Title: E4014 Construction Surveying
1E4014 Construction Surveying
- Transmission Line Surveys
2Objectives
- provide an understanding of the principles
involved and methods used for surveying
transmission lines
- describe factors that affect the location of
transmission lines - describe the basic principles of the survey and
design of transmission lines
3Objectives (cont)
- understand the survey design required for a
rural extension line
- display a knowledge of the surveys required for
high voltage lines
4Introduction
- Three main types of transmission lines
- (a) rural extension of the distribution network
- ( low high voltage )
- (b) extra high voltage lines carried on towers
- similar design principles apply to types (a) and
(b) - factors are more critical and methods more
accurate for type (b)
5Introduction
- Third type of transmission line
- ( c ) urban distribution network
6Power Supply System
- Generation
- Transmission
- Distribution
7Power Supply System
- electrical energy is generated at the power
stations using 3-phase a.c. generators - voltage and frequency are controled producing a
moderate voltage of, say, 13.8 kV
8Power Supply System
- high voltage transmission lines are used to
transfer electrical energy from the power
stations to the load centres - usually 3-phase overhead conductors suspended
from insulators attached to towers, and called
PRIMARY TRANSMISSION lines - 275kV used in Qld, 330kV in NSW and 500kV in Vic
9Power Supply System
- Transmission (cont)
- power transformers are used at generating
stations to step up or step down the voltages - choice of transmission voltage depends on the
power to be transmitted and the distance involved
10Single Wire Earth Return System ( SWER )
- Low cost, low maintenance method of supplying
power to isolated (country) areas
- An isolating transformer separates the main high
voltage system ( 11kV or 33kV ) from the SWER
line ( 12.7kV to 19.1kV ) - separates the different earthing systems
- a single conductor overhead line feeds a
distribution transformer, which steps-down the
voltage to 2 circuits of 250V, or 1 circuit of
500V
11Single Wire Earth Return System ( SWER )
- The SWER system uses a unique method of passing
the return current through the earth - the resistivity of the earth must be within a
certain range for the system to work effectively
12Basic Principles of Transmission Line Design
- Ideal route between the point of power production
and the point of consumption is a straight line - Design Parameters and regional constraints affect
the location of power lines
13Design Parameters
- Height of Poles or Towers
- Span Length
- Foundations
- Angles
14Design Parameters
- Height of Poles or Towers
- minimum height of transmission lines above the
ground, for road crossings etc is laid down by an
Act of Parliament - most economic design attains this ground
clearance and no more - more height increases span length, but
- increases cost of pole or tower
- increases depth of pole, or
- increases foundation costs of tower
15Design Parameters
- aim is to have as few poles or towers per
kilometre - poles should be placed to maximise span length,
whilst maintaining the minimum clearance
16Design Parameters
- location of poles or towers may affect the type
of foundations required - cost of towers in 1978
- normal foundations - 4 legs, 5m deep, 0.5m
deep 2500 - special foundation - unstable soil 5000
- rock anchor - rocky ground 5000
- piled - mangroves, coastal flats 10000
17Design Parameters
- the pole or tower must be able to withstand the
tension of an indirect pull - poles will need to guyed on the half angle
- angle towers can be up to 20000 more expensive
than an ordinary support tower - essential to keep bends to a minimum
18Design Parameters
- Summary of Design Parameters
- Height of Poles or Towers
- Span Length
- Foundations
- Angles
19Constraints
- Built up areas
- topography
- mountains, forests, rivers, swamps, flood zones
- recreational areas
- national parks, development areas
20Constraints (cont)
- mining areas
- cultivation areas
- future uses
- highways, railways, airstrips
- environment
- aesthetics, erosion
21Rural Extension Surveys
- Extend the power transmission network to small
settlements and farm dwellings - may carry high or low voltage
- low voltage lt 650 volts
- high voltage gt 650 volts
- normal extension is 11kV or 22kV high tension line
22Rural Extension Surveys
- Proposed extension is designed by an electrical
engineer and plotted on existing topographical
and cadastral maps - shows location of all properties to be served
- shows proposed location of transformers etc
- actual route location and design functions are
carried out in the field by the SURVEYOR
23Rural Extension Surveys
- Aim for
- minimum number of poles per kilometre
- minimum number of bends
- minimum ground clearance (6m at 49C)
- minimum clearance over
- road cuttings
- railways
- telephone wires
24Rural Extension Surveys
- minimum cut angle between telephone and power
lines is 45 and parallel lines must be a minimum
of 30m apart to avoid interference and power loss - before undergrounding of power and telephone
lines power lines were often placed 30 - 100m
away from the phone line which was often in the
road reserve - advantages - easy connections to sheds and houses
set back from road - disadvantages - cultivation, access
25Rural Extension SurveysSurvey Design
- Basic survey problem is to obtain a profile of
the land over which the transmission line is to
traverse and to negotiate obstacles unforeseen in
the proposed design - trees, hedges, buildings
etc. - clinometer and chain
- total station
- GPS
26Rural Extension SurveysSurvey Design
- traverse along proposed centreline from the last
pole position - note chainage and RL of grade changes and
features - continue past the next pole position
- plot profile
- horizontal and vertical scales are different
- governed by sag templates provided by Electricity
Authority
27Rural Extension SurveysSurvey Design
28Rural Extension SurveysSurvey Design
- by using the sag template the position of the
next pole is determined
- place a peg at the pole position
- only after the chainage and RL of the point have
been compared to the plot - surveyor should do a reconnaissance survey of the
route before hand so that the topography is known
to some extent
29Rural Extension SurveysSurvey Design
- angles are read
- where a bend occurs
- where a spur or branch line occurs
- place a peg at the bend and at the half angle
- poles will have to be guyed
30Rural Extension SurveysSurvey Design
- if line is traversing private property and
easements are required, then occupation is also
located - running chainage to fence, angle along fence and
distance along fence to cadastral corner
31Rural Extension SurveysSurvey Design
- surveyor has measured
- the profile of the line
- the running chainages and RLs
- the angles at bends
- an accurate plot of the final design is made for
construction, easement and record purposes
32High Voltage Lines on Towers
- Basic design factors are the same
- the following are critical
- cost factor
- foundations
- length of route
- aesthetics and environment
33High Voltage Lines on TowersInitial Design
- most suitable route is chosen based on
- voltage, conductor, tower specification
- topographical maps
- cadastral maps
- town planning schemes
- aerial photos
- local Authorities advice
- other Government Departments advice
- ground reconnaissance
34High Voltage Lines on TowersInitial Design
- report on the route is prepared
- costing
- scheduling
- approval
- environmental impact assessment
- comments of interested Public Authorities
35High Voltage Lines on TowersInitial Design
- route maps are prepared
- 110 000
- latest cadastral information
- number of lines proposed
- easement widths
- current land use
36High Voltage Lines on TowersInitial Design
- contact is made with the owners and occupiers
- negotiate easements and access tracks
- property owners ( and other interested parties )
may object - property owners may state their intended future
use of the land
- if objections justify an amendment then the
centre line may be re-routed
37High Voltage Lines on Towers Survey of the Route
- high accuracy required
- control survey for whole of the route
- centre lines are cleared, surveyed and marked
- further public reaction may be forthcoming and
the route may be deviated again - keep lines to a minimum height for aesthetic
reasons
38High Voltage Lines on Towers Survey of the Route
- surveyor locates towers and access tracks
- appreciate land usage and erosion
- report all relevant circumstances particularly
those affecting overall location
- field data must show enough data for the towers
to be located and their positions to be checked
in the office
39Urban Distribution Network
- Transmission lines are entirely located in the
road or street reserve - span length is not as important
- poles are place to service as many consumers as
possible - design and survey is usually carried out by
electrical engineers and their staff - underground transmission conduits
- at least 5 times more expensive