Title: Project Management Systems
1Project Management Systems Scheduling MT 246 -
Module 9
2Topics Covered Previously
- Work Definition
- After System is defined, all development items
are known, and work packages can be defined - Work Package (Summary Task) Development
- Smallest managed unit of a project
- Broken into tasks
- Assigned to Work Package (Subproject) manager
- Formal Project Reporting Requirement
- Relates directly to system deliverables
3Topics Covered Previously (contd)
- Task Definition
- Tasks are the fundamental component of Work
Packages - Explicit inputs and outputs
- Explicit Start and Stop Date
- Work Breakdown Structure
- Organizes Work Packages in a logical fashion
- Encompasses all Work Packages
- Allows assignment of Work Packages to the project
organization via the Responsibility Matrix
4Topics Covered Previously (contd)
- Estimating
- Methodology for definition of cost of each task
- Establish Labor Rates for each type of labor
- Determine man-hours for each task by type of
labor - Determine Material Cost for each task
- Determine ODC for each task
- Demonstrated examples from Construction Estimator
5Responsibility Matrix
- Documents the intersection of the WBS and the
functional organization - Assigns all work packages to organizational units
- Key feature is accountability
- Single point of contact for each work package
- Subproject manager is responsible for
Cost/Schedule/Technical - All work packages must be assigned to someone!!
6Responsibility Matrix
7Project Management System
- Collection of tools which captures and controls
all aspects of project management - Project Org Charts and Responsibility Matrix
- Defines all work via WBS and task descriptions
- Documents Budgets for all Work Packages
- Captures Cost and Schedule information
- Captures technical info via System Engineering
- Provides analysis and reporting (cost/schedule)
- Formal Revision Control
8Revision Control Process
- Project Management System imposes formal revision
control - Changes to budgets require written PM and
Customer approval - Changes to schedules require written PM and
Customer approval - Changes to specifications require written PM and
Customer approval
9Revision Control Process (Continued)
- All changes are formally documented and
configuration managed - Transmitted via Contracts Letters between Buyer
and Seller - Change control boards
- Forms with revision letters and signatures of
approval
10Scheduling
- Parallel task to WBS development
- Captures time phasing of project tasks
- Essentially a project road map
- Composed of Tasks and Milestones
- Updated regularly (at least monthly) during
project life - All Work Packages have a standalone schedule
- Developed, controlled, and updated by WP Manager
- Tiers up to Total Project Schedule
11Scheduling (Continued)
- Work Packages are the work planned
- Road to project goals
- Time, money, manpower, equipment
- Events and Milestones do not consume resources
- Signpost along the road (time)
- Event is start or end of WP
- Milestone is Point in time of significance to a
project - Contract Award
- Delivery of Hardware, Software, etc.
12Types of Schedules
- Purpose is to display project schedule in a 2D
graph or network - Developed from analysis of WBS and Work Package
tasks - Simplest is Gantt, or Bar Chart
- Most complex is Schedule Network
- Precedence (logic) diagram with task duration and
interrelationships
13Scheduling Historical Context
- Gantt Charts were invented during World War I as
a means of controlling Cost/Schedule - Henry Gantt, Management Consultant
- Means of visually portraying the status of
Programs - Shows tasks planned vs. task percent complete and
tasks completed - Refined during the 1950s and 1960s as a result of
cost overruns on large development projects - Provide a means of relating Cost/Schedule via
Manpower and Cost Curves
14Gantt Chart Features
- Display events (or milestones) and activities
(tasks) as a function of time - Tasks and Milestones are described on left
margin, with bars in graph area (Y-Axis) - Length of bar is equal to task duration
- Placement of left side of bar equals task start
date - Time is displayed on X-Axis
- Task/Milestone sequence
- Early Tasks/Milestones at top of chart
- Later Tasks/Milestones progress down the page
15Gantt Chart Features (Continued)
- Gantt Charts vary in detail
- Roll Up into Summary Tasks
- Appropriate for different management levels
- Task relationships are implicit, sometimes
indicated by dotted lines - Progress indicated by shading of task bars in
proportion to Percent Complete
16Gantt Chart
17Setting up a Gantt Chart
- H must be completed before
- I and J can be started
- J must be completed before
- K,L and M can be started
- I must be completed before
- N, O and P can be started
18Task Relationships
- To be useful, schedule must show task
relationships - Earlier tasks that must be finished prior to
starting follow-on tasks - Precedence Relationships
- Common Task Relationships
- Start/Start
- Finish/Start
- Finish/Finish
19Setting up a Gantt Chart (Continued)
20Schedule Baseline
- After Contract Award, all Sub Project Managers
change their Work Packages to reflect the latest
knowledge - Design Changes
- Schedule Changes
- Project manager Reviews/Approves all schedules
- Schedules are placed under formal revision
control - Any changes made to schedule must be approved by
PM and Customer - Schedule is Updated from that point forward
21Updating of Gantt Charts
- Review date is indicated by a vertical line on
chart - Tasks are blackened to a bar length that is
equal to the Percent Complete of the task - Update procedure allows a manager to visualize
task status - Tasks completed early
- Tasks scheduled to be complete, but are now late
- Tasks that have not started, but should have been
initiated - Tasks that are on schedule
22Gantt Chart for Work Progress
23Percent Complete
- All tasks must be Measurable
- Measurable means that the Work Package Manager
must be able to assess how far along a given
task is at the time of the Project Review - Generally based on engineering judgment
- Must be objective, not subjective
- How Far Along is essentially Percent Complete
- Be careful about Thermometer Charts
24Gantt Chart for Weekly and Cumulative Expenses
25Schedule Hierarchy
- In order to avoid confusion, schedules are
provided to varying levels of detail - Rolling Up tasks into Summary Tasks for each
Work Project - Level of detail depends on the reviewer
- Must establish a formal relationship between
schedules - Similar to WBS Indenturing
- Formally controlled via the PMS Procedures
26Schedule Hierarchy Example
27Multilevel Schedule
28Gantt Chart Showing Work Progress (Computer
Generated)
29Gantt Chart Showing Multilevel Schedule (Computer
Generated)
30Disadvantages of Gantt Charts
- Task relationships are not easily displayed
- Effect of task delay is not easily seen
- Problem gets worse with project complexity
- These problems resulted in the development of
schedule networks - Covered in the next two lectures
- This deficiency has been largely overcome by the
use of micro-computers - Gantt vs. Network view of data
31Homework Assignment Preview
- Construction Project
- Garage with workroom
- 30 feet X 40 feet
- Develop Cost Estimate
- Use subset of information provided in Module 8
- Develop Schedule
- Provide logical relationship of tasks
- Assign Task Duration
- Assign manpower by labor grade
32Homework Assignment Preview (Continued)
- Develop Manpower Curve
- Use Microsoft Project
- Due 22 February (Thursday)
- Homework value 50 Points
33Next Lecture
- Read Nicholas Chapter7
- Install Microsoft Project
- Save Files of following Questions for future use
- Work Review Questions 6.17, 6.20, 6.22, 6.23,
6.25,6.26, 6.28, 6.29