Dumpsbook CMRP Dumps
2Things You Learn About SMRP?
3What is SMRP?
SMRP knows the difference a globally-recognized
certification can make for professionals in their
development and career path. For over 10 years,
SMRP and its certification organization, SMRPCO,
have offered world-leading certification programs
for maintenance, reliability and physical asset
management professionals. These certification
programs provide a unique skill set by going
beyond textbook knowledge and testing real-world
experiences and abilities.
Content by Wikipedia.org
https//www.dumpsbook.com/Exam/CMRP
4Your No.1 Choice to Prepare and Pass the CMRP
Exam in the first Attempt by Dumpsbook CMRP Dumps.
Visit Us
5Get SMRP CMRP Exam Dumps With Latest Exam
Questions Answers
By
https//www.dumpsbook.com/Exam/CMRP
6Here Are Some Questions
7Question No 1
Return on Assets (ROA) is determined by A. Net
income/Total assets B. Gross income/Total
assets C. Revenue/Total assets D. Net
income/Maintenance costs Answer C
https//www.dumpsbook.com/Exam/CMRP
8Question No 2
As the maintenance manager at a new plant
(facility) you are developing the maintenance
workforce strategy for start-up. Select the best
workforce attributes for maximum effectiveness,
assuming that unit labor costs are equal A. An
annual bid and selection of a maintenance labor
contractor is performed, using unitcosting of
tasks normally required. B. A managing contractor
is brought on site to handle all aspects and
provision of maintenance labor. C. Multi skilled
mechanical crafts (trades) and instrument
electrical crafts (trades) are hired and
developed. D. Operations performing minor
maintenance and company multi-skilled technicians
performing complex maintenance tasks. Answer D
https//www.dumpsbook.com/Exam/CMRP
https//www.dumpsbook.com/Exam/CMRP
9Question No 3
Which of the following are leading tools or
techniques to identify Maintenance and
Reliability process improvements? 1. Total
Productive Maintenance 2. Reliability Centered
Maintenance 3. Historical analysis of spending
patterns 4. Process benchmarking with industry
leaders A. 2, 3, 4 B. 1, 3, 4 C. 1, 2, 4 D. 1,
2, 3 Answer C
https//www.dumpsbook.com/Exam/CMRP
10Question No 4
For the oil in a pressurized lubrication system,
oil samples for analysis and trending should be
taken from A. The center of flowing oil line
upstream of the oil filter, to assure that the
sample is representative of the oil leaving the
lubricated components. B. The center of a flowing
oil line downstream of the oil filter, to assure
that the sample is representative of the oil
being supplied to the lubricated components. C. A
low point in the oil sump, to assure that the
sample includes wear particles, water, and other
contaminants that may have settled out of the
oil. D. The oil sump at a point above the bottom,
to assure that the sample does not include wear
particles, water, and other contaminants that may
have settled out of the oil. Answer D
https//www.dumpsbook.com/Exam/CMRP
11Question No 5
What are the three most significant constraints
when developing a Maintenance and
Reliability-organization? A. Engineering/Human/Res
ources/Budget B. Budget/Operations/People C.
Culture/People/Resources D. Culture/Engineering/Bu
dget Answer C
https//www.dumpsbook.com/Exam/CMRP
12Question No 6
The 'Karl Fischer Method' measures A. The count
in parts per million (ppm), of coliform bacteria
in a sample of cooling tower water. B. The
viscosity of an oil sample based on its flow rate
through a calibrated orifice. C. The conductivity
in micro-ohms, of a sample of cooling tower
water. D. The amount of water in a sample of oil,
in ppm. Answer D
https//www.dumpsbook.com/Exam/CMRP
13Question No 7
When developing and presenting a new strategic
plan to stakeholders, which of the following is
the most important? A. Implementation
timetable B. Gaining the trust of stakeholders C.
Craft (trade) flexibility D. Establishment of a
common goal Answer B
https//www.dumpsbook.com/Exam/CMRP
14Question No 8
On Monday, the maintenance manager sent an e-mail
memo to the production manager saying that the
date and time of the next planned outage would be
on the third shift of the coming Friday. When the
maintenance manager arrived at the unit on Friday
third shift, the equipment was still operating at
full capacity. The operator said he knew nothing
of a planned outage and he had to make up
production on this shift. Which of the following
is the most likely reason the equipment was still
running? A. The maintenance manager did not know
if the production manager had communicated the
plan to the shift leader. B. The maintenance
manager did not know if the production manager
received his e-mail communication. C. The
maintenance manager made a unilateral decision it
was time to do the outage. D. The maintenance
manager did not know if the production schedule
allowed for the planned downtime. Answer C
https//www.dumpsbook.com/Exam/CMRP
15Question No 9
Reliability predictions are often expressed in
terms of Mean Time Between Failures (MTBF) or its
reciprocal The reciprocal is known as the A.
Failure Rate. B. Failure Mode. C. Mean Time To
Failure. D. Service Life. Answer A