E4014 Construction Surveying - PowerPoint PPT Presentation

1 / 39
About This Presentation
Title:

E4014 Construction Surveying

Description:

understand the survey & design required for a rural extension line ... advantages - easy connections to sheds and houses set back from road ... – PowerPoint PPT presentation

Number of Views:1904
Avg rating:3.0/5.0
Slides: 40
Provided by: wol45
Category:

less

Transcript and Presenter's Notes

Title: E4014 Construction Surveying


1
E4014 Construction Surveying
  • Transmission Line Surveys

2
Objectives
  • provide an understanding of the principles
    involved and methods used for surveying
    transmission lines
  • describe factors that affect the location of
    transmission lines
  • describe the basic principles of the survey and
    design of transmission lines

3
Objectives (cont)
  • understand the survey design required for a
    rural extension line
  • display a knowledge of the surveys required for
    high voltage lines

4
Introduction
  • Three main types of transmission lines
  • (a) rural extension of the distribution network
  • ( low high voltage )
  • (b) extra high voltage lines carried on towers
  • similar design principles apply to types (a) and
    (b)
  • factors are more critical and methods more
    accurate for type (b)

5
Introduction
  • Third type of transmission line
  • ( c ) urban distribution network

6
Power Supply System
  • Generation
  • Transmission
  • Distribution

7
Power Supply System
  • Generation
  • electrical energy is generated at the power
    stations using 3-phase a.c. generators
  • voltage and frequency are controled producing a
    moderate voltage of, say, 13.8 kV

8
Power Supply System
  • Transmission
  • high voltage transmission lines are used to
    transfer electrical energy from the power
    stations to the load centres
  • usually 3-phase overhead conductors suspended
    from insulators attached to towers, and called
    PRIMARY TRANSMISSION lines
  • 275kV used in Qld, 330kV in NSW and 500kV in Vic

9
Power Supply System
  • Transmission (cont)
  • power transformers are used at generating
    stations to step up or step down the voltages
  • choice of transmission voltage depends on the
    power to be transmitted and the distance involved

10
Single Wire Earth Return System ( SWER )
  • Low cost, low maintenance method of supplying
    power to isolated (country) areas
  • An isolating transformer separates the main high
    voltage system ( 11kV or 33kV ) from the SWER
    line ( 12.7kV to 19.1kV )
  • separates the different earthing systems
  • a single conductor overhead line feeds a
    distribution transformer, which steps-down the
    voltage to 2 circuits of 250V, or 1 circuit of
    500V

11
Single Wire Earth Return System ( SWER )
  • The SWER system uses a unique method of passing
    the return current through the earth
  • the resistivity of the earth must be within a
    certain range for the system to work effectively

12
Basic Principles of Transmission Line Design
  • Ideal route between the point of power production
    and the point of consumption is a straight line
  • Design Parameters and regional constraints affect
    the location of power lines

13
Design Parameters
  • Height of Poles or Towers
  • Span Length
  • Foundations
  • Angles

14
Design Parameters
  • Height of Poles or Towers
  • minimum height of transmission lines above the
    ground, for road crossings etc is laid down by an
    Act of Parliament
  • most economic design attains this ground
    clearance and no more
  • more height increases span length, but
  • increases cost of pole or tower
  • increases depth of pole, or
  • increases foundation costs of tower

15
Design Parameters
  • Span Length
  • aim is to have as few poles or towers per
    kilometre
  • poles should be placed to maximise span length,
    whilst maintaining the minimum clearance

16
Design Parameters
  • Foundations
  • location of poles or towers may affect the type
    of foundations required
  • cost of towers in 1978
  • normal foundations - 4 legs, 5m deep, 0.5m
    deep 2500
  • special foundation - unstable soil 5000
  • rock anchor - rocky ground 5000
  • piled - mangroves, coastal flats 10000

17
Design Parameters
  • Angles
  • the pole or tower must be able to withstand the
    tension of an indirect pull
  • poles will need to guyed on the half angle
  • angle towers can be up to 20000 more expensive
    than an ordinary support tower
  • essential to keep bends to a minimum

18
Design Parameters
  • Summary of Design Parameters
  • Height of Poles or Towers
  • Span Length
  • Foundations
  • Angles

19
Constraints
  • Built up areas
  • topography
  • mountains, forests, rivers, swamps, flood zones
  • recreational areas
  • national parks, development areas

20
Constraints (cont)
  • mining areas
  • cultivation areas
  • future uses
  • highways, railways, airstrips
  • environment
  • aesthetics, erosion

21
Rural Extension Surveys
  • Extend the power transmission network to small
    settlements and farm dwellings
  • may carry high or low voltage
  • low voltage lt 650 volts
  • high voltage gt 650 volts
  • normal extension is 11kV or 22kV high tension line

22
Rural Extension Surveys
  • Proposed extension is designed by an electrical
    engineer and plotted on existing topographical
    and cadastral maps
  • shows location of all properties to be served
  • shows proposed location of transformers etc
  • actual route location and design functions are
    carried out in the field by the SURVEYOR

23
Rural Extension Surveys
  • Aim for
  • minimum number of poles per kilometre
  • minimum number of bends
  • minimum ground clearance (6m at 49C)
  • minimum clearance over
  • road cuttings
  • railways
  • telephone wires

24
Rural Extension Surveys
  • minimum cut angle between telephone and power
    lines is 45 and parallel lines must be a minimum
    of 30m apart to avoid interference and power loss
  • before undergrounding of power and telephone
    lines power lines were often placed 30 - 100m
    away from the phone line which was often in the
    road reserve
  • advantages - easy connections to sheds and houses
    set back from road
  • disadvantages - cultivation, access

25
Rural Extension SurveysSurvey Design
  • Basic survey problem is to obtain a profile of
    the land over which the transmission line is to
    traverse and to negotiate obstacles unforeseen in
    the proposed design - trees, hedges, buildings
    etc.
  • clinometer and chain
  • total station
  • GPS

26
Rural Extension SurveysSurvey Design
  • traverse along proposed centreline from the last
    pole position
  • note chainage and RL of grade changes and
    features
  • continue past the next pole position
  • plot profile
  • horizontal and vertical scales are different
  • governed by sag templates provided by Electricity
    Authority

27
Rural Extension SurveysSurvey Design
28
Rural Extension SurveysSurvey Design
  • by using the sag template the position of the
    next pole is determined
  • place a peg at the pole position
  • only after the chainage and RL of the point have
    been compared to the plot
  • surveyor should do a reconnaissance survey of the
    route before hand so that the topography is known
    to some extent

29
Rural Extension SurveysSurvey Design
  • angles are read
  • where a bend occurs
  • where a spur or branch line occurs
  • place a peg at the bend and at the half angle
  • poles will have to be guyed

30
Rural Extension SurveysSurvey Design
  • if line is traversing private property and
    easements are required, then occupation is also
    located
  • running chainage to fence, angle along fence and
    distance along fence to cadastral corner

31
Rural Extension SurveysSurvey Design
  • surveyor has measured
  • the profile of the line
  • the running chainages and RLs
  • the angles at bends
  • an accurate plot of the final design is made for
    construction, easement and record purposes

32
High Voltage Lines on Towers
  • Basic design factors are the same
  • the following are critical
  • cost factor
  • foundations
  • length of route
  • aesthetics and environment

33
High Voltage Lines on TowersInitial Design
  • most suitable route is chosen based on
  • voltage, conductor, tower specification
  • topographical maps
  • cadastral maps
  • town planning schemes
  • aerial photos
  • local Authorities advice
  • other Government Departments advice
  • ground reconnaissance

34
High Voltage Lines on TowersInitial Design
  • report on the route is prepared
  • costing
  • scheduling
  • approval
  • environmental impact assessment
  • comments of interested Public Authorities

35
High Voltage Lines on TowersInitial Design
  • route maps are prepared
  • 110 000
  • latest cadastral information
  • number of lines proposed
  • easement widths
  • current land use

36
High Voltage Lines on TowersInitial Design
  • contact is made with the owners and occupiers
  • negotiate easements and access tracks
  • property owners ( and other interested parties )
    may object
  • property owners may state their intended future
    use of the land
  • if objections justify an amendment then the
    centre line may be re-routed

37
High Voltage Lines on Towers Survey of the Route
  • high accuracy required
  • control survey for whole of the route
  • centre lines are cleared, surveyed and marked
  • further public reaction may be forthcoming and
    the route may be deviated again
  • keep lines to a minimum height for aesthetic
    reasons

38
High Voltage Lines on Towers Survey of the Route
  • surveyor locates towers and access tracks
  • appreciate land usage and erosion
  • report all relevant circumstances particularly
    those affecting overall location
  • field data must show enough data for the towers
    to be located and their positions to be checked
    in the office

39
Urban Distribution Network
  • Transmission lines are entirely located in the
    road or street reserve
  • span length is not as important
  • poles are place to service as many consumers as
    possible
  • design and survey is usually carried out by
    electrical engineers and their staff
  • underground transmission conduits
  • at least 5 times more expensive
Write a Comment
User Comments (0)
About PowerShow.com