Title: 072604.1 Moore 1
1BioIreland Conference Nov 2006
Centocor A Case Study for Biomanufacturing in
Ireland Paul Treacy Vice-President General
Manager Centocor Biologics
2Contents
- Johnson Johnson in Ireland
- Centocor Cork Project Scope
- Lessons Learned
3Johnson Johnson The Company
- Most broadbased healthcare company in the World
- 2005 Revenues 50.51 Billion
- 115,000 employees
- Manufacturing Operations in Europe, North
America, South America, Australia, and Asia - Annual RD expenditure 4 Billion
4Johnson Johnson Ireland
- Celebrated 70 years in Ireland in 2005
- 6 manufacturing operations in Ireland
- Over 2000 Employees
Medical Devices
Pharma Chem
Biotechnology
5Cork Plant Scope
- Greenfield Manufacturing Site
- JJs 5th bulk Biotech plant
- Multi Product Capable
- Capital spend 735 Million
- Capable of producing 480 Kgs Product per Year
- New Generation of Products
- CNTO 148 (Next Generation of REMICADE)
- CNTO 1275
- Other New Molecular Entities currently in RD
pipeline - Employment 311 permanent staff contractors
- 60-70 of employees will be 3rd level qualified,
10 will be 4th level qualified.
6Cork Plant Timeline
7(No Transcript)
8(No Transcript)
9Building Schematics
10August 2005
11September 05
12November 05
13(No Transcript)
14(No Transcript)
15(No Transcript)
16BioIreland Conference Nov 2006
Application of Lessons Learned (Why are large
scale bio/pharma construction projects so
difficult to execute?)
17Learning From Past Mistakes
- Most common mistake involving large
Biotech/pharma construction projects has been the
failure to have experienced users involved in the
initial design of the plant. - Second most common mistake is not adequately
capturing user input and translating it into the
engineering design and construction - The third most common mistake is not giving the
same priority to developing operational readiness
as is given to project construction and
qualification - gt Why have these simple mistakes been repeated
over and over again?
18Learning From Past Mistakes
- The principal reason why users are not involved
early in plant design is due to differing
abilities of various project groupings to
mobilize - gt Contract Design Houses, Construction Companies
Owner Engineering depts can invariably mobilize
much faster than user groups
19Traditional Project Mobilization
20User Input
- Not having Appropriate and Timely user input can
lead to - Schedule impacts due to redesign and rework
- Cost overruns due to redesign and rework
- Processes that are difficult to validate
- Capacity that is less than expected
- Quality and compliance levels that are not to
required standards
21Centocor Plant Mobilization Solution
22Temporary User Concept
23Learning From Past Mistakes
- Most common mistake involving large
Biotech/pharma construction projects has been the
failure to have experienced users involved in the
initial design of the plant. - Second most common mistake is not adequately
capturing user input and translating it into the
engineering design and construction - The third most common mistake is not giving the
same priority to developing operational
readinness as is given to project construction
and qualification
24Capturing the Voice of the Customer
- How can we ensure that the voice of the customer
is captured?
- Use of Design Excellence
- A method for systematically capturing and
integrating user input into the design,
construction and validation effort.
- Janssen P3 was the first large-scale
manufacturing construction project in JJ to
employ Design Excellence - Centocor Cork is the 2nd project.
25Use of Design Excellence
Voice of the Customer
Stakeholders
Customers/Users
GMP Requirements
Non-GMP Requirements
High Level requirements
Low Level requirements
URS
DeX Scorecard
26Benefits of Design Excellence
27Learning From Past Mistakes
- Most common mistake involving large
Biotech/pharma construction projects has been the
failure to have experienced users involved in the
initial design of the plant. - Second most common mistake is not adequately
capturing user input and translating it into the
engineering design and construction - The third most common mistake is not giving the
same priority to developing operational readiness
as is given to plant construction and
qualification
28Integrated Project Management
Project Master schedule is divided into the
following Sub-Projects
But..there is something missing! The schedule
above concentrates predominately on building the
plant. The critical missing piece is preparing
the plant to operate in an efficient,
cost-effective and compliant fashion when it is
handed over.
29Merge Operational Readiness Effort into Master
Project Schedule
Project Directors
Site Leadership Team
Operational Readiness Teams
- Construction
- Tech Transfer
- Identify
- Tasks
- Milestones
- Interdependances
- Resources
BioCork Integrated Schedule
Merge
Fully Integrated Project/Plant Management Process
30Fully Integrated Project Schedule
Master Project Schedule
Commissioning
Qualification Validation
Operational Readiness
Construction
Design
Operational Readiness Teams
Project Directors
Owners/users
31Operational Readiness Teamsexamples
- EHS Steering
- EHS Committee
- Sarbanes Oxley
- Maintenance Exellence
- Change Management (system development)
- Deviation Management (system development)
- Process Mapping
- Process Information Systems
- Training
- Communications
- Documentation
- Labelling
- SAP Preventative Maintenance
- HR Time attendance
- SAP ERP
- Records Management
- Asset Management
- Vendor Management
32Progress To Date
- Currently starting Commissioning
- Project is on schedule
- Project is on budget