Title: 130 Liberty Street Deconstruction Demolition Project
1- 130 Liberty Street Deconstruction Demolition
Project
Critique of the Presentation of the Draft Phase I
Deconstruction Plan presented on December 13,
2004 New York Environmental Law Justice
Project December 22, 2004
2Table of Contents
- Introduction
- Consultants and Contractors
- Critique of Presentations
- LMDC Overview
- TRC Supplemental Testing
- Gilbane Deconstruction Plans
- TRC Proposed Enhanced Air Monitoring Program
- Concerns Planning Issues
3Introduction
- This powerpoint is a point-by-point rebuttal of
the LMDC presentation to the community regarding
their deconstruction plan for the 130 Liberty
Street Deutsche Bank property. - The formatting and many quotations are directly
from the LMDC presentation so credits should go
to LMDC for their own words. All the words by
LMDC are white and italicized (except headings).
Our comments are yellow. - Questions and comments please direct to
nyeljp_at_yahoo.com
4Key Parties
- Consultants/Contractors
- Gilbane Deconstruction Contractor
- LVI Asbestos/Cleaning Subcontractor
- Weston Environmental Monitoring Subcontractor
- CDI Deconstruction Subcontractor
- TRC Environmental Consultant
- URS Corporation, Owners On-Site Representative
- Ecology and Environment, Inc. Public Outreach
Consultant - Ambient Group Exterior Air Monitoring
- Kroll Associates Integrity Monitor
- OUR CONCERN THIS IS A VERY IMPRESSIVE TEAM.
LMDC is spending a lot on planning and testing.
BUT HOW MUCH IS LMDC ACTUALLY SPENDING ON
PRECAUTIONS NOW?
5Key Parties, cont.
- Regulators
- US Environmental Protection Agency
- US Occupational Safety Health Administration
- NYS Department of Environmental Conservation
- NYS Department of Labor
- NYS Department of Health
- NYC Department of Environmental Protection
- NYC Department of Buildings
- NYC Department of Sanitation
- NYC Department of Health
- OUR CONCERN Again, impressive listing of
agencies. We are just concerned that these
agencies may be shifting responsibilities to each
other without communication. EPA could not get
the agencies to sign the Memorandum of
Understanding. Why?
6Key Parties, cont.
- OUR CONCERN REGARDING AGENCY ROLES
- NYELJP concurs with the residents and Congressman
Nadler that EPA should be the lead agency for all
demolition activities for properties contaminated
by WTC dust. - This is not because EPA has performed very well
before. - This is because EPA (and OSHA to a degree) is an
agency that has the capacity to oversee all
demolitions in a wholesome manner. - Having agencies come in sporadically in dealing
with demolition of the Deutsche Bank, 4 Albany
and other buildings would only mislead the public
and fail to earn the trust of the public. - Only constant and concerted presence of the
agencies involved would make the proper oversight
possible.
7Critique Summary of Findings in Initial
Characterization
- The results of the sampling and testing revealed
levels of contaminants that should be addressed
in the deconstruction of the building. - Throughout the building, asbestos containing
materials (ACM) were positively identified. - Detectable levels of asbestos, silica, PAHs,
dioxins, PCBs, and heavy metals (including
mercury) were also identified in dust above and
below the suspended ceilings. - The results are consistent with the highly
variable nature of WTC dust and the level of
activity that has occurred within the building
since September 11th. - These are good findings but these data is far
from complete.
8Preparation for Deconstruction
- Supplemental Testing
- Development of the Deconstruction Plan
- Permitting and Notification Plan
- Concern 1. LMDC is going ahead with the
deconstruction phase despite the fact that
further testing was not completed / analyzed /
reported to the public - Concern 2. They are failing to mention the RJLee
data that documented the contamination even in
the areas LMDC failed to test. LMDC should
assume that contamination found in those areas
are still there, rather than siting the lack of
testing by their experts as the excuse to assume
nothing is there.
9Supplemental Testing
- Additional testing is being conducted in
previously inaccessible - surfaces and interstitial spaces including
- The curtain wall, interior walls, the exterior of
the building, HVAC and ductwork, vertical shafts
and cell systems and raceways within the concrete
slabs - Testing for all COPCs addressed in the initial
characterization study which includes asbestos
and other analytes as well as visual inspection
for mold - Preliminary waste characterization
- These results continue to inform the Phase I
Deconstruction Plan and will form the basis of
the Phase II Deconstruction Plan. - Concern Very troubled that the supplemental
testing is not incorporated into the Phase I
Demolition from the start.
10Supplemental Testing - Results
- HVAC testing is complete
- Average asbestos (1,188,236 str/cm2) and lead
concentrations (611 ug/ft2) generally consistent
with the concentrations identified in the Initial
Building Characterization Report. - Average asbestos and lead concentrations in the
interior of the HVAC ductwork system that exceed
the benchmark criteria provided in the September
2002 and May 2003 USEPA WTC Indoor Environment
Assessment studies - While the USEPA residential benchmark and
background concentrations relate to residential
settings and are not directly applicable to a
commercial deconstruction project, these studies
can be used to put the results of this
supplemental investigation into relative context.
- These results and others as completed will be
available on the LMDC website at
www.renewnyc.com.
11Timeline
December 13, 2004 LMDC presents Regulatory
Agencies and the Public with a draft Phase I
Deconstruction Plan ? January 2005 Public
Information Sessions on the Phase I
Deconstruction Plan ? January 2005 Commencement
of Phase I Deconstruction Activity CONCERN Why
are they rushing this when they delayed and
delayed information disclosure and when they take
months to respond to simple informational
request?
12Principles of Deconstruction Plan
- Protective of the health and safety of the
workers and the neighboring community - Compliant with all applicable rules and
regulations - Consistent with the findings of the Initial
Building Characterization Study Report" and
supplemental testing and - Consistent with current industry standard
practices - THEN how come the workers hired were not
examined for any health conditions / toxic
sensitivity?
13Deconstruction Plan Phasing
- Phase I
- Phase IA
- Phase IB
- Phase II
14Deconstruction Plan Phase I
- Phase I
- Abatement of identified interior ACBM
- Cleaning and removal of World Trade Center (WTC)
dust within the building - Soft strip and interior gut of most interior
non-structural materials, ( i.e. carpet, etc.)
and - Erection of the tower crane on the north side and
hoist on the south side of the building. - CONCERN This is just asbestos removal even
though they found lots of other contaminants in
the building? What is the justification for
this? Should they not plan to incorporate
different toxic chemicals into the cleaning plan
from the get-go?
15Deconstruction Plan Phase II
- Phase II
- Abatement of identified ACBM associated with the
exterior of the structure - Disassembly and removal of some remaining
interior non-structural materials - Removal of rooftop mechanical equipment and the
remaining building envelope and - Deconstruction of the structural components of
the building.
16Phase I Plan Components
- Section 1 Waste Management Plan
- Classifies waste streams that will be generated
- Section 2 Ambient Air Sampling Program
- Methodology to monitor for contaminants of
concern at monitoring locations around the
perimeter of the 130 Liberty Street Building - Section 3 Emergency Action Plan
- Provides the initial response steps and
identifies roles and responsibilities of LMDC and
Gilbane during an emergency situation to protect
the health and safety of onsite workers and the
surrounding community - SIMPLY INADEQUATE (see infra)
- Section 4 Safety Plan (To be provided at a
later date) - Provides the safety procedures for Gilbane, as
well as each subcontractor including CDI, LVI,
and Weston
17Phase I Plan Components Cont.
- Section 5 Health and Safety Plan
- Presents practices and procedures all will follow
during the deconstruction of the 130 Liberty
Street Building - Section 6 Asbestos Abatement Plan
- Comprises Phase IA of the deconstruction process
and details activities necessary to carry out the
abatement of ACBM and the cleaning and removal of
dust - Section 7 Soft Strip/Interior Gut Plan
- Comprises Phase IB of the deconstruction process
and details deconstruction, removal, and disposal
of interior, non-structural materials not removed
during Phase IA.
18Deconstruction Plan Phase IA
- Phase IA
- Activities will be undertaken from the top of the
building down - Abatement of interior Asbestos Containing
Building Materials (ACBM) - Dust cleaning and removal and
- Removal of building components needed to complete
the dust cleaning and asbestos abatement. - Methodology seems to make sense if the
contaminants are only asbestos
19Means and Methods for Phase IA
- Enclose all work areas and establish negative air
pressure to ensure potential contaminants remain
in the building. - Licensed abatement subcontractors will perform
limited soft strip to create an open work area,
followed by the removal of asbestos containing
building materials (ACBM). - Thorough cleaning to remove any fibers that may
have been released during the abatement of ACBM,
and to remove the settled WTC dust. - Prior to any work, all vertical connections
between floors will be sealed properly in order
to prevent dust from reentering spaces/floors
already cleaned and cleared. - Vertical connections (stairwells and shafts) will
be cleaned last once all floors of the building
have been cleaned. - SOUNDS PRETTY WELL THOUGHT OUT BUT MORE DETAILS
ABOUT HOW THE WASTE IS GOING TO BE HANDLED ARE
NECESSARY
20Asbestos Abatement
- Establish negative pressure
- Open work area
- Remove ACBMs
- Clean area and dust
- Encapsulate fireproofing
- Visual inspection and
- Final air clearance.
- What is the clearance? Are they going to just
test for asbestos? Just visuals?
21Deconstruction Plan Phase IB
- Phase IB
- Soft strip and interior gut
- Removal of interior gypsum wall board partitions,
sprayed-on fireproofing, bathroom fixtures,
integral shelving and components and - Removal of remaining small scale mechanical,
electrical and plumbing components. - WHO CHARACTERIZES THESE WASTES? Not the agencies
but LMDC.
22Means and Methods for Phase IB
- Phase IB soft-strip/interior gut operations shall
start at the top of the building and proceed
downward. A minimum buffer zone of one floor
shall be maintained between Phase IA and Phase IB
work at all times. - The interior soft strip/interior gut work will be
done on two floors at a time using diesel-powered
equipment compliant with environmental and safety
regulations/standards including, but not limited
to the Coordinated Construction Act for Lower
Manhattan. - Water will be used to provide dust control on
each floor during this phase of the work. - Deconstruction debris shall be chuted from upper
floors past lower floors on which Phase IA
activities are occurring.
23Tower Crane and Hoist
- Necessary for material and personnel movement
during Phase I. - Tower Crane will be located at the northwest
corner. - Hoist will be located at the mid-south side on
Albany Street. - Pre-cleaning as necessary will be done at
attachment points. - OK.
24Protective Measures
- Waste Sampling (Section 1)
- Classify the waste streams that will be generated
as part of the deconstruction project and
identify proper handling, packaging, labeling,
transportation, and disposal methods. -
- Utilize existing data to determine sampling
program - Collect additional samples of materials in place
- Sampling results to determine personnel,
handling, movement, packaging, transport and
disposal requirements. - Any determined hazardous waste will be properly
segregated - Hazardous waste will not be chuted and
- Containers will be secured at all times when not
being loaded and be clearly labeled. - Who determines that particular item is hazardous
waste as governed by RCRA? - we do not want
rubber stamping..
25Protective Measures Cont.
- Air Monitoring-(Section 2)
- Four levels of monitoring established
- Personnel air monitoring
- Inside building/proximate work activities
- Outside building within site boundaries
- Outside site boundaries in immediate surrounding
community - Community asked for personal air monitoring for
couple residents just for comparison. They
declined saying that contamination wont go
that far. If LMDC is really sure contaminants
wont reach the residents, why not provide
personal air monitoring?
26Protective Measures Cont.
- Air Monitoring-(Section 2)
- Section 2 of the Deconstruction Plan outlines
level four of the program - Utilizing meteorological instrumentation to
record wind speed, wind direction and other
pertinent conditions - Conducting real-time monitoring for potential
off-site migration of emissions using continuous
direct read ambient air monitors and - Conducting integrated air sampling for the
following target compounds Particulates as Total
Suspended Particulates (TSP), metals as TSP,
asbestos, silica, mercury, PAH's (polyaromatic
hydrocarbons) Dioxins Furans (D/Fs), and PCBs. - WE SUPPORT THE EXTENDED AIR MONITORING PROGRAM.
In fact, LMDC should have done this long time
ago. There should have been air monitoring at
elevated levels. Sampling for asbestos and heavy
metals just is not enough.
27Protective Measures Cont.
- LMDC Proposed Enhanced Exterior Air Monitoring
Approach - (on-line at www.renewnyc.com)
- To be modified to ensure program is complementary
and allows for QA/QC of Section 2 - Proposal includes
- Additional sampling locations at various
elevations (i.e. ground level, rooftops and
setbacks) - Co-located sampling locations for QA/QC purposes
- Daily real-time monitoring component
- Enhanced analyte list including COPC list
- Project and public notification protocol
- Continued submission of results to NYCDEP
- Continued public access to air results via LMDC
website - AGAIN, very good that LMDC finally came up with
this. We are slightly concerned that some of the
air monitoring data is still missing although we
indicated the lack of data some months ago.
28Emergency Action Plan (EAP)
- Designates appropriate personnel responsible for
implementation and monitoring of emergency
procedures. - Applies to all contractors working on-site
including employees and visitors. - Gilbane Emergency Coordinator John Graves,
licensed New York City Site Safety Manager
Liaison to the First Responder agencies
throughout the duration of the project. - All prime subcontractors will identify an OSHA
certified Emergency Coordinator, responsible for
the performance of emergency preparedness
responsibilities. - Plan will be revised as necessary during the
course of the project. - We find the emergency action plan very
problematic. Not to disparage John Graves,
community wants an emergency director that can
authorize evacuation and other serious measures
in case of emergency.
29Emergency Action Plan Cont.
- EAP includes
- Pre- Emergency Planning Activities
- Prior to commencement of work, Gilbane Emergency
Coordinator and the LMDC will meet with the FDNY,
NYPD, OEM, and Battery Park City Certified
Emergency Response Team (CERT) to discuss - Emergency Response Activities,
- Agencies roles and responsibilities, and
- To confirm an understanding of the existing
building conditions. - Throughout deconstruction activities the Gilbane
Emergency Coordinator will conduct regular
emergency preparedness meetings with on-site
personnel. - NYELJP has commented again and again that
Emergency Action Plan without consultation with
the firefighters (meaning FDNY and UFA) and other
first responders is SIMPLY INADEQUATE. These
consultation should have happened months ago, not
immediately prior to commencement of work. The
consultation should have been incorporated into
the EAP beforehand.
30Emergency Action Plan Cont.
- The EAP also includes protocol for building
evacuation - Emergency Response Communication Chart
- Emergency Contact Numbers for Local Authorities
- Evacuation Assembly Area
- Community Notification
- One of the reason LMDC should have consulted the
firefighters beforehand is that they should make
sure they are not disrupting the operations of
E10/L10 during emergency situations. The current
evacuation plan lists one of the evacuation
assembly area on liberty street where E10/L10 is
located. We are concerned that this may
practically impede rescue efforts. - LMDC should make sure that emergency vehicles are
given access at all times. Truck traffic should
be adjusted accordingly.
31Community Emergency Action Plan
- Pre-Emergency Planning Activities
- LMDC will meet with Emergency Response Agencies,
local hospital, and the surrounding Community
prior to commencement of work. - LMDC will notify surrounding building landlords
and superintendents of deconstruction activities
and EAP. - LMDC will arrange for the Gilbane Emergency
Coordinator to meet with the Community as
necessary. - We will keep track of how this process is done.
Perhaps final meeting with community members,
GEC, and representatives from the first
responders is necessary.
32Community Emergency Action Plan Cont.
- In the event of any emergency necessitating
immediate community action, LMDC will rely on the
Emergency Response Agencies protocol for
informing the community of necessary actions and
impacts during the event. - In the event of incidents impacting the
community - LMDC will activate the phone tree that was
established with area neighbor volunteers in
October 2004. - LMDC will send an email update regarding
particular incidents. - LMDC will post flyers in neighboring buildings
identifying the actions that were taken. - LMDC will host briefings to discuss the incident
and measures taken in response to the incident. - Community members are still concerned that phone
tree / email wont necessarily reach children
33Additional Comments re Community Emergency Action
Plan
- In the end, LMDC is relying on the First
Responders when emergency situation arises.
Well, LMDC has not really told the First
Responders whats in that building. How can the
First Responders effectively handle emergencies
when LMDC still has not communicated with them?
- THERE ARE GOING TO BE DEMOLITIONS IN OTHER
BUILDINGS IN THE AREA. These buildings would be
contaminated also. There needs to be a
co-ordinated emergency response plan. This is
the crucial reason we want the EPA to come in as
the lead agency for all demolitions of WTC-dust
contaminated buildings.
34Health and Safety Plan (HASP)
- Presents the safety procedures and practices to
be followed during all Phase I site activities
to - Ensure safe completion of tasks
- Ensure prevention of occupational injuries and
exposures to chemical, physical and biological
hazards to workers at the Site and - Ensure compliance with all applicable government
agencies and regulations, including requirements
established by OSHA NIOSH USEPA NYSDEC
NYCDEP NYSDOL, and the City of New York. - All on-site Contractor and Subcontractor
personnel are required to strictly comply with
the provisions of the HASP. - This HASP is based upon current knowledge of
conditions at the Site and shall be updated as
new information becomes available and/or
conditions change within the Building. - AGAIN, LMDC should have consulted the First
Responders regarding the HASP because this is
information First Responders need to know in
order to make proper precautions
35Health and Safety Plan Cont.
- The HASP Outlines
- Engineering Controls
- Personal Protective Equipment and decontamination
requirements - Potential physical hazards
- Chemical hazards
- We are especially concerned about fire hazards.
It seems that fire hazards might increase on the
IB phase due to demolition equipments. Is this
true?
36Coordinated Construction Act
- LMDC will comply with all regulations dictated by
the Coordinated Construction Act, including but
not limited to - The use of Ultra Low-Sulfur diesel fuel
- Hours of operation and
- Pre-planned truck routes
37Proposed Truck Routes-Phase I
- LMDC developing plan with NYC DOT, NYS DOT, Port
Authority of New York and New Jersey. - Proposing the use of Washington Street for access
to the loading dock and the north plaza area. - Proposing the use of Albany Street for access to
the Hoist. - We suggest that the proposed truck routes do not
block the ingress / egress of fire trucks in the
area.
38Next Steps
- Public outreach
-
- Submission of plan to regulators
- Submission of plan amendments as required by
regulators - Submission of permit applications
- Approval of plan
- Mobilization at site
- REGULATORS COMMENTS SHOULD BE PUBLISHED ON THE
WEB AS A MATTER OF PUBLIC RECORD. - We also suggest that that comments from the
community members be also published.
39Opportunities for Public Involvement
- E-Updates
- Public Information Sessions
- Comment through the LMDC Website
- Community Board One meetings
- One public comment during CB1 meeting on December
13th 2004 was very insightful. Deutsche Bank
and LMDC have spend so much money on testing and
public outreach. But how much money was spent on
safety precautions?