Title: Contract Review
1Contract Review
Contract Review
Approved for Public Release
2- A COMPLETE AND THOROUGH CONTRACT REVIEW IS THE
KEY TO SUCCESSFULLY PROVIDING A COMPLIANT END
PRODUCT
Approved for Public Release
3Topics
- Request for Quote (RFQ) vs. the Purchase Order
(P.O.) and supplemental changes - Purchase Order review
- Issues
- Who should perform contract review
- Process
Approved for Public Release
4Request for Quote (RFQ) vs. the P.O. and
Supplemental Changes
RFQ vs. PO
- RFQ (Request for Quote)
- Draft P.O.
- Issued P.O.
- Supplemental Changes
Approved for Public Release
5Topics
- Request for Quote (RFQ) vs. the Purchase Order
(P.O.) and supplemental changes - Purchase Order review
- Issues
- Who should perform contract review
- Process
Approved for Public Release
6Purchase Order Review
P.O. Review
Supplier Number
Supplier Company Address
EB Buyer Contact Information
Approved for Public Release
7Purchase Order Review
P.O. Review
Terms Conditions
Delivery Commitment
Inspection Requirements
Approved for Public Release
8Purchase Order Review
P.O. Review
Approved for Public Release
9Purchase Order Review
P.O. Review
Approved for Public Release
10Purchase Order Review
P.O. Review
Approved for Public Release
11Purchase Order Review
P.O. Review
Documents
Standard Clauses
Remarks
Buyer Standard Messages
Approved for Public Release
12Topics
- Request for Quote (RFQ) vs. the Purchase Order
(P.O.) and supplemental changes - Purchase Order review
- Issues
- Who should perform contract review
- Process
Approved for Public Release
13Issues
Issues
- Unapproved procedures
- Non conforming materials
- DFAR
- Material specification revisions
- Missing testing NDT, first article, heat
treatment, mechanical - Incorrect lubricant
- Certification records
- Lack of flow-down to subtiers
- Material marking
Approved for Public Release
14Topics
- Request for Quote (RFQ) vs. the Purchase Order
(P.O.) and supplemental changes - Purchase Order review
- Issues
- Who should perform contract review
- Process
Approved for Public Release
15Who Should Perform Contract Review?
Contract Review
- Contract Reviewers Need
- Experience
-
- Education / Training
- Attention to detail
- To be from each of the affected areas (e.g.
Engineering, Quality, Operations)
Approved for Public Release
16Ground Rules for Reviewers
Contract Review
IN ALL CASES THE PURCHASE ORDER IS THE
CONTROLLING DOCUMENT AND TAKES PRECEDENCE OVER
ALL OTHER DOCUMENTS, EITHER WRITTEN, IMPLIED OR
SPECIFIED.
Approved for Public Release
Approved for Public Release
17Ground Rules for Reviewers
Contract Review
VPAR
Approved for Public Release
18Review P.O. for Quality System Requirements
Contract Review
- Quality System Requirements include
- EB2678 (Quality Control Requirements for Procured
Material) - MIL-Q-9858 (Quality System Requirements)
- Mil-I-45208 (Inspection System Requirements)
- Mil-Std-45662 (Calibration System Requirements)
- ISO Systems (Allowed per EB 2678 with
modifications)
Approved for Public Release
19Topics
- Request for Quote (RFQ) vs. the Purchase Order
(P.O.) and supplemental changes - Purchase Order review
- Issues
- Who should perform contract review
- Process
Approved for Public Release
20Contract Review Technical Elements Must Consider
Process
- All Referenced documents and revisions (e.g.
Dwgs., Specs, ERs, DRNs, VIRs), Standard Clauses
and Modifications - Testing (e.g. 1st Article, Pre-production,
Production, etc.) - Special processes and procedure approvals (e.g.
Forging sketches, NDT and welding) - Quality System Requirements
Approved for Public Release
21Contract Review Technical Elements Must Consider
Process
- Assembly requirements
- Cleanliness
- Special Marking
- Special Certifications / Documentation / Test
Reports - Packaging
- Customer (EBSI) and Government (GSI) inspection
requirements
Approved for Public Release
22Documents to Review
Process
- RFQ (Request for Quote)
- Draft P.O.
- Issued P.O.
- Supplemental Changes
DO NOT ASSUME THAT OUR USE OF YOUR PART NUMBER
MEANS THERE ARE NO MODIFICATION
Approved for Public Release
23 Review Contract Changes in a Timely Manner
Process
- Supplements, Modifications
- Review to existing order in progress, perform
complete review against prior order - Does it affect work in progress or completed work
not yet shipped? - Resolve issues with customer via formal
contractual correspondence
Approved for Public Release
24Thorough Contract Review Includes All Applicable
Documents
Process
- Review all applicable documents (e.g.
Specifications, Drawing, VIRS, and Engineering
Reports (ERs), etc) - Review all Standard Clauses
- Coded Notes
- Beware of revisions
- Review Remarks Section of P.O.
- Additional modifications and technical
requirements - Testing, acceptance criteria, mods to documents
Approved for Public Release
25Which Documents Apply?
Process
Approved for Public Release
26Which Documents Apply?
Process
Approved for Public Release
27Base Material Requirements Must be Understood
Process
- DFAR compliant specialty metals
- Specification and revision (Spec. Effectivity)
- Alloy, condition, finish, heat treatment
- Testing chemical, mechanical, special processing
(e.g. passivation) - Test and inspection certifications
Approved for Public Release
28Ensure All Testing Requirements are Addressed
Process
- Special fixturing or test setup needs
- Required test procedures and revision
- Test report requirements
Approved for Public Release
29Special Processes(e.g. 1ST Article, NDT,
Welding)
Process
- Special Processing Requirements
- Welding, Nondestructive Testing (NDT)
- Heat Treatment
- 1st Article Testing
- Customer Approval of processes or procedures
- Vendor Procedure Approval Requests (VPARs) are to
be used to obtain customer approval prior to
processing, including subtier supplier procedures
ENSURE NECESSARY CUSTOMER APPROVALS OF PROCESSES
OR PROCEDURES IS OBTAINED
Approved for Public Release
30Ensure All Assembly Requirements Have Been
Addressed
Process
- Special Lubrication Requirements
- Special Torque Requirements
- Special Marking
- Special Tooling
- Assembly Records
Approved for Public Release
31Ensure All Cleanliness Requirements Have Been
Addressed
Process
- S. C. 16-16 (Steam Plant Cleanliness)
- MIL-STD-767 (Control of Hardware Cleanliness)
- MIL-STD-1330 (Precision Cleaning and Testing of
Shipboard Oxygen-Helium, Helium-Oxygen, Nitrogen,
and Hydrogen Systems) - MIL-STD-1622 (Cleaning of Shipboard Compressed
Air Systems) - Critical Hydraulic Components Cleanliness (SC
16-21)
Approved for Public Release
32Special Marking Requirements Can Include Hardware
and Software
Process
- Traceability (Lot code), P.O., Item Number
Identification - Marking may be required on material,
- certification, and packaging
- NDT Marking
- Level 1 Material Designators
- Flow Arrows, Pressure Rating, etc.
Approved for Public Release
33Special Certification, Documentation and Test
Reports
Process
- C of C
- Assembly Records
- Mercury Free Statement
- Vendor Procedure Approval Request (VPARs)
- Shelf Life Certification for Non-Metallics
- Cleanliness Certification
- Test Reports
- Weld / NDT Records
- Repair or Replace Certification
Approved for Public Release
34Ensure All Packaging Requirements Have Been
Addressed
Process
- Warning Labels
- Preservation
- Protection of Noise Critical Equipment
- Electrostatic Discharge (ESD ) Packaging for
Electrical Components - Seals and Capping
Approved for Public Release
35Customer (EBSI) and Government (GSI) Inspection
Requirements
Process
- Advanced notification and location
- Identification of hold points (i.e. in the
production router)
Approved for Public Release
36When Contract Requirements are UnclearGet
Clarification!
Process
- Preferably during the RFQ stage
- Have the contract amended by VIR or PO
supplement. Verbal agreements are not recognized
by EB inspection - Points of Contact
- EB Material Management (Buyer)
- EB Supplier Quality
Approved for Public Release
37Conclusion
Conclusion
- Success or failure is in the details
- Never consider something in the contract of being
of little value or importance because - Trifles are details. Details make perfection and
perfection is no trifle - Benjamin Franklin
Approved for Public Release