Title: ENERGY UPDATE URBANA CAMPUS
1ENERGY UPDATE URBANA CAMPUS -
2Urbana Campus Energy Costs
- FY 2003 26,612,000
- FY 2004 35,684,000 (34)
- FY 2005 52,282,000 (47)
- FY 2006 70,778,000 (35)
- FY2007 58,830,000 (-17)
- FY2008 78,449,000 (33)
- 03 thru 08 deficit approx. 90 million
3How do we compare?
4Some Good News
- FS Retro-commissioning Team
- - Completed gt 1 million GSF
- - Average energy reduction of 21
- - KCPA reduction approx. 40
- - FS now forming RCx Team 2
- Consulting firm SAIC enterprise-wide study of
UofI utility production consumption - Urbana steam consumption down approx. 12 FY06 to
FY08
5Krannert Center Retro-commissioning
- Performed Nov - Dec 2007
- Eight months of metered results
- Electricity reduction 18
- Chilled water reduction 19
- Steam reduction 50
- Annual Savings - 400,000
- Retro-commissioning cost - 188,000
- Simple Payback lt 6 months
Photo by Dan OBrien
6More Good News .
- Major lighting upgrade program underway
- Natural gas prices are down
- Mild winter predicted
- Increasing campus awareness
7AND THE NOT-SO-GOOD NEWS
- Price of coal is up significantly
- Campus electricity usage still increasing up
another 3.1 in FY08 - No approval to employ Energy Service Contractors
8Recent Years
Steam Use Electricity Campus
GSF FY2006 2,756 Mlbs 423,528 Mwhr
19,288,962 FY2007 2,609 Mlbs 438,586
Mwhr 19,433,439 FY2008 2,418 Mlbs 452,375
Mwhr 20,113,569 FY 07 EUI 315,447
Btu/GSF/Yr FY 08 EUI 304,302 Btu/GSF/Yr
9Ten Year Energy Goals
- Reduce energy consumption from FY07 levels by
10 over the next 3 years - Reduce energy consumption from FY11 levels by
15 over the following 2 to 6 yrs
10Electricity Use at Nevada St. ICS Lab
11Key Players
- Dave Ruby, CITES ICS
- Lab supervisor, CITES ICS
- Eva Sweeney, Electrical Engineer, FS
- Sanja Koric, Electrical Engineer, FS
- Robert Halverson, Supervising Engineer, FS
12Nevada St. lab
- 2,438 Gross Square Feet
- 53 iMacs
- 12 PCs
- 2 HVAC systems, X thermostats
- 1 vending machine
- 1 printer
- Fluorescent lighting
-
13Approach
- Install electrical sub-metering, separating
computer power from HVAC and other major loads - Monitor power consumption over time for varying
modes of ICS lab operation - Analyze data for operating modes that save energy
(or not.)
14Timeline
- Installed metering June, 2008
- Began recording electricity use and temperature
date June 26, 2008 - Downloaded data weekly
15ICS Lab Hours
- 1. Summer open 6 hrs/day
- 2. Fall Semester open 12 hrs/day
- Computer Modes
- A. Normal Operation
- -no standby hibernate disabled-hard disk
on-screen saver 10min-monitor off 20min - B. No Sleep Mode
- C. Manual Off
16Summer weekly electricity usage two operating
modes
- Normal with no
- Operation sleep mode
- Computer usage 291 kwh 586 kwh
- Computer cooling 91 kwh 183 kwh
- Total 382 kwh 769 kwh
- Difference is worth 35 per week at normal
summer electricity rates -
17Fall weekly electricity usage two operating modes
- Normal Manual
- Operation Off
- Computer usage 594 kwh 302 kwh
- Computer cooling 165 kwh 84 kwh
- Total 759 kwh 386 kwh
- Difference is worth 25 per week at Fall
electricity rates -
18(No Transcript)
19Fall Semester
- On average, 73 of the buildings Fall
electrical usage was power to workstations and
the A/C required to cool them
20Summer Semester
- On average, 35 of the buildings summer
electrical use power to workstations and the A/C
required to cool them
21IT Pro Guidelines Document
- Being Developed on IT Pro Wiki Space
- https//wiki.cites.uiuc.edu/wiki/x/mwGgAQ
- Audience
- Living Document
22IT Pro Guidelines Document
- Living Document
- Comment and Edit
- Contribute Research Findings and Analysis
- Document what your unit is doingand find out
what others are doing