Title: Innovative Contracting Techniques
1Innovative Contracting Techniques
- Partnering with Industry to Create a Better
Roadway - Presented by
- Doyt Bolling
- Director Utah Technology Transfer Center
2Innovative Contracting Techniques
- Design-Build
- Lane Rental
- AB Bidding
- Warranty
- Job Order Contracting
3Premise for the Implementation of Innovative
Contracting Techniques
- Traditionally highway projects are designed, bid,
and built with the contract awarded to the lowest
bidder. - Innovative contracting allows for other factors
such as time, quality, and innovation to be
considered, in addition to low bid.
4General Warrants and Objectives
- Projects suitable for any innovative contracting
technique are - Projects in which right-of-way, utility,
environmental, and other socio-political issues
have been resolved. - Projects where the potential exists for
increasing quality, decreasing costs, decreasing
time, reducing administration costs, and reducing
the possibility for legal claims and change
orders.
5(No Transcript)
6Design-Build
- Definition When a single entity provides both
the design and construction through a single
contract between the owner and the Design-Build
firm.
7Why Pursue Design-Build
- Primary Objective
- Time Savings
- Other Objectives
- Singular responsibility.
- Reduce administrative costs.
- Allow for contractor innovation and flexibility.
- Provide additional expertise not available in
house. - Allow contractor to pursue new technologies and
approaches that will facilitate design,
construction, and improve final product quality.
8Framework of Design-Build
- There are three principal project categories for
which Design-Build procurement has been
effective - Emergency repair and rehabilitation projects.
- Specialty type projects (I.e. ITS, Ferry Boats,
and etc.). - Mega-reconstruction projects.
9Emergency Repair and Rehabilitation Projects
- Design-Build is used for these projects to
decrease project delivery time and road user
costs.
10Specialty Type Projects
- Design-Build is used because there is
- Limited expertise in house.
- Opportunity for innovation, alternative designs,
and innovative construction approaches.
11Mega-Reconstruction Projects
- Design-Build is used to
- Shorten delivery time for the project by allowing
construction to proceed before design is
completed. - Allow for contractor innovation and flexibility
to be incorporated in the design and construction
of the project. - Save time and reduce road user costs.
- Meet specific delivery dates.
12Utah Example Reasons for Pursuing Design-Build
- Time
- The Olympics and increasing traffic congestion
called for early completion. - For example- A project that under traditional
methods would have taken10 years to complete will
now take just 4.5 years to finish under
Design-Build. - Innovation
- The contractor can provide early insight to the
design to facilitate construction. - Administration and Legal Issues
- Single source responsibility for both design and
construction reduces legal issues and facilitates
administration of the project.
13States Using Design-Build
- Arizona
- Colorado
- California
- Florida
- Hawaii
- Kentucky
- Alaska
- Michigan
- Minnesota
- Missouri
- New Jersey
- Virginia
- North Carolina
- North Dakota
- New Mexico
- Ohio
- Pennsylvania
- South Carolina
- Utah
- Maine
- Oregon
14AB Bidding
- Definition A cost plus time bidding procedure
that selects the low bidder based on a monetary
combination of the contract bid items (A) and the
time (B) needed to complete the critical portion
of the project.
15Benefits of AB Bidding
- AB Bidding is used to motivate the contractor to
minimize the delivery time for high priority and
highly trafficked roadways. This encourages
contractors to finish early by - Offering bonuses for early completion.
- Assessing disincentives for late completion.
16Criteria for Selection of AB Bidding as a
Contracting Procedure
- Traffic restrictions, lane closures, or detours
result in high road user costs. - Safety concerns, or significant impacts to the
local community or economy during construction
warrant expediting the project. - Traffic control phasing can be structured to
maximize a contractors ability to reduce the
duration of construction. - The project is relatively free of third party
conflicts. - It is in the public interest to complete the
project as soon as possible.
17States Using AB Bidding
- Maryland
- Colorado
- California
- Virginia
- Texas
- North Carolina
- Wisconsin
- Washington
- New York
- North Dakota
- Iowa
- New Jersey
- Missouri
- Idaho
- Indiana
- Kansas
- Maine
18New Yorks AB Bidding
- New York has completed 33 projects since 1994.
- Projects were completed an average of 19 days
earlier than bid and an average of 87 days
earlier than the engineers estimate. - An average of 9 days were added for change
orders. - Only one project took more days to complete than
engineers estimate and only two took more days
than bid. - An estimated 20.32 million dollars in road user
costs were saved. - 4.75 million dollars were paid for incentives.
19Lane Rental
- Definition An innovative contracting technique
by which a contractor is charged a fee for
occupying lanes or shoulders to do the work.
20Why Pursue Lane Rental?
- Primary Objective
- To motivate the contractor to minimize the time
that a lane, a shoulder, or a combination of
lanes and shoulders are out of service so there
is minimized traffic delay to highway users.
21Lane Rental Uses
- Lane Rental has been used for projects that
contain one or more of the following
22- Traffic restrictions or lane closures result in
high road user costs. - The use of alternate routes or off-site detours
is impractical. - The traffic control plan allows the contractor
flexibility in scheduling work to minimize the
impact of lane closures. - The agency seeks contractor expertise to minimize
the time that lanes are out of service. - The project is relatively free of third party
conflicts (I.e. right-way issues, utilities,
etc.). - The benefit in terms of reduced impact to the
highway user is greater than the additional cost
to minimize lane closures.
23How are Lane Charges Calculated?
- Charges for lanes or shoulders can be on either
an hourly or daily basis. - Charges per lane can vary depending on time of
day, amount of traffic, and other road user costs.
24Oregon Example
- Traditionally the State of Oregon specified times
at which lane closures were not allowed. - State law did not permit the use of road user
costs in the determination of liquidated damage
amounts. - Therefore no disincentive for closures or
incentive to keep lanes open.
25Oregon DOT US 26 Reconstruction Lane Rental
Project
- Major reconstruction of a 2.08 mile stretch of a
primary commuter route from the west suburbs to
downtown Portland. - ADT ranges from about 100,000 to 130,000 vpd,
with less than 2 trucks. - Rates for every 15 minutes ranged from 0 to
21,000 for lane use.
26States Using Lane Rental
- Colorado
- New York
- North Carolina
- Utah
- Oklahoma
- Oregon
- Washington
27New Yorks Lane Rental
- New York has completed 6 projects since 1995.
- Total project costs were 3.6 million dollars
below the engineers estimate. - Three projects were above and three projects were
below the engineers estimate.
28Warranty
- Definition A guarantee of the integrity of a
product and of the makers responsibility for the
replacement or repair of deficiencies.
29Advantages of Warranty Contracting
- Less owner risk.
- Eliminates cost of owner QA/QC by transferring
this responsibility to the contractor. - Creates an incentive for overall project quality.
- Assures acceptable level of service or
performance for a work item and/or major project
element.
30States Using Warranties
- Wisconsin
- Michigan
- North Carolina
- California
- Missouri
- Ohio
- Montana
- New Hampshire
31Job Order Contracting/Indefinite Delivery
- Definition The combining of like projects into
one contract that is administered by the
owner/agency. - These projects are competitively bid with
indefinite quantity and indefinite delivery at
fixed unit construction prices.
32How is Job Order Contracting Different from
Traditional Contracts?
- Two Ways
- Job Order Contracts cover a variety of similar
types of construction including maintenance,
repair, renovation, and traffic control projects
that are combined under a single contract at
fixed unit prices. - The contracts are in place before the owner
identifies where and when the work is to be done.
These contracts are based on a minimum yearly
amount of work as long as the contractor performs
acceptable work.
33Advantages of Job Order Contracting
- Lower costs
- Quantities are larger by combining similar
projects, therefore resulting in lower unit bid
prices. - Incentives for quality
- The contractor is motivated by the fact that they
will continue to receive work so long as their
performance is satisfactory. - Less owner time and administration cost required
- Several projects can be accomplished under one
contract. - Opportunities for small disadvantaged businesses
- Small firms that cant compete for larger
construction projects can provide services
required by individual job orders.
34States Using JOC
- Armed Forces
- Illinois
- California
35Innovative Contracting Website Access
- Accessing WebSite
- Connect to www.utaht2.usu.edu
- Click on the Innovative Contracting Link.
- Or
- Go directly to the Innovative Contracting Page by
entering http//www.utaht2.usu.edu/IC/Default.html
- Viewing Documents
- Click on the Link Search for Innovative
Contracting Documents. - Then use the pull-down menus to select a state
and a contracting procedure. - NOTE to view all leave the pull-down menus
blank. - Click Run Query
- After the query loads click on the title of the
document you wish to view. - A full description of the document will load.
- Click on View Full Document at the bottom of
the page. - If you have Adobe Acrobat Reader the document
will load. - Or
- If you do not have Adobe Acrobat Reader, click on
the icon, or visit www.adobe.com/prodindex/acrobat
/readstep.html to download a free copy.
36Questions?