Title: TransCanada Pipeline Overview
1TransCanada Pipeline - Overview
- Wisconsin Distributor Group
- October 1, 2008
- Milwaukee, WI
2TransCanada U.S. Pipelines Central
- Introductions
- Martin Wilde Director, Marketing
- Gas Control Operations
- Steve Jaskolski Manager, Gas Control
- Commercial Activities
- Joe Pollard - Director, Transportation Services
- Other
- Q A
3Summer 2008 Operations
4Significant Items During the 2008 Summer Season
- Working storage is fully subscribed for
2008/2009. April 1 starting content was 83-Bcf
(35 full). - Cold Springs 1 was placed into service in the
Spring. Field has a working gas capacity of
14-Bcf and maximum deliverability of 200-MMcf/d. - Average injection rate for this summer season to
date has been 0.79-Bcf/d. - ANR posted storage restrictions on interruptible
storage beginning September 11th. Specifically,
DDS and MBS customers were required to reduce
their remaining storage inventory volume to the
September 10th allocated ending balance level by
October 31st. - Physical storage is approximately 91 full as of
September 28th.
5Significant Items During the 2008 Summer Season
- MLS Issues/Risk Analysis study completed and
options/recommendations have been presented to
Executive Management for consideration. - GLGT Integration Status Gas Control / Operation
Control functions relocated to Houston in May,
2008. - Wisconsin Notification Process (Abnormal
Operations) will be routed to all parties in
the next week for updates.
6Monthly Cooling Degree Day Comparison C(W)TN
COLDER (WARMER) THAN NORMAL
Milwaukee
Green Bay
2007 Summer
2008 Summer
- Milwaukee was 4 CTN for the Summer 2008 and
(25) WTN for Summer 2007.
- Green Bay was (2) WTN for the Summer 2008 and
(35) WTN for Summer 2007 .
30 Year Normal
As of September 25, 2008.
7ANR SYSTEM STORAGE - COMPARISON OF DAILY
BALANCESAPRIL 1 THRU OCTOBER 31
10/31
8ANR System Combustion Turbine Capacity
19982008
ANRPL Operations Control
9Wisconsin Combustion Turbine Capacity
19982008
ANRPL Operations Control
10ANR System Power Generation Volumes
MMDth
ANRPL Operations Control
September 2008 Estimate
11Wisconsin Power Generation Volumes
MMDth
ANRPL Operations Control
September 2008 Estimate
12Winter 2008-2009 Operations
13ANR Pipeline SystemSystem Peak Day Capacity
Units in MDth/d
Crystal Falls 890
Marshfield 325
Storage (owned and contracted) 3,700
Janesville 120
Bridgman East 1,364
Joliet Area 701
SW Mainline 727
Lebanon (410)
SE Mainline 1,435
ANRPL Operations Control
14ANR Pipeline SystemWisconsin Design Day Capacity
Winter 2008/2009
ANRPL Operations Control
15Winter 2008/2009 Available Firm Capacities
- MLS/St. John 94 Subscribed
- Wisconsin Fully Subscribed
- Lebanon - Fully Subscribed
16Significant Items for the 2008/2009 Winter Season
- No known system or facility issues that would
impact ANRs operating ability during the
upcoming heating season. - Modifications at Bridgman and St. John to valve
operator electronics and re-clamping of discharge
piping to dampen vibration. - Fabricate a custom lid for valves at St. John to
eliminate water leaking on the valve seals and
the associated potential for freeze-offs. - Changed out solenoid valves at Weyauwega to
replace electric over gas with air service to
mitigate freezing.
17Significant Items for the 2008/2009 Winter
Season Cont.
- Revised Field Operations Service Level
Agreement with Gas Control for operationally
critical areas. - GLGT Gas Control has been integrated into Houston
Gas Control and will operate in conjunction with
ANR, providing increased operational strength
during peaking operations (i.e., Fortune Lake,
Reverse Flow Operations, etc.).
18Maintenance Schedule 2008-2009
19ANR Maintenance Projects October 2008
- MLS - St. John W-E Capacity Reduction
- 9/29 10/3 100-MMcf/d for St. John Maintenance
- 10/6 10/10 100-MMcf/d for St. John Maintenance
- 10/13 10/17 200-MMcf/d for Bridgman
Maintenance - IT Firm Secondary Service Impacted
- MLN Capacity Reduction
- 10/01 11/07 352-MMcf/d for Pipeline
Maintenance - No Service Impact Anticipated
20ANR Maintenance Projects October 2008
- 20 1-301 Line Class Change
- Kewaskum-CFTP Capacity Reduction
- 202-MMcf/d (leaving 303-MMcf/d)
- Sept 29 Oct 24
- No Service Impact Anticipated
- SWML Compressor Maintenance
- SWML-CFTP Capacity Reduction
- 48-MMcf/d Reduction
- Oct 6 Oct 10
- IT Firm Secondary Service Impacted
- SWML Pigging Operations
- SWML-CFTP Capacity Reduction
- Firm Primary Nominations Only
- October 6 8
- IT Firm Secondary Service Impacted
21ANR Maintenance Projects 2008 Potential Service
Impacts and Schedule Changes
- Service Impacts are estimates. Actual
nominations, markets, weather and pipeline
conditions, etc. will determine any level of
curtailments. - Projects may be added, altered, delayed or
cancelled. Emergent work cannot be planned and
will happen from time to time. - ANR will provide notice of such planned work,
including any additions or changes, via a posting
under the Planned Service Outage (PSO) category
on GEMS. Emergent work will be posted under the
Critical category as soon as possible.
22ANR Pipeline CompanySE Gathering AreaSystem
Facilities From Hurricane IKE
ANRPL Operations Control
23EI 296 Platform
24(No Transcript)
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29ANR Pipeline Winter 2007/2008 Capacity Cuts
Abbotsford Jan 08 5 days Mar 08 3 days
Extreme Conditions Declared 1/18/08 1/25/08
1/30/08 1/31/2008 2/9/08 2/16/2008
2/20/2008 2/22/2008
St. John Nov 07 5 days Mar 08 5 days
Madison Lateral North Jan 08 2 days
Monclova/Maumees Feb 08 1 day
Joliet NGPL Nov 07 1 day
30Q AThank you.