MS4801 Project Management Week 4: Planning - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

MS4801 Project Management Week 4: Planning

Description:

B) Construction plans A 15. C) Traffic study A 10. D) ... G) Wait for construct F 170. H) Occupancy E,G 35. AON with Duration. Activity Preceding Duration ... – PowerPoint PPT presentation

Number of Views:175
Avg rating:3.0/5.0
Slides: 30
Provided by: VGlennFu
Category:

less

Transcript and Presenter's Notes

Title: MS4801 Project Management Week 4: Planning


1
MS4801 Project ManagementWeek 4 Planning
  • Planning is an essential part of project
    management.
  • In essence, the plan is a roadmap.

2
WebCT AssignmentFirst Principles of Project
Management
  • All the principles make certain assumptions
    about the team players involved. For example
  • Everyone is working towards the same or similar
    goals, whatever those might be.
  • Everyone is being honest with one another.
  • An appropriate level of skill or experience is
    available as needed.
  • Everyone wants the project to succeed.
  • Everyone is clear and agrees on who the customer
    is.
  • First Principles of Project Management, By R. Max
    Wideman

3
Step 1 Project Objective
  • The first step is to define the project
    objective.
  • The objective must be clear, attainable,
    specific, and measurable.
  • The objective is usually defined in terms of
    scope, schedule and cost.

5
4
Step 2 Work Breakdown Structure
  • Determine what activities need to be performed.
  • A list of all the activities must be developed.
  • An activity is a piece of work that consumes
    time.
  • The WBS is a hierarchical tree of end items to be
    accomplished.
  • A work item is one small piece of the project.
  • A work package is the lowest-level item.

6
5
Step 3 Developing the Network Plan
  • After all activities have been defined, they are
    graphically portrayed in a network diagram.
  • Two network planning techniques were developed in
    the 1950s
  • Program evaluation and review technique (PERT)
  • Critical path method (CPM)

9
6
Program Evaluation Review Technique
7
Network Principals
  • Different formats can be used to draw the
    diagram
  • Activity in the box (AIB)
  • a.k.a. activity on the node (AON)
  • Activity on the arrow (AOA)

12
8
Build a Project Network
Node
1
3
2
Branch
  • A project is made up of a sequence of activities
    that form a network representing a project.
  • Network consists of branches nodes

9
Network Diagrams
  • Activity Predecessor
  • A None
  • B None
  • C A
  • D A
  • E B
  • F B
  • G C, D, E, F

A
B
10
EXERCISE Network Diagram
  • Activity Predecessor
  • A None
  • B None
  • C A,B
  • D A,B
  • E A,B
  • F C,D
  • G E
  • H F
  • I F,G

Construct a network diagram
11
Need Duration
  • Activity Predecessor
  • A None
  • B None
  • C A
  • D A
  • E B
  • F B
  • G C, D, E, F

12
Need Duration for Activities
  • Activity Pred Duration
  • A None 5
  • B None 10
  • C A 15
  • D A 10
  • E B 5
  • F C 20
  • G E 20
  • H D,E,F 5
  • I G 15

13
Critical Path Analysis (CPM)
C,15
F,20
A,5
H,5
D,10
B,10
E,5
G,20
I,15
14
Work Breakdown
15
Activity-in-Node
16
Activity in the Box (AIB - NODE)
  • Each activity is represented by a box.
  • The activity description is written in the box.
  • Each box is assigned a unique activity number.
  • Activities have a precedential relationship.
  • Some activities may be done concurrently.

13
17
Activity on the Arrow (AOA)
  • Each activity is represented by an arrow.
  • The activity description is written above the
    arrow.
  • The tail of the arrow designates the start of the
    activity.
  • The head of the arrow designates the completion
    of the activity.
  • Activities are linked by circles called events.
  • An event represents the finish of activities
    entering it and the start of activities leaving
    it.
  • Each event is assigned a unique activity number.

14
18
Activity-on-Arrow
19
Preparing the Network Diagram
  • Ask the following questions regarding each
    activity
  • Which activities must be finished immediately
    before this activity can be started?
  • Which activities can be done concurrently with
    this activity?
  • Which activities cannot be started until this
    activity is finished?

19
20
Preparing the Network Diagram (Cont.)
  • Should flow from left to right.
  • Not drawn to a time scale.
  • Can vary in how detailed the diagram should be.
  • AIB vs. AOA is a matter of personal preference.
  • AIB is the most common in project management
    software packages.

20
21
County Engineers Design Department
  • Activity Preceding Duration
  • A) Application approval None 5
  • B) Construction plans A 15
  • C) Traffic study A 10
  • D) Service availability check A 5
  • E) Staff report B,C 15
  • F) Commission approval B,C,D 10
  • G) Wait for construction F 170
  • H) Occupancy E,G 35

22
Simple Activity on Node
Activity Preceding Duration A) Application
approval None 5 B) Construction plans A 15 C)
Traffic study A 10 D) Service avail check A 5 E)
Staff report B,C 15 F) Commission
apprvl B,C,D 10 G) Wait for construct F 170 H)
Occupancy E,G 35
23
AON with Duration
Activity Preceding Duration A) Application
approval None 5 B) Construction plans A 15 C)
Traffic study A 10 D) Service avail check A 5 E)
Staff report B,C 15 F) Commission
apprvl B,C,D 10 G) Wait for construct F 170 H)
Occupancy E,G 35
24
Forward Pass
  • How soon can the activity start (ES)
  • How soon can the activity finish (EF)
  • How soon can the project be finished (TE)

Calculate Forward Pass
25
Backward Pass
  • How late can the activity start (LS)
  • How late can the activity finish (LF)
  • Which activities represent critical path (CP)
  • How long can the activity be delayed (SL)

26
TOOL Responsibility Matrix
  • Displays in tabular format the individuals
    responsible for the work items.
  • X can be used to indicate who is responsible.
  • P indicates who has primary responsibility.
  • S indicates who has secondary responsibility.

EXAMPLE
7
27
Responsibility Matrix e.g., Frame, Page 190
? Responsible / ? Involved / ? Informed
28
TOOL Gantt Charts
  • Gantt charts, or bar charts, are popular due to
    their simplicity.
  • Activities are listed down the left-hand side.
  • A time scale is shown along the bottom.
  • Do not display the interrelationships of
    activities.
  • If one activity is delayed, it is not obvious how
    that will affect other activities.
  • Most project management software can show
    interdependencies with arrows.

10
29
Midterm Preview
  • Go to preview
Write a Comment
User Comments (0)
About PowerShow.com