Title: Strategies for the security of electricity supply
1Strategies for the security of electricity supply
2Contents
- Risk factors in the present Basic Plan of long
- term Electricity Supply Demand, and
Strategies
2. Risk factors in the open market and
countermeasures
3. The strategy for the stability of price in
the open market
4. Nuclear energy and governmental support
3Contents
- Risk factors in the present Basic Plan of long
- term Electricity Supply Demand, and
Strategies
2. Risk factors in the open market and
countermeasures
3. The strategy for the stability of price in
the open market
4. Nuclear energy and governmental support
41-1. The basic plan of long term
electricity supply demand
- Electricity companies enjoy decent profitability
considering the rules and policies set by the
government - The government is responsible for the Basic Plan
- The government predicts electricity demands, and
devises relevant policies - The basic plan covers 14 years, and is updated
every two years - The basic plan reflects basic directions, demands
prospects, and construction plan of grid lines - Power companies refer to the basic plan, when
they make decisions of new investments.
5 1-2. The constructions in the Basic plan
- The basic plan includes A, B, C1, classified by
the degree of uncertainty. - A under construction, imminent completion
- B in pre-construction stage after being
approved - C1 in planning stage to construct, expected to
be approved within 2years (executions
and processes are less certain) - C2 in planning stage, not included in the basic
plan, not expected to be approved within
2years (some issues such as linkage
to power network need further study)
C2
C1
B
A
Under construction
Planning (no approval within 2years)
Preparing to start construction
Planning (approval within 2years)
6 1-3. The Plan of constructions by GenCos
- State owned GenCos plan to commission 31,100 MW
facilities (81 of total construction) from 2004
to 2017 - they will construct nuclear power plants and
coal power plants, which are very capital
intnsive - Private GenCo plan to construct 7,100 MW
facilities, 19 of capacity entries - they prefer to construct LNG power plants, which
require less investment
38,200
Plan period 20042017, unit MW
7,100 (19)
25,200
31,100 (81)
Private GenCo
4,000 (11)
13,000
3,100 (8)
21,200 (55)
State ownedGenco
9,900 (26)
Total
Under construction
In preparation
71-4. Prospects of capacity reserve margin
- Capacity reserve margin is expected to be more
than 1517, the proper margin level to guarantee
supply, when the planned constructions are
successfully completed - capacity reserve margin is expected to reach
1518 by 2006, afterwards 25
81-5. Risk factors in the execution of the plan
- C1 constructions may not be executed if market
condition changes unfavorably - The government cannot force the private
companies construction. - State owned GenCos 9,900MW, private GenCos,
3,100MW - The constructions of nuclear power plants have
many barriers to overcome - Low public acceptance (NIMBY) and opposition of
NGOs while 6 nuclear power plants (6,000MW) are
scheduled for commissioning over the plan period - Prospects of capacity reserve margin by
uncertainties
- The delay of C1 may trigger a demand-supply
emergency starting from 2015 - The delay of 6 nuclear power plants may trigger
an emergency starting from 2013
91-6. Strategies to execute
the construction plan
- The Government (KEPCO) promotes C1 by state owned
GenCos to meet the capacity entries timeframe - The processes of constructions are cautiously
evaluated by KEPCO - State owned GenCos will replace private GenCos in
constructing C1 if the private GenCos withdraw - No corporate investment risk exists in
constructing nuclear power plants because KEPCO
holds 100 shares of the nuclear power company. - However, opposition of NGOs and citizens require
continuous promotion to increase public
acceptance to nuclear power plants. - safety first operation
- co-prosperity with regional community
- advertising the necessity of nuclear energy in
Korea due to high dependence on imported energy
resources
10Contents
1. Risk factors in the present Basic Plan of
long term Electricity Supply Demand, and
Strategies
2. Risk factors in the open market and
countermeasures
3. The strategy for the stability of price in
the open market
4. Nuclear energy and governmental support
112-1. Risk factors to secure electricity supply
in the open market
- Investment decisions are made upon the price
signals and predictability in the open market,
however, the price signals may not function well - when irrational market system distorts the
signals - when price hike and abnormal volatilities are
caused by manipulations of any participants
market power - The GenCos may fail to secure proper
profitability for re-investment - when the market is interrupted by regulatory body
for the purpose of price stabilisation
122-2. Strategies to secure stable supply
of electricity
Cost Based Pool (CBP) is the realistic best
solution
- CBP has proven to be the best way to keep the
market stability in Korea until effective
solution is found - effective promotion of competition for cost
reduction - reasonable market price
- stable supply of electricity
- less distortion of market signal by irrational
market system - less market manipulation by participants
- less interruption by regulatory bodies
132-2. Strategies to secure stable supply
of electricity
- CBP has evolved through improvements such as
adoption of BLMP and A/S - Adoption of Base Load Marginal Price (BLMP)
- In a signal market pool, the estimated market
price set by System Marginal Price (SMP) used to
be too high to be accepted resulting from the
portfolio of fuel mix - Nuclear power plants and coal power plants
determine BLMP - LNG and oil power plants determine SMP
- Payments for ancillary services for grid security
and cycle maintenance to meet the market system - Promoting investments by continuously improving
CBP system - The CBP market system will be improved, i.e.
differentiated capacity payment (CP) will be
linked to reserve margin
To Be
As Is
- low reserve margin, high CP
- high reserve margin, low CP
- CP paid on the Pari passu basis to all
available capacity
14Contents
1. Risk factors in the present Basic Plan of
long term Electricity Supply Demand, and
Strategies
2. Risk factors in the open market and
countermeasures
3. The strategy for the stability of price in
the open market
4. Nuclear energy and governmental support
153-1. Whole sale market and
securing the stability of price
- Oil and LNG generators determine 7580 of market
pricing at around 5.7/kWh under System Marginal
Price (SMP) system - Oil and LNG generators produce 20 of annual
generation volume. - KEPCO may suffer financial risks from high SMP
and low tariff regulated at 6.5/kWh - Financial health of GenCos and KEPCO through
price stabilization measures is essential.
Load Duration Curve
Reserve Margin
( MW)
LNG / Oil
Coal
7580
Nuclear
100
8,760 hours
163-1. Whole sale market and
securing the stability of price
- Introduction of BLMP has secured price stability
- The highest marginal price of base load
generators is determined as BLMP - The highest marginal price of peak load
generators is determined as SMP - The settlement prices have been maintained at
around 4.24.4/kWh
Introduction of Separate Settlement
(Variable Cost)
SMP
5.43
CP 0.63
4.80
LNG
4.19
Oil
3.44
CP 1.79 /kWh
1.64
Coal
BLMP
0.35
Nuclear
Base Load Volume 78
Peak Load 22
173-2. Evaluation on the operation
of the wholesale market
- State owned GenCos have enjoyed significant
increase of operating income ratio (16.5 before
separation ? 20.9 after separation). - They own base load generators (nuclear, coal),
and enjoy reasonable profits from market price. - Private GenCos in the market also have enjoyed
reasonable profits. - They own peak load generators (LNG), and are
sufficiently compensated by the CP to recover
fixed costs. - Private GenCos having PPA with KEPCO are
guaranteed reasonable ROR(8).
? Operating income ratio of GenCos after
separation
18Contents
1. Risk factors in the present Basic Plan of
long term Electricity Supply Demand, and
Strategies
2. Risk factors in the open market and
countermeasures
3. The strategy for the stability of price in
the open market
4. Nuclear energy and governmental support
194-1. The status and the prospects
of nuclear generation
Prospects of nuclear generation
- The further construction of nuclear power plants
is necessary for securing stable supply of
electricity as the demand is expected to highly
increase in South Korea. - Korea imports most of its generation fuel (99),
and the prices of fossil fuel rocketed recently
(56). - The basic plan of long term electricity supply
demand stipulates that nuclear power plant
generation will stay at 30 of the total
generation capacity. - Expanding public acceptance to safe of nuclear
power plants and promoting timely constructions
are required.
204-2. The status of nuclear generation
Current status of nuclear energy in the
electricity industry
- 20 nuclear generators (17,716MW) in operation
compose 29 of total capacity in Korea. - The generation by nuclear power plants reached 39
of total generation volume and 32 of the total
traded amount in 2004, the highest shares among
generation types. - The low generation costs of nuclear power plants
helped Korea not to increase retail prices in
spite of recent price hikes of oil and coal.
214-2. The status of nuclear generation
The profitability of nuclear power plants in the
market
- The operating income ratio of nuclear power
plants (22.4) was higher than those of any
thermal power plants. - ROR of nuclear power (5.8) was higher than the
average ROR of GenCos (5.3) in 2004. - While thermal power companies suffer fuel cost
increase by the coal price increase, the nuclear
power company enjoyed market price increase
without the increase of fuel costs. - No difficulty is expected in raising new
investments in nuclear power plants with stable
profitability under the current CBP market.
224-3. The governmental support
to nuclear generation
- Nuclear power plants need governmental support
for securing construction site and disposal
site, and for continuing operation - More constructions of nuclear power plants are
inevitable in order to secure electricity
supply and stable market price of electricity in
Korea - Institutional Support for constructions of
nuclear power plants - Economic benefits to local areas near power
plants - 914mn/year by special laws for the support
of local area accepting location of
low-medium radio active waste - 68mn/year by special laws for the support of
local area neighboring power plants - Reduction of risk of nuclear energy business by
laws for nuclear damages. - Public relationship in support of nuclear power
plants.