Title: Material Availability and Infrastructure Challenges
1Material Availability and Infrastructure
Challenges
- ICAAP 08 Plenary Session
- Planning for New Plant Construction
- June 9, 2008
- Ed Cummins
- VP Regulatory Affairs
- Westinghouse Electric Co.
2The Demand for Nuclear PowerAP1000 Worldwide
- AP1000 Design Certification Approved by the NRC
on 12/30/2005 - 4 AP1000 Units contracted in China Haiyang
Sanmen - 5 AP1000 Combined Operating Licenses submitted to
date - South Carolina Electric Gas Co. signed letter
of intent with Westinghouse Shaw to purchase
long lead materials for 2 AP1000s - Progress Energy Florida signed letter of intent
with Westinghouse Shaw to purchase long lead
materials for 2 AP1000s - Southern Company signed EPC contract for 2
AP1000s - South Africa tendered Submission C
(Westinghouse, Murray Roberts, Shaw) proposal
for three AP1000s(competition 2 EPR) - UK Jan 08 Gordon Brown gives the go ahead for
Nuclear, potential for up to 20 GW of nuclear.
3Best Solution for New PlantsSimplification
- Simplicity in
- Design
- Safety
- Construction
- Procurement
- Operations
- Maintenance
4Design SimplificationFewer Components
5Construction SimplificationModularization
6Infrastructure Challenges
- Focus of industry attention changes with time.
- Recent Past Focus on engineering and regulatory
resources (some residual challenges remain) - Current Focus Supply Chain
- Next Focus Project management and construction
craft - Future Focus Startup and plant operations
A healthy focus on infrastructure challenges
mitigates the risks and impacts of the challenges.
7Westinghouse Challenge.
8What is Westinghouse Purchasing?Equipment/Compone
nts/Commodities
9Supply Chain ChallengesHigh Level Concerns
- The Nuclear Industry is competing for limited
capacity with other industries - Fossil Fuel
- Petrochemical
- Does the supply chain consider the renaissance
real? - The risk and cost of investment for suppliers
must be addressed
10Supply Chain ChallengesSpecific Concerns
- Status of component design
- Design finalization
- Component design delay in entering manufacturing
process - Raw material supply
- Extended lead times
- Price fluctuations
- Sub-component supply (i.e. forgings, subsystems,
tubing) - Capacity constraints
- High cost to increase capacity
- Long lead-time for capacity expansion
11Supply Chain ChallengesSpecific Concerns
Contd.
- Lack of specialized manufacturing workforce
equipment/machinery - Translating orders into factory instruction for
Procurement, Manufacturing and QA Procedures - No or limited capacity
- Long lead-time to process equipment/ramp-up
production - Limited Nuclear Grade Suppliers
- Certification has lapsed
- Loss of nuclear grade discipline
12Westinghouse Supply Chain Management Actions to
Support New Plant Build
- Identify Supply Chain Risk and Implement
Mitigation Plans - Detailed risk analysis of the AP1000 systems and
components - Working with NEI to identify risks and develop
mitigation plans - Identify the Right Suppliers
- Supplier Evaluation Process
- Approved Supplier List
- Early Customer Engagement
- Assure Capacity
- Sub-component reservation agreements
- Master agreements to reserve capacity
13Summary
- Make the Nuclear Industry the customer of
choice for critical suppliers - A balanced sharing of cost, risk and benefit
- Communicate to the supply chain, the enormous
gain to be realized by the nuclear renaissance
and acknowledge and deal with the risk and cost
at all levels of the supply chain - Owners, A/Es and NSSS Suppliers must demonstrate
a commitment to the Nuclear Renaissance. - Supplier capacity expansion depends on realistic
assessments of the future scope of supply. - Mitigation of future infrastructure challenges
will be addressed when the commitment and focus
occurs.