Title: "A Comprehensive Balance Sheet
1"A Comprehensive Balance Sheet for Nuclear Power
Assessment. Christopher E. Paine,
Director Nuclear Program Natural Resources
Defense Council, Inc. Washington. D.C.
Presented at the The International Meeting
onNuclear Energy and Proliferation in the Middle
EastAmman, Jordan June 22-24, 2009
2- The positive attributes include
- Reliable generation of electricity IF the plant
is properly built and maintained - Low-carbon electricity (but not zero emissions
when total cradle-to-grave life cycle is
considered) - Reliable and plentiful fuel supply available at
predictable cost under long-term contracts - Fuel is a small fraction of total cost
3- NUCLEAR BENEFITS (cont)
- Low-cost generation once the initial capital
costs are amortized - A long operating life (40 60 years) if plant
is properly built and maintained, including
necessary costly capital additions, such as steam
generator replacements - Low health impacts from routine plant emissions
- A source of electricity that is typically
hardened against severe weather events (but
necessary external support and transmission links
may not be as well protected)
4Negative nuclear power attributes include
- Very high capital costs, on both a per-project
and per-kilowatt-of-new-capacity basis - Large technical and industrial barriers to
entry - these may be overcome by reliance on foreign
suppliers and technical experts, but such
dependence could limit national independence and
economic opportunity for the majority of the
population. - Cost-effective power currently available only in
very large, inflexible increments (e.g.1000-1600
MW), requiring costly transmission upgrades in
most developing countrie (smaller
grid-appropriate reactors may be commercially
available in 5 -10 years) - Lengthy nuclear project development/construction
timeframes, 7-12 years, compared to 2-5 years for
wind and solar projects.
5Negative nuclear attributes, cont
- Costly spinning reserve requirements for
replacement power in the event the reactor goes
off-line this problem will be particularly
acute in developing countries without significant
excess generating capacity in their electrical
grids - A requirement for continuing public subsidy costs
(for safety and environmental regulation,
security, peaceful-use safeguards, and waste
management) - Continuing nuclear accident risks, including a
small probability of a very high-consequence
event - Ongoing environmental requirements and costs for
spent-fuel management and eventual disposal, for
low-level nuclear waste disposal, and for
reconversion or recycling of uranium hexafluoride
tails from the enrichment process
6Negative attributes, cont
- Environmental harms from uranium mining milling
(in the case of nuclear power in the Arab Middle
East, these harms would likely be displaced to
other regions, e.g. Niger, Canada, Kazakhstan) - In-Situ Leach (ISL) solution mining of low-grade
domestic uranium deposits in arid countries, such
as Jordan, can severely damage the mined aquifer
a big risk in desert nations. - If uranium fuel is not sourced domestically, the
problem of foreign fuel dependence remains. - Safe operation of nuclear power plants requires
an industrial safety culture and effective
regulation now lacking in many countries . If
this deficit leads to an accident, it could
jeopardize the operation of similar reactors
everywhere. - Nuclear power has high physical security
requirements and costs in comparison to other
generating technologies.
7Negative attributes, cont.
- Nuclear power is a difficult technology for arid
inland environments where it normally requires
massive freshwater withdrawals, massive thermal
discharges, and large evaporative losses for
these reasons, nuclear power stations in the
Middle East will presumably be limited to
sea-coast locations - Seismic risks further constrain the geographic
scope and increases costs of deployment in
certain areas - Nuclear facilities can be magnets for attack in
conflict-prone regions or in the event of war - In the current state of world politics, a big
nuclear build-out supported by autonomous
national fuel-cycle facilities would create
regional and global insecurity and pose a severe
road block to global nuclear disarmament.
8Conclusions Regarding Nuclear Power
- When all is said and done, if one discounts the
technical and geostrategic mystique surrounding
nuclear power, it is really nothing more than
another way to boil water - A costly way to boil water new-build nuclear is
currently expected at 0.12 to 0.21 per kilowatt
hour (kWh) in the U.S.A and Europe - Nuclear power is clearly an option for ME nations
that can meet the steep up-front capital costs,
BUT it should be rigorously evaluated on economic
and environmental grounds against an integrated
portfolio consisting of - Massive application of energy efficiency for
demand reduction - CSP, CPV, and wind, firmed up by geothermal and
selective use of central station CCGT and
distributed High-Temperature Direct Fuel Cells.
9Cost-effective energy alternatives to nuclear
power in the Middle East
- Concentrating Solar Thermal Power (CSP) with
thermal storage and Geothermal for
round-the-clock base-load applications - Wind-Power, Solar Photovoltaic (PV), and Solar
Concentrating Photovoltaic (CPV) for intermediate
and peak-load utility applications, and
distributed Building Integrated PV (BIPV) for
home and commercial applications - Efficient Natural Gas Combined-Cycle (NGCC) and
high-temperature Direct Fuel Cell (DFC) to
backstop and firm-up increased market
penetration of all forms of renewable energy - Increased Energy Efficiency, including tough
Efficiency Standards for buildings and electrical
equipment and Distributed Solar Thermal rooftop
systems for domestic hot water and industrial
process heating and cooling, drastically reducing
consumption of bottled propane/natural gas for
these uses, freeing existing supplies to back
increased market penetration of renewables - Electricity market reforms to shift producer
incentives toward investment in energy efficiency
and independent clean energy production an
open bid process for grid connection and supply
10A 55-kilowatt solar powered pumping station was
brought online in Egypt in 1913.
11How big is the Solar Resource of the Arab League
Nations?
- HUGE for example, with current technology, under
3 of the land area of Morocco could power the
entire European grid.
12(No Transcript)
13(No Transcript)
14(No Transcript)
15What would it take to make Jordan 100
self-sufficient in its electricity supply using
CSP?
- Jordans total electricity consumption (2007)
13,000 GWh/yr - Direct solar radiation in SE Jordan averages
about 2600 kWh/m2/yr 2600 GWh/km2/yr - 13,000 GWh/yr / 2600 GWh/km2/yr 5 km2
- Assuming solar thermal-to-electric conversion
efficiency of 0.25 - 5 km2/0.25eff 20 km2
- Allow 50 in area for spacing between mirrors,
balance-of-plant, roads, security perimeter 20
km2 x 1.5 30 km2 - Assuming average solar plant availability is 29
of its nameplate capacity (about 7 hours of
usable daylight per day) 30 km2 / 0.29 103 sq.
km. are needed to achieve CSP output of 13,000
GWh/yr. -
16CSP Land Requirements(Capacity Basis using
eSolar Corp. Data)
- One eSolar CSP module rated at 46 MWe needs 0.65
sq.km - Jordans installed nameplate capacity (2007)
2019 MWe - 2019 MWe/46 MWe 44 eSolar CSP modules
- 44 modules / 0.29 capacity factor 152 eSolar
CSP modules - 152 CSP modules x 0.65 sq. km/module 99 sq. km
- Rough Conclusion An unused desert area measuring
10 km x10 km one-tenth of one percent of
Jordans total land area dedicated to CSP
systems could power the entire electrical grid,
assuming a portion of this energy can be stored
for dispatch to the grid in the evening/night
time hours while simultaneously meeting peak late
afternoon loads.
17eSolar Scalable CSP
18(No Transcript)
19(No Transcript)
20Torresol Energy Power Tower(Joint Venture
between Abu Dhabis Masdar (60) and Spains
Sener (40)
21(No Transcript)
22 The US Department of Energy (Sandia and NREL
Laboratories) stated in 2007 ... existing CSP
plants produce power now for as low as 12 per
kilowatt hour (12/kWh) (including both capital
and operating costs), with costs dropping to as
low as 5/kWh within 10 years as technology
refinements and economies of scale are
implemented. Independent assessments by the World
Bank, ADLittle, the Electric Power Research
Institute, and others have confirmed these cost
projections. The Trans-Mediterranean CSP report
from the German Aerospace Centre (DLR), published
in 2006, gives the cost of electricity from CSP
plants in Spain as 15 cents per kWh, falling to
about 7 cents per kWh by 2020 (Figure 2-24, p.
63). At that time, it is anticipated that
electricity imported from CSP plants in North
Africa will be about 5.5 cents / kWh, mainly
because North Africa has more sunshine.
23Final Thoughts and a Policy Recommendation
- Just because heavily state-subsidized nuclear
companies in France, Russia, Japan and Canada
want to sell ME countries huge costly nuclear
reactors and fuel services, does not mean that it
is in your national economic or political
interest to buy them - As a matter of rational economic choice, given
the Arab worlds immense CSP potential, you are
not likely to need nuclear energy to power a
low-carbon economy rigorous comparative life
cycle analysis of low-carbon alternatives is
essential! - Recommendation Vigorously pursue building energy
efficiency standards/retrofits and clean
renewable energy opportunities, and wait 7-10
years to see whether more efficient, flexible,
and cost-effective nuclear reactor designs emerge
from the nuclear renaissance.
24Edisons View in 1931