Measure A Facilities Oversight and Advisory Committee - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Measure A Facilities Oversight and Advisory Committee

Description:

Major additions at 3 high schools, 15 other schools upgraded, 3 schools still in ... 'Deferred' maintenance is really 'scheduled' maintenance of major systems ... – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 15
Provided by: cken
Category:

less

Transcript and Presenter's Notes

Title: Measure A Facilities Oversight and Advisory Committee


1
Measure A Facilities Oversight and Advisory
Committee
  • Annual report to the SRVUSD Board of Education
    12/04/07

2
Overview
  • Since Measure D (1998) almost 1 billion in new/
    upgrade SRVUSD school construction
  • Less than half from local bond elections
  • 560 million plus in developer funds/ fees
  • 220 million in state funding (more coming)
  • 166 million returned to developers (1992
    contract)
  • 8 new schools opened through 2007
  • Enrollment growth of 33 since 1997
  • Major additions at 3 high schools, 15 other
    schools upgraded, 3 schools still in process

3
Developer agreements
  • 1992 Dougherty Valley agreement
  • land, buildings, equipment and landscaping
  • Separate Shapell agreement Creekside
  • Results to date 6 new schools
  • 4 new elementary, 1 middle, 1 high
  • DV high school District-designed, constructed
  • Without agreements, major District impact
  • possible year round multi-track program

4
FOAC Facilities oversight and advisory committee
  • Measure A bond oversight per Prop 39
  • Public information, including annual report
  • Design/ cost recommendations
  • Measure A prioritization
  • Future facilities needs
  • Review of all District facility activities
  • All active construction sites and others with
    identified needs visited by Committee, met with
    District project management on site while
    students were in session.

5
2007 FOAC membership
  • March 22 2007 March 2009
  • Jeffrey Beadle Carolyn Degnan
  • Jay Bhalla Kari DeSoto
  • Don Birnbaum Traci Fraas
  • Barbara Brick Chris Kenber
  • Jonathan Buckley John Mascali
  • Clifford Buxton David Struck
  • Ed Chiverton David Yee

6
Measure A cost inflation
  • Measure A assumed 3 per year cost inflation
  • Construction boom grossly inflated costs for
    concrete, steel, copper, other materials
  • 260M project cost grew to 388M
  • Increases rational and justified if unwelcome
  • 64.5M in additional state funding offset to date
  • Total expenditure for Measure A now 343.6M
  • 44.5 million shortfall absent new state funds
  • Quality and standards maintained

7
Measure A prioritization Committee recommendation
  • Factors in order
  • Safety, student impact, , site equity
  • Projects already in design to be finished
  • Except Cal High gym modification (timing)
  • Projects yet to start
  • Modified if subject to later change
  • Portable replacement on hold
  • Technology upgrades to be completed

8
(No Transcript)
9
FOAC process
  • Master Program Budget key control report
  • Provides detail by project
  • Provides funding status by category
  • Tied to audit and financial reporting
  • Reviewed at every meeting in detail.
  • Clean audit reports (attached to report)
  • No material issues found
  • The Committee finds no material issues with
    planning, construction and financial management
    of Measure A and other facilities projects.

10
Future District needs
  • Site master planning key to next steps
  • SRVHS, Stone Valley, others
  • Construction needs at multiple campuses
  • Aging plant/ facilities (Golden View, Del Amigo
    etc)
  • Facilities program creates inequity
  • District standards/ current construction sites
  • Other sites not equal construction, hardscape,
    landscape, technology
  • Further bond will be required
  • Facilities program success drives positive vote

11
2006 FOAC recommendations
  • Mostly operational in nature
  • Met either directly or by alternatives
  • Except 6 and 10 -- deferred maintenance and
    communication
  • FOAC not an operational entity
  • Must not micro-manage Facilities
  • Must be satisfied that data supports oversight
  • We are.

12
2007 recommendationsDeferred maintenance
  • Term is misleading to public
  • Deferred maintenance is really scheduled
    maintenance of major systems
  • Protects investment in facilities
  • Consistently under funded state-wide
  • SRVUSD gap measured in millions
  • Last comprehensive update is dated 2004
  • Prop 39 allows deferred maintenance
  • Comprehensive, annual update essential
  • Show needs and funding gap

13
2007 recommendations Communications
  • Construction program a major success
  • All facilities constructed to high standards
  • Opened on time
  • Major asset to the community and its students
  • The public doesnt know the story
  • Major impact on next bond election
  • Need a proactive, multi-disciplinary
    communications program implemented now

14
Conclusions
  • FOAC report finds no material issues with
    planning, construction and financing of Measure A
    and other facilities projects
  • FOAC commends the Facilities organization for
    extraordinary progress in new/ upgrade facilities
    construction
  • FOAC believes additional facilities needs will
    require a new bond.
  • FOACs mission remains a work in progress