Title: Urban Impaired Stream Standard


1
Urban Impaired Stream Standard
  • Project cannot cause or contribute to an
    impairment of a waterbody
  • Standard BMPs dont get 100 removal
  • Impaired Stream Standard provides a means for
    mitigation.

2
Urban Impaired Stream Standard
  • Projects with 3 acres of impervious area
    located within the direct watershed of an urban
    impaired stream must meet the standard
  • Chapter 502 identifies 32 urban impaired streams

3
Urban Impaired Stream Watershed Maps
http//www.maine.gov/dep/blwq/docstand/stormwater/
stream_map_1.htm
S. Portland West S. Portland East
Portland
4
Urban Impaired Stream Standard
  • Projects must either
  • Pay a compensation fee
  • or
  • Treat, reduce or eliminate an off-site or on-site
    pre-development stormwater source

5
Urban Impaired Stream Standard
  • Exceptions
  • Disturbed areas neither impervious or landscaped
  • Redevelopment of equivalent use

6
Urban Impaired Stream Standard
Fees for partial acreage are prorated
7
Urban Impaired Stream Standard
  • Example
  • 3 acres parking, 1 acre roof, 2 acres lawn
  • Required compensation fee calcualtion
  • Fee (3 X 5000) (1 X 2000) (2 X 1000)
  • Fee 19,000
  • Reqired credit calcualtion
  • Credits (3 X 0.5) (1 X 0.2) (2 X 0.1)
  • Credits 1.9

8
Urban Impaired Stream Standard
9
Urban Impaired Stream Standard
  • Example 3acre