Title: US Participation in the LHC Hardware Commissioning
1US Participation in the LHC Hardware Commissioning
US LHC Accelerator Research Program
bnl - fnal - lbnl - slac
- Michael Lamm for the HC group
- 19 October 2004
2Hardware Commissioning Task
.to paraphrase the LARP Proposal. 2.1.1.
Hardware Commissioning
- HC not included in USLHC construction project
- US component builders most knowledgeable about
operation and integration of US deliverables
(best to help, have most to benefit from
experience) - Modest effort will significantly speed up
commissioning - Important feedback (to designer and builders)on
effectiveness of component designs (..e.g. 2nd
Generation IR) - Effort should continue into beam operation to
study issues such as component performance under
dynamic loads
3Components to be Commissioned in 5 IRs
In IR1,2,5, 8 Cryo, Powering, Vacuum etc. tied
into the sector
Other important components Hadron and neutral
absorber for IR1, 5(LBNL) Other separation
dipoles in IR 1,2,4,5,8 (BNL)
IR 2,8 only
4Hardware Commissioning History
- 2002 HC part of LARP baseline
- Summer 2003 HC part of approved LARP
- Effort 2 FTE/year
- Sept 2003 Port Jefferson LARP meeting
- Establish LARP HC group
- November 2003 Discussion with CERN about
Structure of US participation - Defining job types, length of stays, role in
commission - February 2004 Refine participation, begin to
recruit LARP participants, budget for 2004-6 - Present Understand time scale and scope of
participation in light of the emerging LHC HC
time line.
5CERN Installation and Hardware Commissioning
Milestones
- Major schedule revision is in the works
- Compressed installation and commissioning with
beam in 2007 - The LHC is committed to make every effort
require to provide colliding beams in the LHC in
the summer of 2007 - -Update on the situation of the QRL 20
September 2004 - Milestones
- Hardware Fitup (January-March 2005)
- First Inner Triplet Installation (Sept-December
2005) - Begin Hardware Commissioning (TBA)
- Sector Test (CANCELLED)
- Finish Commissioning (Summer 2007)
- First Circulating Beam (Summer of 2007)
6CERN Installation and Commissioning Org
- In the construction project US responsibility
ends with acceptance of deliverables. - LARP HC participation is through the CERN
Organization - Installation
- Installation is the responsibility of the CERN
project engineer Ranko Ostojic - Hardware Commissioning
- Coordinated by Roberto Saban through the hardware
commissioning team - Types of People needed
- Mechanical Engineers for Installation
- Cryogenic Engineers for Cryo Commissioning
- Magnet Physicists for Electrical and Powering
7How LARP Personnel Would Fit Into LHC
- Duration of Stays
- Short duration (2 weeks to 2 months) especially
during fitup and installation - Longer duration (at least 6 months but up to a
year or more) during commissioning
- Person would be part of the installation or
integrated into an equipment group participating
in the hardware commissioning
Note Scope of LARP has been focused on US
deliverables. Recently CERN has identified a
shortage of qualified engineers and physicist to
complete the formidable global HC. e.g.
global cryogenic system, power systems, quench
protection, controls They are requesting our
help!
8LARP Hardware Commissioning Tasks
- Participation can be summarized by 4 general
areas - Above Ground Fitup
- First and only chance to assemble prior to tunnel
- Installation
- Provide technical assistance to CERN installers
- Commissioning
- Active members, particularly in the cryo,
electrical, powering and protection - Oversight
- Planning is essential in shortened installation
and commissioning time frame
9(1) Mechanical Fitup
- Above Ground Mechanical Fitup
- Inner Triplet (D1,DFBX,Q3-Q1) does not include
TAS fitup - Time Frame January-March 2005 (approximate
duration 8 weeks) - Purpose of Test
- Assemble all pieces for one complete IR
- Mechanical fitup of interconnects
- Pipes adjustments to install length, dry fit
- Vacuum tests
- Shields, interconnect kits
- Magnets on alignment jacks
- Electrical continuity
- Exercise alignment (SSW?)
- Build DFBX Cable trays as per final installation
10Fitup Part II
- How are we preparing for this
- Developing detailed plan for interconnect
- 3-D model, drawings, parts list, procedures
- Generating parts and widgets for assembly
- Work with CERN to develop run plan for
installation - Level of effort
- 0.4 FTEs spread over the 3 labs.
- Mostly mechanical engineers
11(2) Installation
- Time Frame First sector TBA, sometime in late
2005?, Continuous throughout FY2006, 07? - Check mechanical/vacuum/cryo connections
- Check installation procedures
- Participate in electrical connections
- Review electrical and alignment data
- How we are preparing for this
- Writing interconnect assembly procedures etc.
- Through active participation in the Above Ground
Fitups - Level of Effort FY05-6-7
- 1 FTE spread over 3 labs
- 1/3 FTE on First sector
- Time distribution depends on on details of
installation schedule
12(3) Commissioning
- Time Frame Mid 2006? through end of 2007
- Purpose
- Once installation complete, all aspects of
bringing system to full operation. - How we are preparing for this
- Through reviewing CERN documentation on
Commissioning Test Procedures - By remotely following the HC planning progress
through the HC working group - By defining with CERN our roles in HC
- Level of Effort (mostly starts in FY06)
- Full time FTE physicist
- Cryo engineer (s) for IR cryo system and DFBX/HTS
. - 3.5 FTEs in FY06-07, probably one FTE in FY08?
13(4) Oversight
- Oversight
- Time Frame Now through Spring 2007
- Discussion with CERN on defining participation
both IR and new requests - Review installation and commissioning plans
- Recruit participants for long range stays
- Prepare budgets and schedule including Long Term
Living Arrangements - Level of Effort
- Mostly .1/institution/year
- Increase FTE in FY05 to insure hit the ground
running for Installation/commissioning in FY06
14Proposed FTE by Task
- Original Plan Calls for 0.5 FTE in FY04, 2 FTEs
in FY05-6-7, 1 FTE in FY08 - Total of 7. 5 FTEs
- Distribution Depends on CERN Schedule
- Late Start to Installation shifts Effort to
FY06-7 - Effort total slightly increases
15Proposed FTE by Institution
- Distribution in FY06-7 depends on home
institution of long term participants - Short term visitors are from all labs, local
experts in mechanical aspects of installation,
cryo engineering and magnet scientist - We have identified Fermilab Magnet Physicist for
FY06, Fermilab Cryo Engineer for FY06-7. Still
working on Physicist and Cryo engineers,
particularly in FY07, from all institutions.
16Proposed
- Again, effort shifted towards FY06-7 (relative to
original plans)
17Hardware Commissioning Conclusion
- HC is an important way for the US to contribute
to the LHC project - Inner triplet HC contribution is established
- Recent new requests in global commissioning could
greatly expand our role - We have presented our best estimate of required
costs for HC of inner triplet based on CERN
schedule - Plan for success (i.e funding and participation
is minimal and without contingency) - Does not include cost of participation in global
HC - Taking responsibilities in Inner Triplet Region
(an area in which the US has a large and unique
expertise) will help in the global HC (free up
CERN personnel, LARP IR personnel can take on
global jobs). - Major uncertainties
- Uncertainty in CERN schedule
- Cost of living in Geneva (addressed at LAPAC)
- Lining up the appropriate people at the right
time