Chiller Optimization Workshop September 18, 2003 - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Chiller Optimization Workshop September 18, 2003

Description:

Hydraulic pumps. Process loads with high leaving. water temperature (70 plus) ... Engineering study required. Explore complimentary ECMs. Incentive Programs ... – PowerPoint PPT presentation

Number of Views:228
Avg rating:3.0/5.0
Slides: 28
Provided by: newengland2
Category:

less

Transcript and Presenter's Notes

Title: Chiller Optimization Workshop September 18, 2003


1
Chiller Optimization WorkshopSeptember 18, 2003
  • Fran Boucher
  • Senior Energy Engineer

2
New England Territories
3
Who is here today?
o
  • Process / industrial
  • Institutions
  • Office and commercial space
  • Up to 100 Tons
  • 100 to 300 tons
  • Over 300 tons

4
Utility Conservation Programs
  • Utilities provide
  • Technical Assistance
  • Incentive funds
  • Customers pay of cost

5
Utility Conservation Programs
  • Types of Projects
  • New construction
  • New equipment loads
  • Replacement for efficiency
  • Replacement due to age

6
Utility Conservation Programs
  • NOT JUST CHILLERS
  • Cooling towers
  • Optimization controls
  • Base load chiller
  • Pumping
  • Reducing load Lighting efficiency, etc.
  • Eliminating inappropriate loads

7
Utility Conservation Programs
  • Inappropriate process chiller loads
  • Air compressors
  • Hydraulic pumps
  • Process loads with high leaving water
    temperature (70plus)

8
Personal Care Products Manufacturer
Example 1
  • Planned to add an additional 400 ton chiller
  • Used load reduction through our program
  • Avoided purchase of chiller
  • Cut projected annual electric cost by 201,500!
  • Utility incentive over 700k
  • Payback as low as two years!

9
Printed Circuit Board Manufacturer
Example 2
  • Installed heat exchanger to pre-cool with city
    water
  • Eliminated need for 25 ton chiller addition
  • Shut chillers down all winter
  • 37,000 Incentive
  • 2 year payback
  • Saved annual 26,900 dollars electricity costs

10
Massachusetts Manufacturer
Example 3
  • Inappropriate use of Chilled water
  • Replaced 75 Hp water cooled air compressor. Now
    air cooled
  • Compressor cooled with chiller
  • Saved 15,800 per year on chiller operation
  • Payback 2 years

11
Incentive Programs
  • Two paths for Chillers
  • Prescriptive
  • Simple, no engineering
  • Fits chiller only projects
  • Custom
  • Engineering study required
  • Explore complimentary ECMs

12
Incentive Programs
  • Two Custom Programs
  • Retrofit (Energy Initiative)
  • New Construction/ New Equipment / End of Life
    (Design 2000plus)

13
Incentive Program
  • Retrofit (Energy Initiative)
  • Pay 50 of FULL cost
  • 2 year payback limit
  • Examples
  • Load reduction
  • Inappropriate use
  • Waterside economizer
  • New controls

14
Incentive Program
  • New Facility/Equip. (Design 2000plus)
  • Pay 75 of Incremental Cost
  • 1.5 year payback limit
  • Examples
  • New / replacement chillers
  • Beyond code improvements
  • Variable pumping
  • More efficient towers
  • Optimization controls

15
Incentive Program
  • Technical Assistance
  • Modeling key to optimize chiller
  • TA Study for modeling
  • Solid numbers for management
  • Program Volume
  • 25 to 30 chillers a year

16
Comprehensive Chiller Program
17
Comprehensive Chiller Program
  • Premium Chiller Replacement Program
  • Eligibility
  • Replacement of 300 ton or larger chiller
  • Three demand side measures
  • All lighting upgraded
  • Complete energy model
  • Not for industrial refrigeration
  • Reward 90 or 1 yr. payback
  • Note Mix of incremental and full cost

18
Hospital Opportunities
  • 2 Comprehensive Chiller Projects in 2003
  • Hospital A
  • Lighting, EMS, misc. DX to CHW conversion
  • 240,000 incentive
  • 66,000 electric savings
  • 1 yr. payback (incremental cost)
  • Hospital B
  • 750,000 Incentive
  • lt 2 yr payback

19
Comprehensive Chiller
  • Case Study Plastics Manufacturer
  • Situation
  • Immediate need to replace 1 of 2 cooling towers
    (Design 2000plus)
  • Plan to install free cooling for air
    compressors (payback under 2 years)
  • Available incentives lt50,000
  • Their budget 200,000
  • Plan to replace 1 old 250 ton chiller 1 year
    later

20
Comprehensive Chiller
(Continued)
  • Revised Approach
  • Replaced 2 cooling towers
  • Added waterside economizer to whole plant
  • Replaced oversized CHW pumps
  • Several VSDs 30 Hp. each
  • EMS Chiller plant automation
  • New 400 Ton chiller

21
Comprehensive Chiller
(Continued)
  • Project cost 589,770
  • Utility Incentive 393,081
  • Customers cost 196,698
  • Still under 200k budget!
  • Electric Savings 87,372
  • Simple Payback 2.3 years
  • NO BRAINER!!!!!!!!!!!

22
Light Commercial Case Study
  • The Building (New Construction)
  • 60,000 SF
  • Light Commercial
  • 5 days, 12 hours/day
  • 250 ton peak load 277,000 Ton hours
  • Customer Criteria
  • Efficiency / value
  • Redundancy preferred

23
Chiller Options
(Continued)
  • Air Cooled Code min. Non-qualifying
  • Single water cooled screw Qualifying
  • Two water cooled screws Qualifying
  • Centrifugal Qualifying
  • VSD centrifugal Qualifying
  • All 270 tons except 3 with 2_at_ 135 tons

24
Chiller Comparison Case Study
Cost is net cost compared to Air Cooled chiller
base case
25
Case Study Wrap Up
  • Modeling is the key to a good decision
  • Your results likely different
  • We assist with the modeling
  • Single water cooled screw saves 5000 per year
    and 1.5 year payback even without an incentive
    program!
  • VSD economics improve with longer hours and
    larger machines

26
Energy Conservation Opportunities
  • Favorable Opportunities
  • Long hours multiple shifts and weekends
  • Year-round chiller load
  • Process and computer room loads
  • Multiple chillers without automation controls

27
Utility programs are your friend!
Thank you!
Fran Boucher, CEM 508-421-7299
Write a Comment
User Comments (0)
About PowerShow.com