Title: Prsentation PowerPoint
1Lessons learnt from the French Nuclear Program
ICAPP 2007 Nice May 2007
Georges Servière Nuclear Engineering Division
EDF
2CONTEXT OF FRENCH NUCLEAR PROGRAM
50s and early 60s ? hydro-power program Late
60s ? coal fuel-oil program ? nuclear
variety of reactor types heavy water Brennilis
(1967) gas-cooled Saint Laurent 1-2, Chinon
2,3, Bugey 1 fast neutron Phénix no
standardization developed by French Atomic
Energy Commission 1969 ? PWR Franco Belgian
Plant of Tihange 1 ordered 1970 ? Beginning of
construction of Fessenheim and Bugey 1973 ?
Oil crisis / Launching of the French Nuclear
Program 58 PWR units Superphénix
(sodium cooled breeder)
34 900 MWe class reactors CP0 - CP1 -
CP2 20 1300 MWe class reactors P4 P?4 4
1450 MWe class reactors N4
2
3History Age of Series 01.01.07
3 different series 900 MW PWR (34 units), 1300
MW PWR (20 units), 1500 MW PWR (4 units)
25 years
19 years
9 years
Age since 1st connection
5 to 8 units/year
4The French Nuclear Program
SFR Rapide Sodium
PWR
HWGCR Eau Lourde
Gaz-Graphite UNGG
5Construction RythmsUSA-France
30
6 Fold
60 of installed power
6Financing the French Program
533
500
TWh
52
Nuclear made it for and was financed by both
Substitution Growth
400
416
300
200
Nuclear
Fossil fuels
100
65
Hydro
0
1950
1960
1970
1980
1990
2000
7A few reasons for a success story
- A "no alternate choice" context
- No Coal, no Oil, no Gaz, no more Hydro, ....
- An existing strong nuclear industrial context
- EDF, CEA, Framatome
- Industrial shift to PWR before the oil crisis
- A continued political will
- A clear resolute energy policy
- Supported by the successive governments
- Limited opposition
- Clear benefits from
- Standardized nuclear fleet
- Concentration of competencies
- High level of control by Nuclear Safety
Authority
8A few reasons for a success story
- To achieve such a program
- In addition to the context
- Robust proven designs
- Industrial capabilities
- Engineering, Construction Project Management
skills within EDF Owner/Operator - Necessity for standardisation
- We could not afford managing different types of
units - made possible thanks to a (almost) unique
decision maker
9Series effects
THE SERIES EFFECT A KEY FACTOR FOR A
SUCCESSFULL NUCLEAR PROGRAM
10Creusot workshop for vessels in the 70's
Standardisation in Manufacturing
Creusot Workshop in the 70's
- Standardisation
- Benefits to
- Quality
- Schedule
- Costs
11Gravelines NPP6 identical 950MWe Units
Standardisation for Construction Commissioning
Paluel NPP 4 identical 1300MWe Units
- Standardisation
- On each site
- Between sites
12Unique Experience Interfacing Design Operation
58 nuclear power plants give EDF the equivalent
of more than 1300 reactor-years of experience
13- Standardisation is not a so simple concept
- Design
- Overall Management Procurement
- Manufacturing
- Construction Commissioning
- Operations
- Standardisation is intended to save money and/or
improve Safety - Standardisation has to be tuned for those goals
14INDUSTRIAL ORGANIZATION OF EDF FOR DEVELOPMENT OF
THE FRENCH NUCLEAR PROGRAM
- No turn key basis, but allotment (as for
hydro and classic thermal program) - EDF, Architect Engineer, masters all the process
- Plant divided into sub assemblies (about 400
contracts) civil works, electromechanical
systems and components, IC, Design, - All sub assemblies offered to competition,
except (so far) - turbo generator ? Alstom
- primary circuit (plus some connected circuits) ?
Framatome - Competitive prices
- Partnership for long term with sub contractors
as far as possible one contract for all units of
a series or sub-series -
- The direct involvement in Design and the
allotment system is not free (cost of EDF
Engineering) nevertheless, for a large fleet of
reactors, this organization saves money - The issue is who benefits from standardisation
and who decides its extent ?
4
15STANDARDIZATION OF ENGINEERING AND DESIGN
- 2 examples of limitations for standardization
over a long period for a significant number of
sites - different site conditions
- technological progress
- 1- Different site conditions
- geology, seismicity, human geography, industrial
environment, heat sink, ... - if the design is adapted to each site ? no
standardization - if the design bounds all sites ?
standardization but maybe anti economical - The solution chosen by EDF
- To define a standard that can be adapted to each
site with a minimum of modifications,
consistently with a careful selection of sites. - Practically, a small number of site adaptations
- foundations
- cooling water systems
- connection to transmission lines
- etc
6
16STANDARDIZATION OF ENGINEERING AND DESIGN (2)
- 2 - Technological Progress
- If the design is stabilized without any changes
over a long period - good for standardisation
- not so good to accomodate technological progress
or experience feedback from Design, Construction
Commissioning, Operation - The solution chosen by EDF
- different overlapping plant series, each limited
in time, to allow for main design changes - CP0 CP1 CP2 for 900 MWe plants
- P4 P?4 for 1300 MWe plants
- N4 for 1450 MWe plants
- Limited de-standardization, to allow for
manufacturing changes
7
17POSSIBLE DRAWBACKS OF STANDARDIZATION
- Some other limitations to total standardization
- aggregates for concrete
- detailed chemical composition or manufacturing
process - ...
- The risk of standardization the generic
defects - Some examples vessel heads
- steam generators
- Backfitting associated with generic defects
only a few examples - vessel heads all vessel heads replaced
- steam generators progressive replacement of
SG with Inconel 600 tubes - In fact, a certain level of destandardization
prevented EDF to replace all steam generators - Backfitting expenses associated to generic
defects so far less than 10 of construction
cost savings due to standardization
10
18BENEFITS OF STANDARDISATION PROGRAM POLICY
- Standardisation is intended to save money and/or
improve Safety - and has to be tuned for those goals ...
- Most of the benefit on manufacturing is reached
at the 5th-6th unit
10
19BENEFITS OF STANDARDISATION PROGRAM POLICY
- Standardisation is intended to save money and/or
improve Safety - and has to be tuned for those goals ...
- Most of the benefit on manufacturing is reached
at the 4th-6th unit - There is a real effect for site activity, from
identical units on one site, and on sites if
teams can take over - ? 8-12 months between 2 units on the same site
- ? careful planning sharing between 2 sites
(or more) - This part of the benefit is more largely
dependant on the program size - Clear benefit in terms of relations with Safety
Authority - ? But probably implies organized/collective
periodic safety reviews for a standardised series
with joint backfit, when there is not a unique
Owner/Operator - ? Clear international harmonisation will
certainly facilitate/enhance standardisation
benefit
10
20... for the future
- EDF intends to maintain a large proportion of
nuclear power, as it showed safe,
reliable and competitive for base load also for
some semi-base (load following mode) - EDF will follow the same principles for the Fleet
renewal, but with some adaptations - A smoothened construction rythm, with more time
between 1st Unit and following ones - Still an allotment of supply with call for bids,
but a smaller number of contracts - A strong Project Management, reinforced due to
the more complex procedures of all kind and a
more international context, ... - ..., which also has to include "public debate"
management capabilities, because it is now not
only part of the decision making , but also of
the project management itself
13
2120 years 2500 MWe/year
5000 MWe/year
A strategy to smooth investment
30 years 1700 MWe/year
The nuclear renewal in France has to be
smoothened . but we must be ready to launch a
series by 2015
22A strategy to smooth investment and give
flexibility
A scenario for Renewal up to present level at
1700MWe/year
50 years avg.
23In summary
- After the oil crisis of 1973, France and EDF
launched a large nuclear program, totalling now
58 units. - The standardization and allotment policy
(implying strong architect engineering
capabilities) was very efficient to master the
construction rythm and to reduce costs. - In the future, EDF will maintain a high
proportion of nuclear. - Benefiting from the experience gained over the
past years, EDF is preparing the renewal of its
existing fleet, and possibly to face an increase
of demand
EPR Flamanville 3 construction will start very
soon Creation Decree issued April 2007
(COL) preliminary works underway first concrete
end of 2007.
18
2418