072604.1 Moore 1 - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

072604.1 Moore 1

Description:

Contract Design Houses, Construction Companies & Owner Engineering depts can ... Use of Design Excellence ... Benefits of Design Excellence. 072604.1 Moore 27 ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 33
Provided by: kon65
Category:
Tags: moore

less

Transcript and Presenter's Notes

Title: 072604.1 Moore 1


1
BioIreland Conference Nov 2006
Centocor A Case Study for Biomanufacturing in
Ireland Paul Treacy Vice-President General
Manager Centocor Biologics
2
Contents
  • Johnson Johnson in Ireland
  • Centocor Cork Project Scope
  • Lessons Learned

3
Johnson Johnson The Company
  • Most broadbased healthcare company in the World
  • 2005 Revenues 50.51 Billion
  • 115,000 employees
  • Manufacturing Operations in Europe, North
    America, South America, Australia, and Asia
  • Annual RD expenditure 4 Billion

4
Johnson Johnson Ireland
  • Celebrated 70 years in Ireland in 2005
  • 6 manufacturing operations in Ireland
  • Over 2000 Employees


Medical Devices
Pharma Chem
Biotechnology
  • DePuy
  • Cordis
  • Vistakon
  • Janssen
  • Alza
  • Centocor

5
Cork Plant Scope
  • Greenfield Manufacturing Site
  • JJs 5th bulk Biotech plant
  • Multi Product Capable
  • Capital spend 735 Million
  • Capable of producing 480 Kgs Product per Year
  • New Generation of Products
  • CNTO 148 (Next Generation of REMICADE)
  • CNTO 1275
  • Other New Molecular Entities currently in RD
    pipeline
  • Employment 311 permanent staff contractors
  • 60-70 of employees will be 3rd level qualified,
    10 will be 4th level qualified.

6
Cork Plant Timeline
7
(No Transcript)
8
(No Transcript)
9
Building Schematics
10
August 2005
11
September 05
12
November 05
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
BioIreland Conference Nov 2006
Application of Lessons Learned (Why are large
scale bio/pharma construction projects so
difficult to execute?)
17
Learning From Past Mistakes
  • Most common mistake involving large
    Biotech/pharma construction projects has been the
    failure to have experienced users involved in the
    initial design of the plant.
  • Second most common mistake is not adequately
    capturing user input and translating it into the
    engineering design and construction
  • The third most common mistake is not giving the
    same priority to developing operational readiness
    as is given to project construction and
    qualification
  • gt Why have these simple mistakes been repeated
    over and over again?

18
Learning From Past Mistakes
  • The principal reason why users are not involved
    early in plant design is due to differing
    abilities of various project groupings to
    mobilize
  • gt Contract Design Houses, Construction Companies
    Owner Engineering depts can invariably mobilize
    much faster than user groups

19
Traditional Project Mobilization
20
User Input
  • Not having Appropriate and Timely user input can
    lead to
  • Schedule impacts due to redesign and rework
  • Cost overruns due to redesign and rework
  • Processes that are difficult to validate
  • Capacity that is less than expected
  • Quality and compliance levels that are not to
    required standards

21
Centocor Plant Mobilization Solution
22
Temporary User Concept
23
Learning From Past Mistakes
  • Most common mistake involving large
    Biotech/pharma construction projects has been the
    failure to have experienced users involved in the
    initial design of the plant.
  • Second most common mistake is not adequately
    capturing user input and translating it into the
    engineering design and construction
  • The third most common mistake is not giving the
    same priority to developing operational
    readinness as is given to project construction
    and qualification

24
Capturing the Voice of the Customer
  • How can we ensure that the voice of the customer
    is captured?
  • Use of Design Excellence
  • A method for systematically capturing and
    integrating user input into the design,
    construction and validation effort.
  • Janssen P3 was the first large-scale
    manufacturing construction project in JJ to
    employ Design Excellence
  • Centocor Cork is the 2nd project.

25
Use of Design Excellence
Voice of the Customer
Stakeholders
Customers/Users
GMP Requirements
Non-GMP Requirements
High Level requirements
Low Level requirements
URS
DeX Scorecard
26
Benefits of Design Excellence
27
Learning From Past Mistakes
  • Most common mistake involving large
    Biotech/pharma construction projects has been the
    failure to have experienced users involved in the
    initial design of the plant.
  • Second most common mistake is not adequately
    capturing user input and translating it into the
    engineering design and construction
  • The third most common mistake is not giving the
    same priority to developing operational readiness
    as is given to plant construction and
    qualification

28
Integrated Project Management
Project Master schedule is divided into the
following Sub-Projects
But..there is something missing! The schedule
above concentrates predominately on building the
plant. The critical missing piece is preparing
the plant to operate in an efficient,
cost-effective and compliant fashion when it is
handed over.
29
Merge Operational Readiness Effort into Master
Project Schedule
Project Directors
Site Leadership Team
Operational Readiness Teams
  • Construction
  • Tech Transfer
  • Identify
  • Tasks
  • Milestones
  • Interdependances
  • Resources

BioCork Integrated Schedule
Merge
Fully Integrated Project/Plant Management Process
30
Fully Integrated Project Schedule
Master Project Schedule
Commissioning
Qualification Validation
Operational Readiness
Construction
Design
Operational Readiness Teams
Project Directors
Owners/users
31
Operational Readiness Teamsexamples
  • EHS Steering
  • EHS Committee
  • Sarbanes Oxley
  • Maintenance Exellence
  • Change Management (system development)
  • Deviation Management (system development)
  • Process Mapping
  • Process Information Systems
  • Training
  • Communications
  • Documentation
  • Labelling
  • SAP Preventative Maintenance
  • HR Time attendance
  • SAP ERP
  • Records Management
  • Asset Management
  • Vendor Management

32
Progress To Date
  • Currently starting Commissioning
  • Project is on schedule
  • Project is on budget
Write a Comment
User Comments (0)
About PowerShow.com