Title: Change Orders
1Change Orders
- As always, you all try and administer contracts
as written, but designers (maintainers) cannot
for see every problem that may arise. Crap
happens, you all just get to clean it up. - Need to try and establish a cost BEFORE
contractor submits you a price. In other words,
have a price in mind before they give you one
2KYTC updated guidance manual should be helpful
- http//transportation.ky.gov/construction/ConstGui
dManl/GuideManlIndx.htm
3Possible Change to Contract
- Consult with District Construction TEBM and/or
DCE Central Office Liaison. (on-site, phone,
e-mail) - If FHWA oversight (APD, interstate or TN river
Bridge) make sure FHWA liaison informed. - Draft Proposed Change Order in SM. Send HTML or
PDF via e-mail for review, then apply REVIEW in
SiteManager, sending an e-mail notice
4Change Order Creation
- Funding issues may require a new Category or
Project to be added in Contract, contact Beth
Combs with information. - Supplemental items require a price submittal from
Contractor. Make sure the price is justified.
i.e. Average Prices 2008 or Labor-Material-Equipme
nt analysis - Some supplemental items of work that are Contract
Items for example Fuel Asphalt Adjustments are
at Unit Price of 1.00 and Quantity of Dollars
calculated.
5SiteManagerChange Orders continued
- Keep current on submittals
- Send for Review in SiteManager to
- Section Engineer,
- District (TEBM for PPD),
- Construction Change Order manager (bcombs),
- Div of Construction (Director and DO liaison),
- DSHE for Project Delivery (Chuck Knowles)
- and If applicable FHWA liaison..
6SiteManagerChange Orders continued
- Be sure to create an e-mail alerting above
parties to Review in SM. Also include CDE
(Executive Director for District), Creator of
Project (Design, Maintenance or Rural Roads)
DME by e-mail only for information - If changed during Draft Review, make sure all
parties are sent new copy. Money for Review copy
needs to match submitted copy. If you have to
change money during review, make sure to let Beth
Combs know so she can create a new funding sheet
for submittal to SHE office.
7Change order e-mail Notice
E-mail should Include ContID Change Order Number.
Brief overall Description of Change and HTML
attachment of change order to reviewers. This
alerts individuals that it is ready for REVIEW.
The attachment should be CHOR report (Change
Order Funding report). Attachment file name
should have ContIDCO ie 071210-003 (default
HTML name)
8Change Order Explanations
- Brief but explain the problem and solution.
- If supplemental item need to reference how price
established (average. bid cost, breakdown, etc) - Mention item of work in explanation. Do not put
simply this item - example
- 8001 8002 GUARDRAIL-Material Only these items
are for invoice paid for remainder of guardrail
quantities on grade contract and will be
installed as an "install only" price on the
surfacing contract. This will allow for the grade
contract to be completed.
9SiteManagerChange Orders continued
- Put a standard reason code on items in change
order
10SiteManager REVIEW
- During the REVIEW process, the change order is in
DRAFT status. If any major changes (adding
items, changing prices) are made. Notification
should be made to all parties. - Spelling or minor grammar changes do not required
full re-review. - After reviewed by DSHE for Project Preservation
Delivery (cknowles) and if applicable FHWA the
change order signature report is signature by TE
Section Supervisor for PPD and CHE then it is
ready for formal submittal to contractor for
signature.
11SiteManager Change Orders HTML or PDF report
- To create a copy from SiteManager for review,
create report, open file, save as HTM, open HTM
file in browser and send that via e-mail. The
HTM can be viewed from e-mail. No need to scan
or paste into WORD, use the HTM file.
12Prequalified Contact Link
- http//transportation.ky.gov/Contract/Pqbook.pdf
- Request an e-mail at Pre-Construction meeting for
submitting Change Orders and Pay Estimates.
13SiteManagerChange Orders continued
- Ready for Signature after reviews completed by
- TE Section Supervisor
- District (TEBM for PPD),
- CO Construction (bcombs),
- Div of Construction (Director and/or DO liaison),
DSHE for Project Delivery (Cknowles), - if applicable FHWA liaison.
14List ready for PEND statussent periodically
15SiteManager Change order
- If in Pending but need to change, put back into
DRAFT, make corrections send for review before
putting back into PEND. RE should NOT deny in
PENDING STATUS.
16Change Order Signature Report
- TE Supervisor for PPD CDE (Chief District
Engineer) are to sign the change order as
requested by and mail (or deliver) to contractor
for signature and further submittal to State
Highway Engineers Office. - Correct Address
- State Highway Engineers Office
- Attn DSHE for PDP
- TCOB 6th Floor
- 200 Mero Street
- Frankfort, KY 40622
17Change Order Signature Report
- SM is updated to PEND status and date applied for
when mailed to contractor with instructions to
mail to SHE address. - When signed Change Order received in SHE office
from contractor, SM approval level 2 date is
updated . This cannot be applied until Level 1
date is applied!
18SiteManagerChange Orders Pending approvals
- Approval Levels are
- Level 1 Contractor- (Project Engineer) this
indicates when change order mailed to Contractor
after KYTC DO signatures - Level 2 Deputy State Highway Engineer (linman)
Once date inserted, indicates Change Order from
Contractor received in Central Office.
19Change Order Signature Report
- Level 3 State Highway Engineer (by blewis) Once
date inserted, indicates approved by State
Highway Engineer and passed to Div of Accounts
for uploading into system - Level 4 Final Approval e-Mars Change Order
(bcombs) approval indicates date received from
Accounts and ready for use in SiteManager,
should be fully funded.
20Payment for Change Order Items
- After Change Order has been put in APRV status,
payment can be made on items included in the
change order. They are now part of the contract. - Approved Change order copies then mailed out by
Division of Construction to Contractor, e-mailed
to District.
21Robert C. Lewis, PE Assistant State Highway
Engineer State Highway Engineers Office TCOB 6th
Floor 200 Mero Street Frankfort, KY 40622 E-mail
Bob.lewis_at_ky.gov Cell 502-330-3470 Office
502-564-3730 ext 3129