Title: LAWN DEPOT, INC.
1LAWN DEPOT, INC.
- Establishing the Optimal Capital Budget
- Paige Baccus
- Arif Hussain
- Ari Kempler
- Rupetrus Musamuli
2OVERVIEW
- Background
- WACC / MCC
- IRR / IOS
- MIRR
- SML / CAPM
- Risk Adjustment
3BACKGROUND / HISTORY
- National Retail Outlet Specializing in Garden
Supplies and Equipment
- Family Owned and taken Public in 1983
- Future of Company relies on proper analysis of
capital investment decisions
4Cost of Capital Components
All figures are based on market values
ITEM VALUE WEIGHT
Short-term debt 50,000,000 5
Mortgage bonds 283,465,550 30
Preferred Stock 145,000,000 15
Common Equity 480,000,000 50
TOTAL 958,465,550 100
5Weighted Average Cost of Capital
WACCRE KdWd (1-t) KpsWps KreWre KsdWsd
(1-t) .3.08(.6) .15.09 .5.166 .
05.07(.6) 11.3 WACCCS .3.125(.6) .
15.09 .5.191 .05.07(.6) 13.6
6BREAK P0INT ANALYSIS
- Exhaustation of internal funds forces the firm
to seek external capital.
- Flotation costs and effects of market
pressures.
- Cost of retained earnings is less than the cost
of issuing new equity.
- Break point analysis Re x b/ Equity Fraction
- .4(80,000)/ 0.5
- 64,000 non-cash exp.
- 64,000,000 60,000,000(depr)
- 124,000,000
7MCC Schedule
13.5
11.4
0
124
Dollars in millions
8ESTIMATED IRRs NPVs FOR PROJECTS
Project Initial Cost Cash Inflows Life
IRR NPV A 30.0
6.26 12yrs 18 9.8
A 30.0 7.81
8 20 9.62 B 160.0
27.36 15 15 N/A
9IOS Schedule
20
18
15
30
60
90
120
150
180
210
240
Dollars in millions
10MCC VS IOS
- MCC determined by WACC
- WACC found under relative certainty
- Therefore, MCC schedule has high degree of
certainty
- IOS assumes cash flows under uncertainty
- IOS schedule will be less certain then MCC
schedule
11MCC Schedule and IOS Schedule
20
17
IOS
14
MCC
11
50 100 150 200 250
Dollars in millions
12ACCEPT/REJECT DECISIONS
- All projects IRR are higher than WACC so accept
all
- A and A are mutually exculsive
- The IRRs of both projects exceed the cost of
capital
- NPVAA is greater than the NPVAA
- Conflicts between IRR and NPV of the projects
- Accept A, because NPV is higher
- Accept B, because IRR is above WACC
13TAKING RISK INTO ACCOUNT
- Riskiness of projects absent from analysis
- In real world, must account for risk
- Two main methods to account for risk
- 1. Adjust firms cost of capital up or down to
account for differential risk
- 2. Lower IRRs of riskier projects and raise
IRRs of less risky projects
14MIRR ANALYSIS
- IOS developed using IRR
- IRR assumes cash flows reinvested at IRR rate
- Using MIRR to determine IOS schedule will cause
downward shift of IOS schedule
- Reason for downward shift is lower discount
rate, or WACC, inherent in MIRR
15MIRR EFFECT
- Example, Project A IRR 20 vs. MIRR
14.55
- Project B has an IRR of 15
- Project B is barely above the MCC schedule or
WACC of 13.6
- Under MIRR analysis, Project B would probably
not be accepted
- Conclusion, projects accepted under IRR not
necessarily accepted under MIRR
16SML EQUATION
- All the figures were provided by Ibbotson
- Associates.
- KS KRF (KM - KRF)b
- 6 (12 - 6) 1.4
- 14.4
17BEST ESTIMATE
- Cost of Equity used in WACC found using DCF
(16.6)
- By using CAPM, Cost of Equity is 14.4
- Which method is superior?
- Company has only been public for 10 years, the
Beta
estimate is probably innacurate
- Beta more accurate for longer periods of time,
converges toward 1
- The company probably in specific growth stage