Deliverables to be Accomplished
- Perform Real Estate Construction and Repairs -
CM/PM - Complete building assessments for 124 schools
- Create RFPs, review bids, and award the winning
bid - Monitor the progress of GC, Environ, HVAC, and
Janitorial - Work with FEMA and DAF on Scope of Repairs
- Develop a school readiness checklist to be used
for each school - FEMA project work sheets, building assessments,
and cost estimates - OPSB School Openings - FM
- Develop custodial, grounds, and maintenance
contracts - Obtain and maintain all facilities maintenance
programs - NOPS Master Planning Strategic Planning
- Master planning, community Development
- RF AE firms, manage process
- Surplus property transaction program
- Create process program to identify and sell
surplus land
24 Dispute Analysis and Forensics
- Key Accomplishments
- Continued to compile supporting documentation for
property files - Created master list of properties that lists
acquisition values, carrying values, and damage
caused due to Katrina for each OPSB owned
property. - Created list of surplus properties which will be
eligible for sale in the coming months.
Initiated research to determine any leases
involving surplus properties. - Compiled complete documentation on 42 of 140 OPSB
owned properties. - Continued historical cost property valuations.
- Advanced insurance claims and inventory process
- UBS (Insurance Adjusters) has assessed 140
facilities. - AAA (Capital Asset Valuation) has inventoried 93
facilities and has produced 8 asset reports. - Eighteen asset reports will be delivered by AAA
on 3-31-06. - Stoner (Wind damage contents) has assessed 25
wind damaged properties. - Continued to meet with FEMA and provide
documentation to build Project Worksheets - Confirmed Project Worksheets for approximately
4.8 million in reimbursements to date. Pressed
FEMA to complete Project Worksheets on 22.2
million in construction costs in which FEMA has
all necessary documentation, but OPSB has
received no Project Worksheet. - Worked with building contractors to reconcile
contractor bidding/invoicing with FEMAs
bidding/invoicing requirements to ensure maximum
reimbursement for eligible reconstruction costs.
Worked extensively with Parsons Construction and
Satterfield Pontikes Construction to recreate
invoice detail ensuring FEMA reimbursement for
eligible construction costs. - Compiled, created, and refined school
reconstruction (temporary and permanent repairs
caused by Hurricane Katrina) documentation for
submittal to FEMA.
25 Dispute Analysis and Forensics (cont.)
- Key Accomplishments (cont.)
- Advanced divesture of vehicles and managed
vehicle inventory - Accepting bids from firms interested in acquiring
the flood damaged vehicles located at the
Almonaster (Central Services) facility. - Filed police reports for vehicles which have been
stolen from OPSB facilities. - Obtained all titles on vehicles owned and leased
by OPSB. - Converting all titles from original to salvage.
- Auctioning buses on EBAY.
- Collected additional 2 million in insurance
proceeds. - Advanced flood insurance collections
- Facilitated the collection of 5.5 million.
- Expecting receipt of an additional 7.7 million.
26 Dispute Analysis and Forensics (cont.)
- Key Deliverables to be Accomplished
- Property
- Investigate ownership of 150 properties with the
Office of Conveyance - Document titles to those properties in which we
have ownership - Research all Section 16 lands owned by District
and royalty entitlements - Work with Real Estate in divesting of unnecessary
properties - Ensure all FEMA PW worksheets are complete for
properties owned - Work with Real Estate to declare certain
properties for Alternative use for FEMA per
direction of State and Board of Education - Vehicles
- Establish number of vehicles owned, vin numbers
and locations - Document ownership of vehicles
- Determine which vehicles are damaged and which
are salvageable - Find Titles and assign to inventory
- Make recommendation for divestiture of vehicles
- Identify those vehicles missing and file police
reports - Negotiate with Insurance Carriers for payment
- Ensure all FEMA PW worksheets are complete for
vehicles owned and damaged - Asset Inventory
- Perform assessment of each District property and
take detailed inventory of all assets
27 Dispute Analysis and Forensics (cont.)
- Key Deliverables to be Accomplished
- Contents FEMA claim
- Perform assessment of cost to repair/replace
contents of each District building. - File Documents for Project Worksheets for FEMA
- Fixed Assets
- Obtain and analyze a check register for the past
four years - Recreate asset list based on check register
- Reconcile with inventory
- File Documents for Project Worksheets for FEMA
- Temporary Classrooms
- Coordinate placement of classrooms
- Coordinate FFE for temp classrooms
- File Documents for Project Worksheets for FEMA
28 Dispute Analysis and Forensics (cont.)
- Key Deliverables to be Accomplished
- FEMA Documentation
- Manage all document request for FEMA and prepare
documentation for OIG audit - File, document and classify all FEMA Project
Worksheets and documentation - Utilize FTP site to streamline submission process
- Loss Payees
- Determine contractual obligations to loss payees
- Coordinate with Loss Payees to retrieve equipment
per contractual obligations - Negotiate and recommend settlements with Loss
Payees - Insurance Company Claims
- Prepare Proof of Loss for Insurance Companies
- Coordinate inspections for all insurance
adjusters and their representatives - Negotiate claim, manage claim efforts and
document all repair work in compliance with the
insurance claim - Expert witness testimony in the event litigation
becomes necessary - Cash Reconciliation and Overall Recordkeeping
- Prepare documentation to support inflows and
outflows of cash - Prepare reports for State and Board of Education
documenting uses of funds - Maintain data repository
29Appendix
30Schedule A Financial Management Accounting
31Schedule B Human Resources
32Schedule B Human Resources (cont.)
33Schedule B Human Resources (cont.)
34Schedule C Procurement
35Schedule D - Information Technology
36Schedule D - Information Technology (cont.)
37Schedule E - Facilities Maintenance