Project Management Systems - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Project Management Systems

Description:

Organizes Work Packages in a logical fashion. Encompasses all Work Packages ... Shows tasks planned vs. task percent complete and tasks completed ... – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 34
Provided by: andyd6
Category:

less

Transcript and Presenter's Notes

Title: Project Management Systems


1
Project Management Systems Scheduling MT 246 -
Module 9
2
Topics Covered Previously
  • Work Definition
  • After System is defined, all development items
    are known, and work packages can be defined
  • Work Package (Summary Task) Development
  • Smallest managed unit of a project
  • Broken into tasks
  • Assigned to Work Package (Subproject) manager
  • Formal Project Reporting Requirement
  • Relates directly to system deliverables

3
Topics Covered Previously (contd)
  • Task Definition
  • Tasks are the fundamental component of Work
    Packages
  • Explicit inputs and outputs
  • Explicit Start and Stop Date
  • Work Breakdown Structure
  • Organizes Work Packages in a logical fashion
  • Encompasses all Work Packages
  • Allows assignment of Work Packages to the project
    organization via the Responsibility Matrix

4
Topics Covered Previously (contd)
  • Estimating
  • Methodology for definition of cost of each task
  • Establish Labor Rates for each type of labor
  • Determine man-hours for each task by type of
    labor
  • Determine Material Cost for each task
  • Determine ODC for each task
  • Demonstrated examples from Construction Estimator

5
Responsibility Matrix
  • Documents the intersection of the WBS and the
    functional organization
  • Assigns all work packages to organizational units
  • Key feature is accountability
  • Single point of contact for each work package
  • Subproject manager is responsible for
    Cost/Schedule/Technical
  • All work packages must be assigned to someone!!

6
Responsibility Matrix
  • Fig 6-8

7
Project Management System
  • Collection of tools which captures and controls
    all aspects of project management
  • Project Org Charts and Responsibility Matrix
  • Defines all work via WBS and task descriptions
  • Documents Budgets for all Work Packages
  • Captures Cost and Schedule information
  • Captures technical info via System Engineering
  • Provides analysis and reporting (cost/schedule)
  • Formal Revision Control

8
Revision Control Process
  • Project Management System imposes formal revision
    control
  • Changes to budgets require written PM and
    Customer approval
  • Changes to schedules require written PM and
    Customer approval
  • Changes to specifications require written PM and
    Customer approval

9
Revision Control Process (Continued)
  • All changes are formally documented and
    configuration managed
  • Transmitted via Contracts Letters between Buyer
    and Seller
  • Change control boards
  • Forms with revision letters and signatures of
    approval

10
Scheduling
  • Parallel task to WBS development
  • Captures time phasing of project tasks
  • Essentially a project road map
  • Composed of Tasks and Milestones
  • Updated regularly (at least monthly) during
    project life
  • All Work Packages have a standalone schedule
  • Developed, controlled, and updated by WP Manager
  • Tiers up to Total Project Schedule

11
Scheduling (Continued)
  • Work Packages are the work planned
  • Road to project goals
  • Time, money, manpower, equipment
  • Events and Milestones do not consume resources
  • Signpost along the road (time)
  • Event is start or end of WP
  • Milestone is Point in time of significance to a
    project
  • Contract Award
  • Delivery of Hardware, Software, etc.

12
Types of Schedules
  • Purpose is to display project schedule in a 2D
    graph or network
  • Developed from analysis of WBS and Work Package
    tasks
  • Simplest is Gantt, or Bar Chart
  • Most complex is Schedule Network
  • Precedence (logic) diagram with task duration and
    interrelationships

13
Scheduling Historical Context
  • Gantt Charts were invented during World War I as
    a means of controlling Cost/Schedule
  • Henry Gantt, Management Consultant
  • Means of visually portraying the status of
    Programs
  • Shows tasks planned vs. task percent complete and
    tasks completed
  • Refined during the 1950s and 1960s as a result of
    cost overruns on large development projects
  • Provide a means of relating Cost/Schedule via
    Manpower and Cost Curves

14
Gantt Chart Features
  • Display events (or milestones) and activities
    (tasks) as a function of time
  • Tasks and Milestones are described on left
    margin, with bars in graph area (Y-Axis)
  • Length of bar is equal to task duration
  • Placement of left side of bar equals task start
    date
  • Time is displayed on X-Axis
  • Task/Milestone sequence
  • Early Tasks/Milestones at top of chart
  • Later Tasks/Milestones progress down the page

15
Gantt Chart Features (Continued)
  • Gantt Charts vary in detail
  • Roll Up into Summary Tasks
  • Appropriate for different management levels
  • Task relationships are implicit, sometimes
    indicated by dotted lines
  • Progress indicated by shading of task bars in
    proportion to Percent Complete

16
Gantt Chart
  • Figure 6-10

17
Setting up a Gantt Chart
  • H must be completed before
  • I and J can be started
  • J must be completed before
  • K,L and M can be started
  • I must be completed before
  • N, O and P can be started

18
Task Relationships
  • To be useful, schedule must show task
    relationships
  • Earlier tasks that must be finished prior to
    starting follow-on tasks
  • Precedence Relationships
  • Common Task Relationships
  • Start/Start
  • Finish/Start
  • Finish/Finish

19
Setting up a Gantt Chart (Continued)
20
Schedule Baseline
  • After Contract Award, all Sub Project Managers
    change their Work Packages to reflect the latest
    knowledge
  • Design Changes
  • Schedule Changes
  • Project manager Reviews/Approves all schedules
  • Schedules are placed under formal revision
    control
  • Any changes made to schedule must be approved by
    PM and Customer
  • Schedule is Updated from that point forward

21
Updating of Gantt Charts
  • Review date is indicated by a vertical line on
    chart
  • Tasks are blackened to a bar length that is
    equal to the Percent Complete of the task
  • Update procedure allows a manager to visualize
    task status
  • Tasks completed early
  • Tasks scheduled to be complete, but are now late
  • Tasks that have not started, but should have been
    initiated
  • Tasks that are on schedule

22
Gantt Chart for Work Progress
23
Percent Complete
  • All tasks must be Measurable
  • Measurable means that the Work Package Manager
    must be able to assess how far along a given
    task is at the time of the Project Review
  • Generally based on engineering judgment
  • Must be objective, not subjective
  • How Far Along is essentially Percent Complete
  • Be careful about Thermometer Charts

24
Gantt Chart for Weekly and Cumulative Expenses
25
Schedule Hierarchy
  • In order to avoid confusion, schedules are
    provided to varying levels of detail
  • Rolling Up tasks into Summary Tasks for each
    Work Project
  • Level of detail depends on the reviewer
  • Must establish a formal relationship between
    schedules
  • Similar to WBS Indenturing
  • Formally controlled via the PMS Procedures

26
Schedule Hierarchy Example
27
Multilevel Schedule
28
Gantt Chart Showing Work Progress (Computer
Generated)
  • Fig 6-16

29
Gantt Chart Showing Multilevel Schedule (Computer
Generated)
30
Disadvantages of Gantt Charts
  • Task relationships are not easily displayed
  • Effect of task delay is not easily seen
  • Problem gets worse with project complexity
  • These problems resulted in the development of
    schedule networks
  • Covered in the next two lectures
  • This deficiency has been largely overcome by the
    use of micro-computers
  • Gantt vs. Network view of data

31
Homework Assignment Preview
  • Construction Project
  • Garage with workroom
  • 30 feet X 40 feet
  • Develop Cost Estimate
  • Use subset of information provided in Module 8
  • Develop Schedule
  • Provide logical relationship of tasks
  • Assign Task Duration
  • Assign manpower by labor grade

32
Homework Assignment Preview (Continued)
  • Develop Manpower Curve
  • Use Microsoft Project
  • Due 22 February (Thursday)
  • Homework value 50 Points

33
Next Lecture
  • Read Nicholas Chapter7
  • Install Microsoft Project
  • Save Files of following Questions for future use
  • Work Review Questions 6.17, 6.20, 6.22, 6.23,
    6.25,6.26, 6.28, 6.29
Write a Comment
User Comments (0)
About PowerShow.com